Arian Silver Corporation: Operations Update
31 March 2014 - 5:00PM
Marketwired
Arian Silver Corporation: Operations Update
LONDON, ENGLAND--(Marketwired - Mar 31, 2014) - Arian Silver
Corporation (TSX-VENTURE:AGQ)(AIM:AGQ)(FRANKFURT:I3A) (the
"Company" or "Arian Silver") a silver exploration, development and
production company with a focus on projects in the silver belt of
Zacatecas, Mexico, reports that good progress continues to be made
on the refurbishment of the El Bote custom processing plant (the
"Plant"), which is expected to process up to 1,500 tonnes per day
("tpd") when operating at full capacity.
Key points:
- Refurbishment of the Plant is approximately 95% complete and
the Plant is on track to be commissioned by end 2014
- Transportation of the refurbished Plant to the new site has
commenced
- Installation of a new line to supply grid power to the new
plant site is complete
- Pre-construction earthmoving at the new site is complete
- New decline into the Soledad section of the San José mine has
commenced
- Financing discussions are advancing positively
Jim Williams, Chief Executive Officer of Arian Silver,
commented: "Arian Silver is making excellent progress in finalising
the refurbishment programme of its wholly-owned custom processing
plant, keeping the Company on track for the reassembly of the
Plant, and it's commissioning during the final quarter of this
year. Refinancing activities are also advancing positively, and I
look forward to updating shareholders further, in due course."
El Bote Processing
Plant
In August 2013, Arian Silver purchased a custom processing
plant, located just 60km from the Company's mine site. The
acquisition of this Plant is expected to enable Arian Silver to
increase production in a modular manner up to a maximum capacity of
1,500 tpd. This, together with increased mine production and the
elimination of Arian Silver's reliance upon third-party toll
millers, is expected to provide significantly increased operational
control and efficiency, which should therefore translate into
significantly reduced operational costs.
The refurbishment of the Plant is now approximately 95% complete
and on track to be commissioned by end 2014. Refurbished parts of
the plant have begun to be transported to site adjacent to the San
José mine.
The land set aside for the Plant has been prepared and is now
ready for the first concrete to be poured for the foundations.
A 35KW power line has been installed for exclusive use at the
Plant, which is ample to supply the Plant's needs. This is in
addition to the existing 13KW exclusive power line to the San José
mine.
The offices and associated buildings at the plant site have been
refurbished and are ready for use.
San José
mine
Mine development continues in the San José and Santa Ana
sections of the mine. Construction has commenced on an additional
4x5m ramp at the Soledad section of the mine, which is
approximately 1km west of the existing San José ramp. These works
will support the required increase in mine production capacity to
approximately 1,500 tpd within 18 to 24 months.
The mine has been dewatered to the 180m level (180m below the
surface), enabling access to new areas, and significant further
development has occurred at these deeper levels.
Financing
In August 2013, the Company entered a 12 month US$15.6 million
loan facility, convertible at the lender's option at C$1.10 per
share. The Company is negotiating the refinancing of this loan
note, and these financing activities are now advancing
positively.
Notes to editors
Arian Silver is a silver exploration, development and production
company with a focus on projects in Zacatecas, within the silver
belt of Mexico, the world's most productive silver district.
Arian Silver's flagship San José silver project comprises the
San José underground mine (Ag, Pb, Zn) and the El Bote custom
processing plant. The Company is in the process of refurbishing,
transporting and constructing the plant, which is expected to be
commissioned by the end of 2014.
Full details of the Company's NI 43-101 compliant mineral
resource estimate are available from
www.ariansilver.com/s/Sanjose.asp.
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) and no stock exchange, securities commission or
other regulatory authority accepts responsibility for the adequacy
or accuracy of this release nor approved or disapproved of the
information contained herein.
Arian Silver CorporationJim Williams, CEODavid Taylor, Company
Secretary(London) +44 (0)20 7887
6599dtaylor@ariansilver.comwww.ariansilver.comHume Capital,
BrokerJon Belliss / Abigail Wayne(London) +44 (0)20 7101
7070jon.belliss@xcapgroup.comGrant Thornton UK LLPPhilip Secrett /
David Hignell(London) +44 (0)20 7383
5100philip.j.secrett@uk.gt.comYellow Jersey PR LimitedDominic
Barretto(London) +44 (0)7768537739dominic@yellowjerseypr.com
Arian Silver Corporation (TSXV:AGQ)
Historical Stock Chart
From Dec 2024 to Dec 2024
Arian Silver Corporation (TSXV:AGQ)
Historical Stock Chart
From Dec 2023 to Dec 2024