Troilus Gold Corp. (TSX: TLG; OTCQX: CHXMF) (“Troilus” or the
“Company”) reports results from a Feasibility Study (“FS” or the
“Study”) completed on the gold-copper Troilus Project (the
“Project”) located in northcentral Quebec, Canada. The Study
incorporates an initial mineral reserve estimate (“MRE”) that
supports a long life, large scale, 50,000 tonnes per day (“tpd”)
open-pit mining operation; a project in a tier-one mining
jurisdiction that stands out in the Quebec and Canadian mining
landscapes.
Troilus has taken a focused and conservative
approach to all costs and inputs to deliver a realistic and
compelling Feasibility Study that we believe maximizes the scope
and scale of this mineral asset over the long term. All amounts are
in United States dollars, unless otherwise stated.
2024 FEASIBILITY STUDY
HIGHLIGHTS
Large Scale Open-Pit Project
- Open pit mine life of 22 years with the potential for future
underground development.
- Life-of-mine (“LOM”) average payable gold production of 244,600
ounces annually, 17.3 million pounds of copper and 446,700 ounces
of silver annually.
- Peak annual payable gold production of 456,100 ounces, 31.8
million pounds of copper and 613,600 ounces of silver in year
7.
- Open pit mine, processing 50,000 tonnes-per-day (“tpd”); a 43%
larger scale operation than the 35,000 tpd processing rate
contemplated in the Preliminary Economic Assessment (“PEA”) from
2020.
- An economical and energy-efficient process to produce a
desirable gold-rich copper concentrate for sale to smelters, with a
cyanide-free gravity concentration circuit to produce doré after
Year 1.
- Supported by an initial Mineral Reserve estimate of 380Mt
grading 0.59 g/t gold equivalent (“AuEq”) (0.49 g/t Au, 0.058% Cu
and 1.0 g/t Ag) for a contained 7.26Moz AuEq (6.02 Moz Au, 484 Mlbs
Cu and 12.2 Moz Ag).1
- LOM total payable gold of 5.4 million ounces, 382 million lbs
of copper and 9.9 million ounces of silver.
- Average LOM strip ratio of 3.1:1.
Low-Cost Production2
- All-in sustaining cash operating costs (“AISC”) of
$1,109/oz.
- Average operating costs of $19.06/t milled ore.
Strong Economic Results
- Base Case after-tax NPV5% of USD$884.5 million and IRR of 14%,
reflecting long-term forecast prices of US$1,975/oz Au, $4.05/lb
Cu, $23/oz Ag and $0.74 USD/CAD exchange rate.
- After-tax NPV5% of USD$1.55 billion and IRR of 19.5% at April
2024 average metal prices (Au: $2,332/oz; Cu: $4.30/lb; Ag:
$27.50/oz).
- Cumulative after-tax cashflow of $2.2 billion on base case
assumptions; increasing to $3.4 billion using average metal prices
for April 2024.
Attractive Capital Intensity Given Inflationary
Environment and Scale of Operation
- Initial development capital of (“CAPEX”) of $1,074 million,
including all mine pre-production costs, net of existing
infrastructure.
- Existing and upgraded infrastructure, including powerlines and
50MW substation, all-weather access roads and tailings facility
among other infrastructure, reduce capital requirements for the
project and overall capital intensity.
Exploration Upside:
- Numerous targets ranging from grass roots geochemical anomalies
to early-stage drill targets are actively being explored and
advanced, both near mine and regionally, representing significant
future upside potential.
_______________________________
1 AuEq was calculated using metal prices of $1,550/oz Au;
$3.50/lb Cu and $20.00/oz Ag.2 See Non-IFRS Measures at the end of
this news release.
Justin Reid, CEO of Troilus, commented, “The
entire Troilus team is proud to present results that clearly
demonstrate the potential for our project to become a major North
American copper and gold producer. The FS outlines a
generational-scale asset, with a 22-year mine life and compelling
economics, both at discounted and current metal prices. The project
has reasonable CAPEX and capital intensity, including bottom
quartile operating costs among the major Canadian gold mines. With
a life-of-mine average payable gold production of nearly 245,000
ounces annually, more than 17 million pounds of copper and nearly
447,000 ounces of silver, Troilus stands not only as a
strategically significant project that aligns with the Province of
Quebec’s priority on the production of strategic metals but is also
positioned to be amongst the largest scale, lowest cost gold and
copper projects across Canada.
In today’s challenging market, the value of our
existing infrastructure has become even more critical, reducing the
capital intensity required to build project infrastructure and
providing ongoing access to low-cost renewable energy supplied by
Hydro-Quebec. The Troilus Project has been designed to minimize the
environmental footprint of the future operation including using a
cyanide free process, engaging in progressive reclamation, making
use of the existing tailings facility and minimizing GHG emissions
through reliance on sustainable energy sources.
The Study provides a strong foundation to
continue building and growing the Company. Our geology team has
proven their ability to identify new targets and rapidly add
significant ounces, and we believe there is strong potential to
further expand the scale of this project and extend the mine life
beyond the 22 years presented in this Study with further
exploration and drilling.
With the FS now complete, Troilus is focused on
next steps, namely the finalization of the Environmental &
Social Impact Assessment and ongoing exploration of the geological
potential of the 435 km² Troilus property. We look forward to
working with our partners in the Eeyou Istchee James Bay region,
including the Cree Nation of Mistissini, the Cree Nation Government
and Grand Council of the Crees, the local communities of
Chibougamau and Chapais, as well as the governments of the Province
of Quebec and Canada, to advance the Troilus Project.”
2024 Feasibility Study Summary
PRODUCTION |
Mine Life |
22 years |
Daily Mill Throughput |
50,000 tpd |
Annual Mill Throughput |
18.3Mt/year |
Average Annual Metal Production (Payable) |
Gold (oz) |
Copper (Mlbs) |
Silver (oz) |
Years 1-5 |
256,200 |
16.1 |
475,200 |
Years 6-22 |
241,200 |
17.7 |
438,300 |
Life of Mine |
244,600 |
17.3 |
446,700 |
Proven & Probable Reserves |
380 Mt containing 7.26 Moz AuEq (6.02 Moz Au, 484 Mlbs Cu,
12.2 Moz Ag) |
Proven & Probable Average Grades |
0.59 g/t AuEq (0.49 g/t Au, 0.058% Cu, 1.0
g/t Ag) |
Strip Ratio |
3.1:1 |
Average LOM Gold/Copper/Silver Recoveries |
92.7% / 91.8% / 91.9% |
COST METRICS |
Initial Capital Expenditure |
$1,074 million |
Sustaining Capital Expenditure |
$276.6 million |
All-in-sustaining-cost (life-of-mine)¹ |
$1,109/oz |
ECONOMIC RESULTS |
Base Case (Au: $1,975/oz; Cu: $4.05/lb; Ag:
$23/oz) |
After-tax NPV @ 5% discount rate |
$884 million (C$1,208 million) |
After-tax IRR |
14% |
Payback (years) |
5.7 years |
April 2024 Average (Au: $2,332/oz; Cu: $4.30/lb; Ag:
$27.50/oz) |
After-tax NPV @ 5% discount rate |
$1,553 million (C$2,121 million) |
After-tax IRR |
19.5% |
Payback (years) |
4.7 years |
*Assuming a US$:C$ exchange of $0.74.¹ See
Non-IFRS Measures at the end of this news release.
Project Overview
The Troilus Project is comprised of four main
zones of mineralization, which are located on a NE-SW trend
covering approximately seven kilometres. These deposits will be
mined using conventional open pit mining methods over a 22-year
period. Ore will be processed in a flotation mill to produce
gold-rich copper concentrate for sale to a smelter, with provision
for gravity gold recovery to produce doré after Year 1.
The projected payable gold production averages
256,200 oz per year over the first 5 years, 241,200 oz per year for
the remaining 17 years, for a LOM average of 244,600 oz per year.
Copper payable annual production averages 16.1 million pounds per
year for the first five years, 17.7 million pounds per year for the
remaining 17 years and 17.3 million pounds for the life of mine
average. Silver payable annual production is 475,200 oz per year
for the first five years, 438,300 oz per year for the remaining 17
years with a life of mine annual average of 446,700 oz per year.
The production profile is shown in Figure 1.
Total payable metal over the 22-year mine life
is estimated at 5.4 million ounces of gold, 381.8 million pounds of
copper, and 9.9 million ounces of silver.
Figure 1: Production Profile - Payable Gold, Silver, and
Copper
https://www.globenewswire.com/NewsRoom/AttachmentNg/2fbb01f6-11ef-4d81-8237-265e1397d087
Economic Analysis
The Troilus Project’s estimated Base Case
after-tax NPV (5%) is $884 million and IRR is 14%, assuming metal
prices of $1,975 per ounce gold, $4.05 per pound copper, $23 per
ounce silver and a USD:CAD foreign exchange rate of $0.74:1.
Payback on initial capital is expected to be achieved in 5.7 years
under the base case scenario.
Assuming April 2024 average gold price of $2,333
per ounce, the after-tax NPV(5%) increases to $1.55 billion and IRR
increases to 19.5%, with the payback decreasing to 4.7 years.
|
Base Case |
April 2024 Avg. |
Gold Price (per oz) |
$1,975 |
$2,332 |
Copper Price (per lb) |
$4.05 |
$4.30 |
Silver Price (per oz) |
$23.00 |
$27.50 |
|
|
|
Pre-Tax NPV (5%) |
$1,564 MM |
$2,670 MM |
Pre-Tax IRR |
18.1% |
25.0% |
|
|
|
Post-Tax NPV (5%) |
$884 MM |
$1,553 MM |
Post-Tax IRR (%) |
14.0% |
19.5% |
Post-Tax Payback |
5.7 |
4.7 |
|
|
|
Table 1: Troilus Project NPV and IRR Sensitivity to
Metal Prices
Under the base case scenario, the Project generates cumulative
cash flow of $2.2 billion on a post-tax basis and $3.5 billion on a
pre-tax, based on a throughput of 50,000 tpd over 22 years (see
Figure 2).
Figure 2: Cumulative After-Tax Free Cash Flow After
Repayment of Capital at Base Case and April 2024 Average Metal
Prices
https://www.globenewswire.com/NewsRoom/AttachmentNg/6124e15b-c4e6-4f13-9cb8-9379b51319c5
Capital Costs
The initial CAPEX for the Troilus Project is
$1,075 million, net of existing infrastructure that includes
all-weather access roads, power lines and a 50MW substation, a
tailings facility, water treatment plants and site roads.
Sustaining CAPEX over the life of the mine is an additional $276.6
million. A breakdown of the capital requirements is presented in
Table 2.
Table 2: Troilus Project Capital
Expenditure Estimates Breakdown (US$)
Capital Costs ($ million) |
|
Mining |
$258.3 |
Process Plant |
$443.0 |
Infrastructure |
$100.3 |
Indirects |
$173.0 |
Contingency |
$89.3 |
Subtotal – Initial Capital |
$1,063.9 |
Environmental |
$10.7 |
Total – Initial Capital |
$1,074.6 |
Sustaining Capital |
$209.1 |
Closure Costs |
$67.4 |
Total Sustaining Capital |
$276.6 |
*Net of existing infrastructure (access road,
power line, substation, tailings facility, water treatment plant,
site roads)
Operating Costs
Total all-in-sustaining costs of $1,109 per
ounce. Total operating costs are expected to average $19.06 per
tonne of ore processed. A breakdown of the operating costs is
presented in Table 3.
Table 3: Troilus Project Operating Cost
Estimates (US$)
Average Life-of-Mine Operating Costs |
|
Mining |
$11.60/t |
Processing |
$5.64/t |
G&A, Trucking, Port, Shipping |
$1.82/t |
Total Operating Cost/Tonne Ore |
$19.06/t |
All-in Sustaining Cost |
$1,109/oz |
|
|
Mining
The Study considers a conventional open pit
mining operation using a 100% owner-operated equipment fleet
peaking at 41–227 tonne trucks, electric hydraulic shovels, wheel
loaders and drills. The mine has been designed to deliver 18.3
million tonnes per year (50,000 tonnes per day) of mill feed. The
FS contemplates a mine that delivers 379.5 million tonnes with an
average head grade of 0.49 g/t Au, 0.058% Cu, 1.0 g/t Ag.
The process plant is expected to have three
months of commissioning in pre-production, followed by nine months
of production ramp-up during the first year of production.
The project will mine four areas: Z87, J Zone,
Southwest (SW) Zone and X22. Mining commences in the Z87 pit area
in the pre-production period and will be mined continuously until
Year 8. The final phase of the 87 Zone pit area will be mined from
Year 12 until Year 19. The SW Zone pit area starts production in
Year 1 and is mined continuously until completion in Year 9 and
will then be used for deposition of tailings from year 10 to 16.
The J Zone pit area starts production in Year 5 and is mined
continuously until early Year 15. The X22 pit will be mined from
Year 18 to 21. Waste from the Z87 and X22 open pits will be
backfilled over the SW tails from Year 16 onward. When Z87 pit area
is completed in Year 19, waste is also backfilled into it from the
X22 pit area, reducing the overall size of the waste storage
facilities.
The average strip ratio for the open pit life of
the mine is estimated at 3.1:1. Material movement averages 86
million tonnes (feed and waste) in the first 5 years with the peak
at 86 million tonnes in Year 5. The open pit will provide 379.5
million tonnes of feed to the process plant over the 22-year mine
life. Open pit bench heights of 10 metres will be mined and ore
hauled with 227-tonne haul trucks and matching loading equipment
including electric hydraulic shovels. The open pit mining fleet
will be leased. Best practice grade control drilling will be done
with reverse circulation drilling and rock sampling on mine benches
prior to blasting. This provides the greatest flexibility for grade
control during operations while maintaining reasonable mine
operating costs and production capability.
During the mining operation a stockpile will be
maintained adjacent to the primary crushing plant to be used as
supplemental feed as required to meet production targets, weather
events, and as mill feed in the later years of the operation. Waste
rock will be hauled to dedicated waste management facilities near
the open pits, backfilled into the 87 Zone pit, placed in lifts
over the tails in SW Zone pit, and also used for lifts of the
tailings management facility. Concurrent reclamation of the waste
management facilities is planned.
Metallurgy
The flowsheet, similar to the original Troilus
Mill operated by Inmet, has been developed based on testwork
completed at Eriez, FLS/Knelson, Base Met and Kappes Cassidy. The
process plant consists of primary and secondary crushing, HPGR and
ball milling, copper/gold flotation with a regrind circuit,
concentrate filtration and tailings thickening and disposal. Copper
concentrate, enriched with gold, will be sent to a smelter for
refining. Provision has been made to install gravity gold
concentration for the primary and regrind circuit in Year 1 where
gold dorés will be produced. Overall recovery is estimated to be
92.7% for gold, 91.8% for silver, and 91.9% for copper based on the
LOM average head grades.
Figure 3: Troilus Project Process Flowsheet
https://www.globenewswire.com/NewsRoom/AttachmentNg/48305ee6-3509-40a3-ab93-a8cf6eb13362
Location and Infrastructure
The Troilus Gold Project is located in Quebec,
Canada, approximately 120 kilometres north of Chibougamau, where
Inmet Mining Corporation operated a large mine/concentrator complex
from 1996 to 2010. Access to the mine site from Chibougamau is by
the Route du Nord.
The Troilus Project benefits greatly from the
upgraded, and substantial infrastructure on site, which
includes:
- Power line and 50MW substation sufficient for project power
requirements,
- All-weather access road,
- Tailings facility and water treatment plant,
- Camp facilities,
- Site roads,
- Water supply,
- Septic system.
As part of the design, it is proposed to develop
the tailings dyke as a downstream raise constructed containment
from the existing tailings management facility which will limit the
overall footprint disturbance. This structure will have the
capacity to accommodate the first 10.5-year life of mine production
and then from years 11-22, the tailings will be disposed
subsequently into the mined-out SW pit, J pit and 87 pit as
described in this FS. Waste rock from the mine operation placed
along the tailings facility’s containment dyke will enhance the
facility’s stability and safety and will also limit the footprint
disturbance.
Figure 4: Troilus Project Location
https://www.globenewswire.com/NewsRoom/AttachmentNg/c90a9853-2eed-41c7-b20c-ff01a8e5b4c2
Figure 5: Troilus Project Mine Site Layout (Year
22)
https://www.globenewswire.com/NewsRoom/AttachmentNg/fa4d71e4-7030-421b-9144-6e6129c557db
Mineral Reserve Estimate
The FS is based on an inaugural Proven and
Probable Mineral Reserve estimate totaling 380 million tonnes,
grading 0.59g/t AuEq (0.49 g/t Au, 0.058 % Cu and 1.0 g/t Ag) and
containing 7.26 million ounces of gold equivalent (6.02 Moz Au, 484
Mlb Cu and 12.15 Moz Ag), reflecting the successful conversion of
Indicated and Inferred Mineral Resources (see Table 4).
Table 4: Troilus Project Mineral Reserve
Estimate
|
Tonnage |
Grades |
Contained Metal |
|
|
Au |
Cu |
Ag |
AuEq |
CuEq |
Au |
Cu |
Ag |
AuEq |
CuEq |
Class |
(Mt) |
(g/t) |
(%) |
(g/t) |
(g/t) |
(%) |
(Moz) |
(Mlb) |
(Moz) |
(Moz) |
(Blbs) |
Proven |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Probable |
380 |
0.49 |
0.058 |
1.00 |
0.59 |
0.39 |
6.02 |
484 |
12.15 |
7.26 |
3.24 |
P&P |
380 |
0.49 |
0.058 |
1.00 |
0.59 |
0.39 |
6.02 |
484 |
12.15 |
7.26 |
3.24 |
|
|
|
|
|
|
|
|
|
|
|
|
Note: This mineral reserve estimate has an
effective date of January 15, 2024, and is based on the mineral
resource estimate dated October 2, 2023, for Troilus Gold by AGP
Mining Consultants Inc. The Mineral Reserve estimate was completed
under the supervision of Willie Hamilton, P.Eng. of AGP, who is a
Qualified Person as defined under NI 43-101. Mineral Reserves are
stated within the final pit designs based on a US$1,550/oz gold
price, US$20.00/oz silver price and US$3.50/lb copper price. An NSR
cut-off of C$9.96/t was used to define reserves. The life-of-mine
mining cost averaged C$3.99/t mined, preliminary processing costs
were C$8.02/t ore and G&A was C$1.94/t ore placed. The
metallurgical recoveries were varied according to gold head grade
and concentrate grades. 87 pit recoveries for equivalent grades
were 95.5%, 94.7% and 98.2% for gold, copper, and silver
respectively. J pit recoveries for equivalent grades were 93.1%,
89.3% and 88.9% for gold, copper, and silver respectively. X22 pit
recoveries for equivalent grades were 95.5%, 94.7% and 98.2% for
gold, copper, and silver respectively. SW pit recoveries for
equivalent grades were 85.7%, 91.5% and 85.6% for gold, copper, and
silver respectively. The formulas used to calculate equivalent
values are as follows, for 87 Pit AuEq = Au + 1.5361*Cu +0.0133
*Ag, for J Pit AuEq = Au + 1.4849*Cu +0.0123 *Ag, for SW Pit AuEq =
Au + 1.6535*Cu +0.0129 *Ag, for X22 Pit AuEq = Au + 1.5361*Cu
+0.0133 *Ag. Please refer to the identified risks in the Company’s
Annual Information Form available under the Company’s profile at
www.sedarplus.ca for known legal, political, environmental, and
other risks that could materially affect the potential development
of the mineral resources and mineral reserves.
Exploration Upside
The Troilus Project is held within a large
exploration land package totaling 435 km² within the prospective
Frôtet-Evans Greenstone Belt. Numerous targets ranging from grass
roots geochemical anomalies to early-stage drill targets are
actively being explored and advanced by the Company, both near mine
and regionally.
In late 2022, the ‘X22 Zone’ was discovered
along an oblique structural trend immediately adjacent to the
previously mined Z87 pit, and now hosts 1.19M ounces AuEq Indicated
mineral resources, highlighting the prospectivity and continued
opportunity for discovery at both the mine site and within the
belt. X22 remains open, particularly at depth, and has previously
not been drill tested below 250 metres from surface.
A 25,000m drill program is underway, largely
focused across the ‘Gap Zone’ between Z87 and the SW zones, and at
depth at the X22 Zone. Using multiple layers of geoscientific data
and the latest understanding of the deposit genetics, a spectrum of
targets were developed that range from strategic resource expansion
to those more conceptual in nature.
Next Steps
The Company will be focused on the following
activities over the next 24 months:
- Completion and submission of the Environmental and Social
Impact Assessment (“ESIA”) by the end of 2024.
- Progressing the Federal and Provincial permitting processes,
which were initiated in May 2022, and obtaining all final permits
to commence construction.
- Initiate detailed engineering in preparation for
construction.
- Project Financing: The Company has engaged Auramet
International, Inc (“Auramet”) as Financial Advisor in conjunction
with project financing for the Troilus Project.
- Ongoing exploration both near the mine and regionally.
Feasibility Study Review
Webinar
Troilus will be hosting a webinar to discuss the
results of the Troilus Project Feasibility Study. CEO, Justin Reid,
Senior Vice-President of Technical Services, Ian Pritchard, and
other members of the Troilus leadership team will be on the call.
Participants will be able to submit questions or email them in
advance to info@troilusgold.com.
Date: May 14,
2024Time: 4:00 pm ET /1:00 pm PT
To join the webinar, please register here:
https://event.webinarjam.com/register/1318/84ll8tyg8
Feasibility Study
Consultants
The Troilus Project Feasibility Study is being
prepared and compiled by AGP Mining Consultants Inc. (“AGP”) and
supported by independent consulting firms, Lycopodium Limited
(“Lycopodium”) and WSP Canada Inc. (“WSP”), in collaboration with
Troilus’ technical team and the completed NI 43-101 technical
report associated with the Troilus Project FS will be available on
SEDAR+ at www.sedarplus.ca under the Company’s issuer profile, as
well as the Company’s website at www.troilusgold.com within 45
calendar days.
Qualified Persons
The FS is prepared by independent
representatives of AGP, Lycopodium and WSP, each of whom are
Qualified Person as defined by NI 43-101 Standards of Disclosure
for Mineral. Each of the QPs are independent of Troilus Gold Corp.
and have reviewed and confirmed that this news release fairly and
accurately reflects, in the form and context in which it appears,
the information contained in the respective sections of the Troilus
FS for which they are responsible. The affiliation and areas of
responsibility for each QP involved in preparing the Troilus FS are
provided below.
AGP QPs
Paul Daigle, P.Geo. - Mineral Resources
estimate.Willie Hamilton, P.Eng. - Mineral Reserves, Mine design
and scheduling.Gordon Zurowski, P.Eng - Mine Costing and financial
analysis.
Lycopodium QP
Ryda Peung, P.Eng. - Metallurgical review,
process design and operating cost estimate.Balvinder Singh, P. Eng.
- Process plant and associated infrastructure cost estimates.Zuned
Shaikh, P. Eng.- Design and material take off for the process plant
related infrastructure.
WSP QPs
Vlad Rojanschi, P.Eng. - Design and material takeoff for the
surface water management infrastructure (not including
electromechanical treatment or pumping equipment), hydrogeology,
and mine site water balance prediction.Laurent Gareau, P.Eng. -
Geotechnical design and material takeoff for the Tailings Storage
Facility.Pierre Primeau, P.Eng. - Design and costs for TSF water
treatment for suspended solids removal, and selected surface water
conveyance pipelines and pumping.Marc Rougier, P.Eng. - Mine
geotechnical aspects of open pits slopes design.
Non-IFRS Financial
Measures
The Company has included certain non-IFRS
financial measures or ratios in this news release, such as Initial
Capital Cost, All-In Sustaining Cost, Sustaining Capital and
Capital Intensity, which are not measures recognized under IFRS and
do not have a standardized meaning prescribed by IFRS. As a result,
these measures may not be comparable to similar measures reported
by other corporations. Each of these measures used are intended to
provide additional information to the user and should not be
considered in isolation or as a substitute for measures prepared in
accordance with IFRS.
Non-IFRS financial measures used in this news
release and common to the gold mining industry are defined below.
As construction and operation of the Project are at the study
stage, the Company does not have historical non-IFRS financial
measures nor historical comparable measures under IFRS, and
therefore the foregoing prospective non-IFRS financial measures or
ratios may not be reconciled to the nearest comparable measures
under IFRS.
All-in Sustaining Costs (“AISC”) and AISC per
Ounce
AISC is reflective of all of the expenditures
that are required to produce an ounce of gold from operations. AISC
reported in the FS includes total cash costs, sustaining capital,
expansion capital and closure costs, but excludes corporate general
and administrative costs and salvage. AISC per Ounce is calculated
as AISC divided by payable gold ounces and copper/silver
credits.
About Troilus Gold Corp.
Troilus Gold Corp. is a Canadian
development-stage mining company focused on the systematic
advancement of the former gold and copper Troilus Mine towards
production. Troilus is located in the tier-one mining jurisdiction
of Quebec, Canada, where is holds a large land position of 435 km²
in the Frôtet-Evans Greenstone Belt. A Feasibility Study completed
in May 2024 supports a large-scale 22-year, 50ktpd open-pit mining
operation, positioning it as a cornerstone project in North
America.
For more information:
Caroline Arsenault VP Corporate Communications
+1 (647) 407-7123 info@troilusgold.com
Cautionary Note Regarding
Forward-Looking Statements and Information
This press release contains “forward-looking
statements” within the meaning of applicable Canadian securities
legislation. Forward-looking statements include, but are not
limited to, statements regarding the results of the FS, including,
without limitation various project economics, financial and
operational parameters such as the timing and amount of future
production from the Project, expectations with respect to the IRR,
NPV, payback and costs of the Project, anticipated mining and
processing methods of the Project; proposed infrastructures,
anticipated mine life of the Project, expected recoveries and
grades, timing of future studies including the environmental
assessments (including the timing of an environmental impact study)
and development plans, the timing and progress of the Federal and
Provincial permitting processes, the timing and success of detailed
engineering in preparation for construction, the ability of the
Company to secure sufficient project financing, the opportunity to
expand the scale of the project, the project becoming a cornerstone
mining project in North America; the development potential and
timetable of the project; the estimation of mineral resources and
reserves; realization of mineral resource and reserve estimates;
the timing, success and amount of estimated future exploration;
costs of future activities; capital and operating expenditures;
success of exploration activities; the anticipated ability of
investors to continue benefiting from the Company’s low discovery
costs, technical expertise and support from local communities, the
timing and amount of estimated future exploration; and the
anticipated results of the Company’s 2024 drill program and their
possible impact on the potential size of the mineral resource
estimate. Generally, forward-looking statements can be
identified by the use of forward-looking terminology such as
“plans”, “expects” or “does not expect”, “is expected”, “budget”,
“scheduled”, “estimates”, “forecasts”, “intends”, “continue”,
“anticipates” or “does not anticipate”, or “believes”, or
variations of such words and phrases or statements that certain
actions, events or results “may”, “could”, “would”, “will”, “might”
or “will be taken”, “occur” or “be achieved”. Forward-looking
statements are made based upon certain assumptions and other
important facts that, if untrue, could cause the actual results,
performances or achievements of Troilus to be materially different
from future results, performances or achievements expressed or
implied by such statements. Such statements and information
are based on numerous assumptions regarding present and future
business strategies and the environment in which Troilus will
operate in the future. Certain important factors that could
cause actual results, performances or achievements to differ
materially from those in the forward-looking statements include,
amongst others, currency fluctuations, the global economic climate,
dilution, share price volatility and competition.
Forward-looking statements are subject to known and unknown risks,
uncertainties and other important factors that may cause the actual
results, level of activity, performance or achievements of Troilus
to be materially different from those expressed or implied by such
forward-looking statements, including but not limited to:
there being no assurance that the exploration program or programs
of the Company will result in expanded mineral resources; risks and
uncertainties inherent to mineral resource and reserve estimates;
the high degree of uncertainties inherent to feasibility studies
and other mining and economic studies which are based to a
significant extent on various assumptions; variations in gold
prices and other metals, exchange rate fluctuations; variations in
cost of supplies and labour; receipt of necessary approvals;
availability of financing for project development; uncertainties
and risks with respect to developing mining projects; general
business, economic, competitive, political and social
uncertainties; future gold and other metal prices; accidents,
labour disputes and shortages; environmental and other risks of the
mining industry, including without limitation, risks and
uncertainties discussed in the Company’s latest Annual Information
Form, its technical reports and other continuous disclosure
documents of the Company available under the Company’s profile at
www.sedarplus.ca. Although Troilus has attempted to identify
important factors that could cause actual results to differ
materially from those contained in forward-looking statements,
there may be other factors that cause results not to be as
anticipated, estimated or intended. There can be no assurance
that such statements will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue
reliance on forward-looking statements. Troilus does not
undertake to update any forward-looking statements, except in
accordance with applicable securities laws.
Troilus Gold (TSX:TLG)
Historical Stock Chart
From Oct 2024 to Nov 2024
Troilus Gold (TSX:TLG)
Historical Stock Chart
From Nov 2023 to Nov 2024