Firestone Ventures Inc. ("Firestone" or the "Corporation") (TSX
VENTURE:FV)(FRANKFURT:F5V) is pleased to announce the results of the Preliminary
Economic Assessment ("PEA") completed on its Torlon Hill Zinc-Lead-Silver
Project located in Guatemala (the "Project") by ProMet Dadi Pty. ("ProMet")
based in Johannesburg, South Africa. The PEA outlines an operation with a
617,000 tonne per year throughput, projecting an after-tax 97% internal rate of
return ("IRR") and an after-tax US $45.4 Million net present value ("NPV") at a
5% discount rate. 


Firestone's plan is to construct the mine and mill facility that will produce a
zinc concentrate and a silver-rich lead concentrate that will be direct shipped
to market. Firestone continues to advance the social, environmental and
technical aspects of the Project that will allow for the completion of a
Feasibility Study and advance the project to production.


ProMet Study Base Case Highlights



--  After-tax and after-royalty Net Present Value ("NPV") at a 5% discount
    rate of US$45.4 Million and an after-tax Internal Rate of Return ("IRR")
    of 97% that assumes expenditure and commissioning happen in the same
    year, 
--  Payback of 1.2 years after tax and after plant start-up, 
--  Initial capital cost ("Capex") of US$26 Million over a 12-month
    development period, 
--  An initial 5 year mine life from the mining and processing of three
    million tonnes at a processing rate of 617,000 tonnes per year from one
    open pit operation with a strip ratio estimate of 2.57:1, 
--  Life of Mine ("LOM") payable production of 106,392 tonnes of contained
    zinc metal, 42,979 tonnes of contained lead metal and 766,800 ounces of
    silver from the production of a zinc concentrate and a silver-rich lead
    concentrate, 
--  Estimated Operating Costs for the initial 5 year mine-life are
    $42.42/tonne, 
--  Commodity price assumptions for base case of $1.00/lb zinc, $1.00/lb
    lead and $30/ounce silver. 



The PEA is preliminary in nature and includes inferred mineral resources that
are considered too speculative geologically to have economic considerations
applied to them that would enable them to be categorized as mineral reserves.
There is no certainty that the estimates of the PEA will be realized.


Firestone's President and CEO, Pamela Strand commented, "The operation outlined
by this PEA for the Torlon Hill Project indicates the potential for a fast track
to market approach for our zinc project. The projected NPV, net cash flows, and
relatively low capital costs arise from Firestone's advantages, including a
deposit near significant infrastructure (including the Pan American highway,
multiple ports and future hydro power). Our results to date, coupled with this
engineering study make a compelling case for expediting the development of the
Torlon Hill Project."


Economic Sensitivities

The economics of the Project are most sensitive to metal prices, recovery and
the grade of the potentially mineable mineralization. The results of the
sensitivity analysis are illustrated below. 


Note: To view the "NPV Sensitivity" graph, please click the following link:
http://media3.marketwire.com/docs/fv0306.pdf.




Financial Sensitivities at Various Zinc Prices (5%    
discount rate)                                        
                                                      
------------------------------------------------------
     Price of Zinc     After-tax NPV                  
          (US$/lb)      US$ Millions     After-tax IRR
------------------------------------------------------
             $1.05             $48.0              102%
------------------------------------------------------
             $1.00             $45.4               97%
------------------------------------------------------
             $0.95             $42.5               91%
------------------------------------------------------
             $0.90             $39.6               84%
------------------------------------------------------



The Project has favorable economic potential across a range of discount rates
and commodity prices. The operations outlined in this PEA are projected to
generate over $49.4 Million in revenue after-tax over the 5 years of mine life
at an 5% discount rate.


The metallurgical test work completed by Firestone and used within this PEA is
preliminary in scope and results in the generation of the concentrates from the
process proposed. Firstly a zinc concentrate with 30-40% zinc as carbonate with
45% payable metal and a lead concentrate with 60% lead and greater than 300 g/t
silver with 95% payable. These initial terms have been obtained from metal
traders in China using specific assumptions although no specific contracts have
been finalized. Costs in this PEA are CIF Chinese Port and all transport costs,
treatments charges and fees are included.


The Company has completed significant drilling of the current National
Instrument 43-101 ("NI 43-101") defined resource whereby 92% of the resource
estimate and the ore included in this PEA is in the measured and indicated
categories. The ore body is open in two directions and this PEA recommended
continued definition drill program to expand the existing resource. All past
resource estimates have had a 3% zinc equivalent cut off within the defined pit
shell confines. With a successful definition drill program and remodeling of the
current resource, Firestone expects to be able to support increased production
scenarios, which would further increase the already favorable Project NPV.


Terry Tucker, Firestone Director, elaborated on the preliminary economics of the
Project, "We are pleased with the level of engineering expertise behind this
PEA. Through the process we gained considerable insight into potential
opportunities for further improvement in the already attractive overall
potential economics, including future zinc concentrate concepts that will be
validated during the Feasibility Study phase. The relatively low unit operating
cost of production coupled with demand for zinc concentrate by various smelters,
means this operation has the potential to remain profitable and we are
predicting that the zinc price to remain strong as both demand and supply
increase in the future."




Project Description                               
                                                  
--------------------------------------------------
Capital Costs                                  US$
--------------------------------------------------
Process Plant                          $11,255,074
--------------------------------------------------
Infrastructure                         $ 2,927,605
--------------------------------------------------
Indirect Costs                         $ 7,621,414
--------------------------------------------------
Project Sub Costs                      $21,804,094
--------------------------------------------------
Contingency (20%)                      $ 4,455,873
--------------------------------------------------
PROJECT TOTAL                          $26,259,967
--------------------------------------------------



Mining at Torlon will be by standard open pit methods using a mining contractor
with a bench height of 5m. Waste haulage distance is estimated at 500m with ore
haulage at 2km. It is assumed that 75% of the rock will be free digging with
ripping and hydraulic breaking and that the balance of 25% will require light
blasting. Based on a 617,000 tonne per year of ore milled and 1,700 tonnes per
day of ore mined, the cost estimates for mining ore and waste are $2.47 and
$1.80 per ton respectively with a 2.57 stripping ratio. 


The process plant proposed has been based on a three stage crushing and
screening, DMS pre concentration, then milling of the DMS concentrate. The mill
product will then by subjected to differential floatation to generate both a
zinc and lead concentrate. The concentrates will then be washed, dewatered and
shipped from the site. 


ProMet has concept designed the location for deposition of slimes and tailings.
All materials to be mined at Torlon would be oxidized forms of mineralization. 


Estimated power requirements for the site infrastructure were estimated at
3000kW that is envisioned to be supplied by four 1000 kVA diesel generating
units with a fifth for standby. 




-------------------------------------------------------------------------
Operating cost summary                                                   
------------------------------------------------------------
                                Total Monthly                            
Item                                Cost (US$)    % of Total             
------------------------------------------------------------             
Fixed costs                                                              
------------------------------------------------------------             
Overheads                      $        2 353             1%             
------------------------------------------------------------             
Sub Total                      $        2 353             1%             
------------------------------------------------------------
                                                                         
------------------------------------------------------------             
Variable costs                                                           
------------------------------------------------------------             
Power                          $      238 021            62%             
------------------------------------------------------------             
Water                          $       13 129             3%             
------------------------------------------------------------             
Reagents                       $       49 270            13%             
------------------------------------------------------------             
Grinding Media (Primary and                                              
 Secondary Mills)              $        7 492             2%             
------------------------------------------------------------             
Mill Liners (Primary and                                                 
 Secondary Mills)              $        4 911             1%             
------------------------------------------------------------             
Crusher Liners                 $       11 090             3%             
------------------------------------------------------------             
Laboratory Costs               $       20 899             5%             
------------------------------------------------------------             
Maintenance Costs              $       38 074            10%             
------------------------------------------------------------             
Concentrate Transport          $            -                            
------------------------------------------------------------             
Sub total                      $      382 886            99%             
------------------------------------------------------------             
                                                                         
------------------------------------------------------------             
Total                          $      385 239              $ 7.49 per ROM
-------------------------------------------------------------------------


----------------------------------------
Cash Costs per ton                      
 processed                           US$
----------------------------------------
Mining                            $ 7.09
----------------------------------------
Processing                        $ 7.49
----------------------------------------
Slimes                            $ 0.12
----------------------------------------
Fixed                             $ 5.09
----------------------------------------
Off Mine                          $12.58
----------------------------------------
Capex Inc Financing              $ 10.04
----------------------------------------
TOTAL COST/TON ROM                $42.42
----------------------------------------



Areas for Optimization

The PEA has been successful in achieving the target set by Firestone to provide
a low Capex fast track to market operation. A series of recommendations have
been outlined in the PEA to meet a potential 18-24 month Project execution
timeline. The budget for this work is $1.2 Million. These areas include:




--  Resource optimization to identify additional mineral resources including
    remodeling for a total metal content to include low grade ore, 
--  Remodel the resource using a new block and geological model, 
--  Quantification and design of the upgrades to the existing road access
    route, 
--  Continue environmental baseline studies, socioeconomic studies and
    completion of an EIA, 
--  Additional metallurgical analysis to quantify the key design criteria to
    include but not limited to crushing work, milling liberation, screening
    performance, flotation tests and upgrade testwork on the zinc
    concentrates, 
--  Geotechnical studies, and 
--  Finalize formal off take agreements. 



PEA Report

The PEA was prepared in accordance with the guidelines of National Instrument
43-101 by the independent engineering firm ProMet Dadi Africa (Pty) Ltd.
("ProMet") located in Cape Town, South Africa. ProMet is a leading full-service
engineering firm and has experience in the sector that includes the design and
construction supervision of mining projects in Africa. The complete PEA report
will be filed on SEDAR and Firestone's website within 45 days of this news
release.


Qualified Persons

The PEA was prepared under the supervision of Mr. Kevin Van Wouw, FSAIMM and Mr.
Alan Minnaar, Pr. Eng., both independent Qualified Persons as defined by NI
43-101 and independent of Firestone. Mr. Van Wouw has reviewed and is
responsible for the technical information contained in this news release. The
geological block model and resource estimate are derived from the NI 43-101
compliant mineral resource estimate dated December 2008 (www.sedar.com),
authored by Al Workman, P.Geo. and Kurt Breede., P.Eng., of Watts Griffis McOuat
Limited, Toronto. ProMet has reviewed the 2008 estimate, and confirms that there
is no material change to the resource since its initial publication and accepts
the estimate as its own for use in the PEA. On behalf of the Company, the
technical information in this news release has also been reviewed and approved
by Pamela Strand, P.Geol., President of Firestone and a Qualified Person in
accordance with NI 43-101.


About Firestone Ventures Inc.

Firestone is a Canadian-based exploration and development company with
zinc-lead-silver and copper projects in Central America and has been working in
Guatemala since 2004. Our main project is the Torlon Hill Zinc-Lead-Silver
Project in Guatemala. The current NI 43-101 oxide resource (see news release 18
November 2008 on www.sedar.com) is summarized in the following table and the
deposit remains open to expansion. The NI 43-101 resource used a 3% zinc
equivalent cut-off grade and a 35.5% zinc top-cut. 




Torlon Deposit Oxide Mineral Resource - as at March 6, 2013

---------------------------------------------------------------------------
                        Zinc        Zinc   Lead        Lead Silver   Silver
               Tonnes      %     (lbs)(i)     %     (lbs)(i)  (g/t)  (oz)(i)
---------------------------------------------------------------------------
Measured                                                                   
 and                                                                        
 Indicated  1,891,636   7.32 304,905,997   2.41 100,294,541  14.25  866,663
---------------------------------------------------------------------------
Inferred      169,705   4.42  16,502,114   1.96   7,317,680  12.53   68,367
---------------------------------------------------------------------------
(i)The total contained metal assumes 100% metal recovery and does not 
   indicate economic viability



Smithsonite (ZnCO3) is the prevalent zinc mineral at Torlon, occurring as a
replacement to limestone and resulting in high grade mineralization locally
exceeding 40% zinc. Other non-sulphide zinc minerals are relatively rare and
there is no evidence of deleterious zinc-clay minerals.


In addition to Torlon, Firestone also has a large land position covering a
significant portion of the Central Guatemala Zinc District with four drill ready
targets and over fifty zinc mineral occurrences. The land position has excellent
exploration potential and with systematic exploration could develop as the
world's next major zinc district. The common shares of the Company are currently
listed on the TSX Venture Exchange (symbol FV) and the Frankfurt Stock Exchange
(symbol F5V).


Additional information about the Project can be found in the technical report
filed on SEDAR at  www.sedar.com entitled "Report on the Geology, Exploration
and Mineral Resources of the Torlon Hill 'Oxide' Zn-Pb-Ag Project District,
Huehuetenango, Guatemala" dated December, 2008.


This news release may contain forward looking statements, being statements which
are not historical facts, including, without limitation, statements regarding
potential mineralization, exploration results, resource or reserve estimates,
anticipated production or results, sales, revenues, costs, "best-efforts"
financings or discussions of future plans and objectives. There can be no
assurance that such statements will prove accurate. Such statements are
necessarily based upon a number of estimates and assumptions that are subject to
numerous risks and uncertainties that could cause actual results and future
events to differ materially from those anticipated or projected. Important
factors that could cause actual results to differ materially from the Company's
expectations are in Company documents filed from time to time with the TSX
Venture Exchange and provincial securities regulators, most of which are
available at www.sedar.com. The Company disclaims any intention or obligation to
revise or update such statements unless required by law.


FOR FURTHER INFORMATION PLEASE CONTACT: 
Firestone Ventures Inc.
Pamela Strand, P. Geol.
President
Toll Free: 1-888-221-5588
(780) 428-3476 (FAX)
info@firestoneventures.com
www.firestoneventures.com

Firestone Ventures (TSXV:FV)
Historical Stock Chart
From May 2024 to Jun 2024 Click Here for more Firestone Ventures Charts.
Firestone Ventures (TSXV:FV)
Historical Stock Chart
From Jun 2023 to Jun 2024 Click Here for more Firestone Ventures Charts.