Edenville Energy plc (AIM: EDL), the company developing a coal
to power project in south western Tanzania, is pleased to update
shareholders on the status of the Rukwa Coal to Power Project near
Sumbawanga.
The Company has made good progress in partnership discussions
since the last project update provided on 8(th) July 2015,
specifically in the following areas:
- Cost analyses have been received from several EPC
(Engineering, Procurement and Construction) groups, with details of
key modules including BTG (boiler, turbine, generator) and BOP
(balance of plant) components. Further refinement of costs is
expected as work continues. Additional visits to Tanzania by
potential partners are expected and continuing technical and
commercial analysis by the groups concerned is being undertaken in
conjunction with the Edenville team.
- Further development of relationships and discussions with
banks for the provision of debt finance to the Rukwa Power Project.
Providers of debt finance often work alongside EPC groups to ensure
adequate project finance is available when needed throughout the
project build.
Edenville Energy is pursuing an integrated approach to project
development, with the potential EPC partners and financial
institutions involved being progressed in parallel at this stage,
working alongside the Tanzanian government to execute its Power
System Master Plan. The Power System Master Plan includes
transmission expansion and upgrade, along with selection of the
most suitable power generation solution for each region.
Edenville's Rukwa coal deposit is considered an ideal platform to
provide much needed electricity in the Rukwa and surrounding
regions. The project's location next to the planned grid expansion
gives the potential for provision of baseload power, providing a
long term solution to energy needs in the Rukwa region.
Rufus Short, CEO of Edenville commented, "Edenville continues to
progress the Rukwa Coal to Power project, with attention focused on
the selection of EPC and financial partners. We have made
significant progress in this area over the past 6 months and aim to
complete the process during Q4, 2015, but external factors beyond
our control may influence timing. We will pursue an integrated
approach to project development, with the aim of implemention
alongside the Tanzanian authorities, to provide a successful
outcome for all stakeholders. During Q4, when all interested
parties will have concluded meetings and put forward formal
proposals, we expect our discussions to reach a point where a
structured, multi-party plan can allow the project to progress to
the stage where advanced discussions on timing for project
development can be entered into with the Tanzanian authorities.
We will continue to update our shareholders on developments
relating to the Rukwa Coal to Power Project as they occur. "
Contact
Edenville Energy Plc +44 (0) 20 7652
Rufus Short - CEO 9788
Cantor Fitzgerald Europe
(Nominated Advisor and Corporate
Broker)
Stewart Dickson
Philip Davies +44 (0) 20 7894
Jeremy Stephenson 7000
IFC Advisory
(Financial PR and IR)
Tim Metcalfe
Graham Herring +44 (0) 20 3053
Heather Armstrong 8671
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCUGUACBUPAGQM
(END) Dow Jones Newswires
September 08, 2015 02:00 ET (06:00 GMT)
TV Commerce (LSE:TVC)
Historical Stock Chart
From Nov 2024 to Dec 2024
TV Commerce (LSE:TVC)
Historical Stock Chart
From Dec 2023 to Dec 2024