Minera IRL Provides Corporate Update
24 November 2020 - 12:00AM
Minera IRL Limited (“Minera” or the “Company”) (BVL:MIRL)
(CSE:MIRL) expands upon the path forward following its recent
settlement agreement with Corporacion Financiera de Desarrollo
(COFIDE).
While the agreement with COFIDE, which was
signed at midnight on November 10, 2020, is simple, it took
extraordinary effort to complete. Dealing with government bodies is
never quick or easy, but dealing with them during COVID-19 and the
political roller coaster that has been the Peruvian Government for
the past five years has added difficulty and delay to an already
unpredictable negotiation. Since COFIDE made the Bridge Loan, Peru
has had five new Presidents and these changes at the top have had a
profound trickle-down effect on COFIDE’s Board of Directors,
management and priorities.
Without the settlement agreement, Ollachea could
not be financed. It was pledged as security for the Bridge Loan and
COFIDE put the Bridge Loan into default status in 2017. The
arbitration award did not fix this - when the arbitration panel
determined that COFIDE’s decision to abandon its mandate to finance
Ollachea was wrongful, it expressly declined to make a finding
affecting the Bridge Loan because the Bridge Loan could only be
adjudicated by the courts of New York State. In addition, COFIDE
promptly asked the Peruvian courts to ‘annul’ the arbitration
award, which application is only now being dismissed pursuant to
the settlement agreement. So even with the arbitration award in
hand, the Bridge Loan remained in default and the request for
annulment remained pending, and financing Ollachea was hostage to
the potential for years of expensive litigation in New York and
Peru. This roadblock has finally been removed and, for the first
time in years, Minera IRL can turn its collective energy back to
the task of advancing Ollachea.
Advancing Ollachea
The initial effort to advance Ollachea is
focusing on two fronts – updating the technical reports,
construction plans and budgets and raising money. For the benefit
of our newer shareholders, here is a recap of the evolution of the
project:
- The Definitive
Feasibility Study for Ollachea, based on 86 thousand meters of
drilling, was completed in November 2012.
- In 2013, the
Company completed a 1,234-meter tunnel to serve as the primary
access for the mine and as a platform for further exploration.
- The Environmental
Impact Study (EIA) was approved and the Construction Authorization
was obtained in 2013 and 2014.
- In 2014, Mining
Plus, an international mining consulting firm with extensive
experience in the proposed underground mining method, updated the
mine design. As a result:-- Total gold production increased
to 930,000 ounces (from 921,000 ounces).-- Average annual
production of 100,000 ounces over the first two years (up from
70,500 ounces).-- Average annual production unchanged at
100,000 ounces per year over an initial nine year mine
life.-- Initial capital cost of $164.7 million (down from
$177.5 million).-- Average total cash cost of $587 per ounce
(slight adjustment from $583 per ounce).-- An after-tax NPV,
at a 7% discount rate and gold price of $1,300 per ounce, of $181
million (up 17% from $155 million).-- IRR of 28.2% (up from
22.1%).-- Pay-back period decreased to 3.1 years (from 3.7
years).
- In 2016, a new
5,421 meter exploration underground program at the eastern end of
Minapampa showed that gold mineralization continues 500 meters to
the east and remains open to the east and at depth. These drill
hole results have been used to outline an exploration target in the
Minapampa Far East mineralized zone of 370,000 to 550,000 ounces of
gold contained within 3.1 to 4.6 million tonnes, grading 2.9 to 4.3
g/t gold (these potential tonnages and grades are conceptual in
nature and are based on drill results that define the approximate
length, thickness, depth and grade of mineralization in the
Minapampa Far East mineralized zone).
- In 2019, the EIA
was renewed indefinitely.
- Despite the
considerable financial constraints caused by the dispute with
COFIDE, the Company has continued to push forward with the
technical work, investigating various options for project execution
and a practical and optimized project start up.
The Company estimates that it will cost
approximately USD $800,000 to complete the technical work,
including ongoing support for project financing. This will lead
into the detailed engineering, execution planning and contractor
selection, as well as putting experienced staff on the ground to
start the mine. The recent resolution of the COFIDE dispute allows
the Company to re-direct cash flow away from legal expense and back
to project start up and execution planning and the Company believes
that it can fund this work out of ongoing revenue from
Corihuarmi.
Financing
During the second half of 2019 and the first few
months of 2020, the Company was actively contacting potential
financing parties (banks, debt funds and other lenders) in an
attempt to resolve both financing and the COFIDE situation in a
single sweep. Unfortunately, these markets were closed until the
situation with COFIDE was resolved. However, with the COFIDE
settlement in the rear-view mirror, the Company has re-opened its
stalled dialogue with these parties and it is already seeing
progress - two of the fourteen companies that have signed
non-disclosure agreements have already begun a due diligence
review.
Going forward, in addition to renewing
discussions with financing parties from last year, the Company has
opened discussions with a North American capital markets specialist
firm with a view to executing on a combined public equity and debt
transaction.
Diego Benavides, the Company’s Chief Executive
Officer, said “we have a proven record of accomplishment with
Corihuarmi and I have every confidence that we can do it again with
Ollachea. We are committed to getting this mine right the first
time, using the best international experience available in
underground mining for project oversight combined with the
practicality and affordability of Peruvian based professionals and
the continued support of the Ollachea community”.
FOR FURTHER INFORMATION, PLEASE CONTACT:
Minera
IRL Limited |
|
|
|
|
|
Gerardo PérezPresident |
|
+51 997 548 927 |
|
|
|
Diego BenavidesCEO and
Director |
|
+51 997 548 927 |
|
|
|
No stock exchange, securities commission or
other regulatory authority has approved or disapproved the
information contained in this news release.
Cautionary Statement on Forward-Looking
Information
Certain information in this news release, including
information about the Company’s expectation that it can update its
technical reports and further optimize its plans, that it can
complete its construction and engineering drawings for Ollachea,
that it can pay for these efforts out of revenue from Corihuarmi,
and that it can raise the capital that it needs to finish
construction at Ollachea, as well as the terms and timing of those
efforts, constitute “forward-looking statements”. Forward-looking
statements are based upon assumptions. While management believes
these assumptions and statements are reasonable in context,
forward-looking statements are inherently subject to political,
legal, regulatory, business and economic risks and competitive
uncertainties and contingencies. The Company cautions readers that
forward-looking statements involve known and unknown risks,
uncertainties and other factors that may cause Minera IRL’s actual
results and future performance to be materially different than
those expected or estimated future results, performance or
achievements and that forward-looking statements are not guarantees
of future performance, results or achievements.
Minera IRL assumes no obligation, except as may be
required by law, to update or revise them to reflect new events or
circumstances. Risks, uncertainties and contingencies and other
factors that might cause actual performance to differ from
forward-looking statements include, but are not limited to, Peru’s
ability to contain the COVID-19 crisis and to legislative,
political, social health or economic developments both within Peru
and in general.
Minera IRL (CSE:MIRL)
Historical Stock Chart
From Nov 2024 to Dec 2024
Minera IRL (CSE:MIRL)
Historical Stock Chart
From Dec 2023 to Dec 2024