SSE PLC (SSE.LN) said Friday that it has completed the construction, commissioning and energization of the new Caithness-Moray electricity transmission link in Scotland, its largest-ever single investment.

The energy company said the total spend on the project is expected to be 970 million pounds ($1.24 billion), within an initial budget of GBP1.06 billion.

SSE said the transmission link was completed on time and within Ofgem's requirements.

The Caithness-Moray link provides up to 1.2 gigawatts of capacity to transmit power from the increasing sources of renewable energy from across the far north of Scotland, SSE said.

 

Write to Oliver Griffin at oliver.griffin@dowjones.com; @OliGGriffin

 

(END) Dow Jones Newswires

January 11, 2019 06:49 ET (11:49 GMT)

Copyright (c) 2019 Dow Jones & Company, Inc.
SSE (PK) (USOTC:SSEZY)
Historical Stock Chart
From Mar 2024 to Apr 2024 Click Here for more SSE (PK) Charts.
SSE (PK) (USOTC:SSEZY)
Historical Stock Chart
From Apr 2023 to Apr 2024 Click Here for more SSE (PK) Charts.