Torex Gold Resources Inc. (the “Company” or “Torex”) (TSX: TXG)
provides the third quarterly update on the development of its Media
Luna Project (“Media Luna”). Unless otherwise stated, progress and
milestones referenced in this press release are as of June 30,
2023.
Jody Kuzenko, President & CEO of Torex,
stated:
“Development activities related to the Media
Luna Project continued to advance well during Q2 with the project
remaining on budget and on schedule. At quarter-end, Media Luna was
35% complete across engineering, procurement, underground
development, and surface construction. With $143.6 million of
expenditures incurred through H1 and the quarterly spend rate
expected to increase further, full year guided expenditures are
trending towards the lower end of the guided range of $390 million
to $440 million. As of June 30th, 45% of upfront project
expenditures had been committed or incurred.
“Detailed engineering and procurement activities
increased materially during the quarter, with several key purchase
orders awarded, the most significant being the battery electric
mining fleet for production support and personnel transport, as
well as the ball mill motors equipped with variable frequency
drives. In addition, we awarded the vertical development and
underground construction contract, and the contractor is now
mobilizing to site. Work to expedite the paste plant filter presses
has been successful in pulling the delivery dates forward by one
month, while efforts to expedite the schedule critical underground
electrical equipment to mitigate schedule risk are ongoing.
“The Guajes Tunnel has advanced 4,500 metres
with breakthrough on track for early Q1 2024, if not earlier. At
South Portal Lower, the main spiral ramp was completed post-quarter
end and the primary tunnel has advanced 2,075 metres. Civil works
on both sides of the Balsas River continued during the quarter, and
concrete installation will commence as the site-wide concrete
contractor is selected.
“With development activities tracking to plan,
robust financial liquidity, and strong ongoing cash flow from El
Limón Guajes, we are well positioned physically and financially to
deliver Media Luna on time and on budget, with first concentrate
production in Q4 2024 and commercial production in early 2025.”
CAPITAL EXPENDITURES
Total upfront expenditures related to the
development of Media Luna are tracking to the initial estimate of
$874.5 million. As at quarter-end, Torex had incurred $268.3
million of project period expenditures (31% to date) with $395.9
million of expenditures committed or incurred (45% to date).
Table 1: Media Luna Project – Project
Expenditures (April 1, 2022 through June 30, 2023)
Millions of U.S. dollars |
Project To DateQ2 2023 |
Project expenditures per 2022 Technical Report |
$848.4 |
Adjustment for Q1 2022 underspend |
$26.1 |
Total budgeted spend post March 31, 2022 |
$874.5 |
Expenditures incurred post March 31, 2022 |
($268.3) |
Remaining spend |
$606.2 |
Committed expenditures (inclusive of total project expenditures
incurred to date) |
$395.9 |
Uncommitted expenditures |
$478.6 |
1) Project period commenced on
April 1, 2022; excludes capital expenditures incurred prior to
Board approval on March 31, 2022.2) Project period
is defined as April 1, 2022 through December 31,
2024.3) Excludes borrowing costs capitalized.The
Company has guided $390 to $440 million of capital expenditures
related to the development of the Media Luna Project in 2023
($143.6 million accrued during H1 including $77.2 million in Q2).
Quarterly expenditures are expected to increase in H2 2023, and
remain relatively consistent through H1 2024, before declining as
development activities wind down ahead of commercial production,
which is anticipated in early 2025.
More detail on the Media Luna Project, including
the feasibility study results, can be found in the Company’s most
recent Technical Report dated effective March 16, 2022, filed on
March 31, 2022 (“Technical Report”).
PROJECT COMPLETION
As at quarter-end, development of Media Luna was
tracking to plan, with the project 35% complete, up from 24% at the
end of Q1 2023. Detailed engineering is at the 60% completion mark,
while procurement is 48% complete, with a majority of the schedule
critical purchase orders either awarded, or soon to be awarded.
Based on the current schedule, first concentrate production is on
track for late-2024.
Table 2: Media Luna Project – Project Completion
(April 1, 2022 through June 30, 2023)
|
Project To DateQ2 2023 |
Procurement |
48% |
Engineering |
60% |
Underground development/construction |
33% |
Surface construction |
27% |
Total Project |
35% |
Notes to Table1) Physical
progress measured starting as of April 1, 2022; excludes progress
made prior to Board approval on March 31,
2022.2) Project period is defined as April 1, 2022
through December 31, 2024.3) Total Project is
weighted average based on activity levels.
ProcurementDuring the quarter, the Company
executed numerous key purchase orders including the paste plant
conveyors and hoppers, underground material handling transfer
conveyors, rubber lined pipe spools for the tailings system feeding
the paste plant, and additional camp modules to accommodate our
underground construction contractor. For the surface plant, key
orders included medium voltage switchgear, pad mounted
transformers, air compressors, concrete reinforcing steel to
initiate foundation installation next quarter, and most notably the
ball mill motors with variable frequency drives.
Orders were also finalized with Maclean for our
battery electric vehicle (“BEV”) production support equipment and
with Rokion for our BEV personnel transport equipment. With respect
to contracts, both the vertical development and underground
construction contract evaluations were completed and awarded on a
combined basis to an already well established Torex contractor,
with a view to creating cost and productivity synergies. Contractor
mobilization has commenced.
EngineeringThe pace of detailed engineering
increased during the second quarter and continues to support
procurement activities. Key engineering activities included
detailing of the underground ore and waste handling infrastructure,
advancement of electrical supply and distribution systems within
the mine considering the selected BEV vendor’s fleet requirements.
For the surface facilities, final foundation designs for the water
treatment plant and flotation plant were issued and steel detailing
was initiated with a view to advancing fabrication. Electrical
foundations and layout designs were submitted and reviewed with the
federal power regulator CFE, with the overall design and
installation of the 115 kV and 230 kV systems and associated
infrastructure advancing to plan.
Underground Development and ConstructionSteady
progress was made in advancing the Guajes Tunnel and South Portal
Lower. Breakthrough of the Guajes Tunnel on the south side of the
Balsas River remains on track for Q1 2024, if not earlier. Delivery
of the Guajes conveyor table segments began during this period as
well as preparation of the tunnel for conveyor anchor installation
next quarter.
As of the end of June, the Guajes Tunnel had
advanced 4,500 metres and South Portal Lower had advanced 2,075
metres. Development of the main Media Luna Lower spiral ramp
continued and was completed in mid-July. This crew then moved to
advancing infrastructure excavation in the lower part of the mine
in preparation for the arrival of the underground construction
crews, all of which was enabled by the excellent progress of the
Guajes development crews. With this work complete post-quarter end,
the development crew will now commence advancing the Guajes Tunnel
from south to north.
Figure 1: Breakthrough of Guajes Tunnel on
schedule for early Q1 2024 (advance rates as at end of June)
Steady progress was also made on ventilation and
in-mine development during the quarter. The first 112 metre
ventilation raise was completed in Media Luna Upper and the second
175 metre raise pilot was started. As of the end of June, there
were eighteen active headings, including six in Media Luna Lower
and twelve in Media Luna Upper. Development across all headings
continues to advance well, with high monthly development rates
achieved as ground conditions are excellent.
Surface ConstructionOn the north side of the
Balsas River, civil works for the water treatment plant were
completed as well as rough grading for the 230 kV substation with
concrete foundations planned to start next quarter. The expanded
laydown area in Atzcala began receiving large equipment such as the
100 cubic metre Cu flotation cells and Guajes conveyor table
segments. Additional camp modules to house project staff were also
installed. Extension of the main water management culvert below the
area of the new flotation plant and Cu concentrate storage
facilities were significantly advanced, allowing remaining mass
civil works to begin. Relocation of the power distribution and
installation of new buried power conduits around the flotation
plant are expected to be completed early next quarter allowing
preparation for the start of the plant concrete foundations and
slab on grade.
On the south side of the Balsas River, expansion
of the construction camp pad continued, and work began on the
foundation preparation for the new kitchen and project office
areas. Slope remediation of the South Portal access road was
completed which allowed for advancing the construction of both the
south sedimentation and decant pond dams. Final slope reinforcement
of the west paste plant wall excavation was completed and grading
of the backup generator area for foundation work to start next
quarter was completed. Work advanced well on both the Mazapa – San
Miguel bypass road, which received final regulatory clearance
(archeological), and the Mazapa bridge, which will be in place by
Q4 2023 to accept deliveries of larger equipment related to both
the paste plant construction and the underground construction.
Operational ReadinessIn parallel with
development and construction activities, the surface and
underground operational readiness strategy is progressing to plan.
Operational readiness teams are accountable for ensuring that
processes and systems for all new work areas are established and
ready in advance of the handover from the project team to
operations. This includes workforce transition planning and
training (hiring for roles has commenced with initial job-specific
training expected to start shortly), developing the operating
strategy (including all standard operating procedures), maintenance
plans for all fixed and mobile equipment, blend and feed
strategies, detailed commissioning plans, first fills, concentrate
shipment logistics, and all other requirements to ensure a smooth
ramp up to commercial production in Q1 2025.
PROJECT EXECUTION PLAN
Based on progress made during Q2 2023, and a
detailed review of both the surface and underground schedules
completed late in the quarter, the overall project execution plan
is unchanged compared to the prior plan outlined within the
inaugural Media Luna update press release published on February 9,
2023, with some potential movement within the plan as set out
below.
Figure 2: Project execution plan for the Media
Luna Project
Initiatives to expedite the delivery of the
paste plant filter presses are progressing and the delivery
schedule has been improved by one month since the last update. The
Company is also working to expedite the underground electrical
equipment to reduce schedule risk given delivery times for the
underground electrical equipment are some of the longest for the
project. Plans for the installation of the early Phase 1 FeS
flotation circuit and water treatment plant have been adjusted.
Given the Company’s success with reducing cyanide consumption
levels over the last 18 months, the business benefits of a single
schedule for construction and commissioning the FeS circuit and
water treatment plant at the same time as the Cu flotation circuit
outweighed the benefits to landing the FeS circuit early. In terms
of underground development, schedule gains have been made since the
last update.
The current project plan relative to the
Technical Report reflects the Company’s estimates for the
completion of key project deliverables. These updated deliverables
have not impacted the overall project schedule given the original
plan had assumed the potential for schedule adjustments and the
possibility for supply chain disruptions.
ABOUT TOREX GOLD RESOURCES
INC.
Torex is an intermediate gold producer based in
Canada, engaged in the exploration, development, and operation of
its 100% owned Morelos Property, an area of 29,000 hectares in the
highly prospective Guerrero Gold Belt located 180 kilometres
southwest of Mexico City. The Company’s principal asset is the
Morelos Complex, which includes the El Limón Guajes (“ELG”) Mine
Complex, the Media Luna Project, a processing plant and related
infrastructure. Commercial production from the Morelos Complex
commenced on April 1, 2016 and an updated Technical Report for the
Morelos Complex was released in March 2022. Torex’s key strategic
objectives are to optimize and extend production from the ELG Mine
Complex, de-risk and advance Media Luna to commercial production,
build on ESG excellence, and to grow through ongoing exploration
across the entire Morelos Property.
FOR FURTHER INFORMATION, PLEASE
CONTACT:
TOREX GOLD RESOURCES INC. |
Jody Kuzenko |
Dan Rollins |
President and CEO |
Senior Vice President, Corporate Development & Investor
Relations |
Direct: (647) 725-9982 |
Direct: (647) 260-1503 |
jody.kuzenko@torexgold.com |
dan.rollins@torexgold.com |
|
|
QUALIFIED PERSONThe technical and scientific
information in this press release has been reviewed and approved by
Dave Stefanuto, P. Eng, Executive Vice President, Technical
Services and Capital Projects of the Company, and a qualified
person under National Instrument 43-101.
CAUTIONARY NOTES ON FORWARD LOOKING
STATEMENTSThis press release contains “forward-looking
statements” and “forward-looking information” within the meaning of
applicable Canadian securities legislation. Forward-looking
information includes, but is not limited to, statements that:
development activities related to the Media Luna Project continued
to advance well during Q2 with the Project remaining on budget and
on schedule; with $143.6 million of expenditures incurred through
H1 and the quarterly spend rate expected to increase further, full
year guided expenditures are trending towards the lower end of the
guided range of $390 million to $440 million; the Guajes Tunnel has
advanced 4,500 metres with breakthrough on track for early Q1 2024,
if not earlier; with development activities tracking to plan,
robust financial liquidity, and strong ongoing cash flow from El
Limón Guajes, the Company is well positioned physically and
financially to deliver Media Luna on time and on budget, with first
concentrate production in Q4 2024 and commercial production in
early 2025; total upfront expenditures related to the development
of Media Luna are tracking to the initial estimate of $874.5
million; quarterly expenditures are expected to increase in H2
2023, and remain relatively consistent through H1 2024, before
declining as development activities wind down ahead of commercial
production, which is anticipated in early 2025; as at quarter-end,
development of Media Luna was tracking to plan; based on the
current schedule, first concentrate production is on track for
late-2024; overall design and installation of the 115 kV and 230 kV
systems and associated infrastructure advancing to plan; relocation
of the power distribution and installation of new buried power
conduits around the flotation plant is expected to be completed
early next quarter allowing preparation for the start of the plant
concrete foundations and slab on grade; the Mazapa Bridge will be
in place by Q4 2023 to accept deliveries of larger equipment
related to both the paste plant construction and the underground
construction; the surface and underground operational readiness
strategy is progressing to plan; the overall project execution
plan; the current project plan relative to the Technical Report
reflects the Company’s estimates for the completion of key project
deliverables; and the Company’s key strategic objectives are to
optimize and extend production from the ELG Mining Complex, de-risk
and advance Media Luna to commercial production, build on ESG
excellence, and to grow through ongoing exploration across the
entire Morelos Property. Generally, forward-looking information can
be identified by the use of forward-looking terminology such as
“expect”, “plan”, “strategy”, “schedule”, “anticipate”, “guide”,
“continue”, “forecast”, or variations of such words and phrases or
statements that certain actions, events or results “will” occur or
are “on track” to occur. Forward-looking information is subject to
known and unknown risks, uncertainties and other factors that may
cause the actual results, level of activity, performance or
achievements of the Company to be materially different from those
expressed or implied by such forward-looking information,
including, without limitation, risks and uncertainties identified
in the technical report (“Technical Report”) titled ELG Mine
Complex Life of Mine Plan and Media Luna Feasibility Study, with an
effective date of March 16, 2022, and a filing date of March 31,
2022 and in the Company’s annual information form (“AIF”) and
management’s discussion and analysis (“MD&A”) or other unknown
but potentially significant impacts. Forward-looking information is
based on the reasonable assumptions, estimates, analyses and
opinions of management made in light of its experience and
perception of trends, current conditions and expected developments
as set out in the Technical Report, AIF and MD&A, and other
factors that management believes are relevant and reasonable in the
circumstances at the date such statements are made. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
the forward-looking information, there may be other factors that
cause results not to be as anticipated. There can be no assurance
that such information will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such information. Accordingly, readers should not place undue
reliance on forward-looking information. The Company does not
undertake to update any forward-looking information, whether as a
result of new information or future events or otherwise, except as
may be required by applicable securities laws.
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/fd8df85a-7939-44fc-9d46-1a834b44bac0
https://www.globenewswire.com/NewsRoom/AttachmentNg/0e63fcb6-7869-41f0-86cc-49ed244a2445
Torex Gold Resources (TSX:TXG)
Historical Stock Chart
From Nov 2024 to Dec 2024
Torex Gold Resources (TSX:TXG)
Historical Stock Chart
From Dec 2023 to Dec 2024