Galane Gold Ltd. (“Galane Gold” or the “Company”) (TSX-V: GG;
OTCQB: GGGOF) is pleased to provide an update on its Galaxy
property and to announce that it has initiated phase 2 of its
Galaxy expansion plan (“Phase 2”) to take production to over 43,000
ounces per year at an all in operating cash cost of less than $750
per ounce.(1) All dollar amounts referenced herein are stated
in United States dollars.
GALAXY UPDATE
Processing Plant Upgrade
Galane has commissioned and completed the
upgrade of the processing capacity at the plant at Galaxy (the
“Galaxy Plant”) from 15,000 tonnes per month to 50,000 tonnes per
month.(2)(3)(4) This means that the plant is now right sized for
the completion of Phase 2.
The following is a summarized description of the
work performed at the Galaxy Plant:
- Ore bins –
- Modification of
the first ore bin to allow the installation of a Titan 850 x 4000
apron feeder
- Installation of
three new chutes and five refurbished vibrating feeders with new
vibrating motors
- Upgrade of all
conveyors in the crushing area
- Installation of
a NMS JC850 jaw crusher into the existing structure
- Installation of
a new NMS CC100 hydraulic cone crusher
- Installation of
a 3.6m x 6.7m ball mill complete with cyclone tower and feed
conveyors with a milling capacity of 50,000 tonnes per month
- Refurbishment
of the existing flotation plant
- Installation of
two new rougher flotation units and three new scavenger units to
increase flotation capacity
- Conversion of
the old plane table building to house copper sulphate, sodium
isobutyl xanthate, and sodium hydrosulfide reagent mixing and
dosing systems
- Conversion of
old carbon-in-leach (“CIL”) tanks to slurry storage, pre flotation
conditioning tanks and concentrate storage tanks
- Installation of
two bright 200m2 x 76 plate, 4.25 tonnes/hour side bar hydraulic
concentrate filter presses
- Installation of
three concentrate transport conveyors to feed a new bagging
system
Mining Update
On December 14, 2020, Galaxy commenced mining at
both Princeton and Galaxy (the “Projects”) with its newly acquired
Rham mining fleet. Due to poor performance by the existing
contractor at the Projects, management of the Company made a
decision to capitalise and supervise the mining operations at the
Projects itself. It is expected that the introduction of the new
fleet and a new management structure will greatly improve the
performance of mining at the Projects.(3)
The Company’s Phase 1 mine plan (“Phase 1”)
involves mining at both the Princeton and Galaxy mineralised zones
to feed 10,000 tonnes per month from Princeton, and 20,000 tonnes
per month from Galaxy. With the introduction of the new mining
fleet, it is envisioned that the Projects will reach their
production targets by the fourth quarter of 2021 (“Q4
2021”).(3)
Phase 2 Expansion
The Company’s Board of Directors has approved a
plan and budget to commence Phase 2 at Galaxy as of January 1,
2021, and to take production to over 43,000 ounces per annum.(2)(3)
Galane now forecasts that Phase 2 will be completed by the fourth
quarter of 2022.(3)
Based on the results of the Technical Report (as
defined below), the Company redesigned the mine plan at Galaxy to
combine Phase 1 and Phase 2 of the mine plan and, as a result, has
accelerated the implementation of Phase 2. As the processing plant
is already sized to accommodate the increased production associated
with Phase 2, no further work is required to accommodate the
acceleration of the implementation of Phase 2. In addition, with
the current gold prices, the expansion can be fully funded by
Galane’s own cash flows, as well as paying off the debt relating to
the re-commencement of the operations.
Production update
Due to various factors in 2020, including the
COVID-19 pandemic and the performance of the existing contractor at
the Projects, the Company is not as advanced as it had forecast to
be. In addition, with the commencement of Phase 2 in January 2021,
Galane’s existing fleet is required to do additional development
beyond what was originally planned, to ultimately accelerate the
completion of Phase 2. To address this issue, the Company will be
adding to its mining fleet in 2021.(3) However, the completion of
Phase 1 will be delayed until the arrival of the new additions to
its mining fleet.
Galane’s currently anticipates that Phase 1 will
be completed in Q4 2021, in line with mining reaching its
production targets.(3) This will translate to an annualised
production of over 26,000 ounces per year at an all in operating
cash cost of less than $900 per ounce.(1)(3)
PHASE 3(3)
The Company’s Board of Directors has also
approved that work should commence on a Phase 3 expansion plan
(“Phase 3”) with an objective to increase production to 60,000
ounces per annum. It is currently envisaged that Phase 3 will take
the form of a new CIL plant and a new oxidisation step in the
processing plant. This will increase recoveries at the processing
plant from 75% to 90%. Management will work on an internal
preliminary economic assessment during 2021.
Galane CEO, Nick Brodie, commented: “Giant steps
continue to be made at Galaxy and I congratulate the team for
completing the processing plant upgrade and the implementation of a
new mining programme.
The work done to accelerate the implementation
of Phase 2 is of great benefit to Galane and puts us in a strong
position to profit from the current gold environment in advance of
our original plans.
I believe it is time for us to stop talking
about expansion phases as I expect that once we complete the work
to support Phase 3 we will already be planning Phase 4. It is the
reality of the camp resource that we have at Galaxy that there is
the potential to continue to expand production in a staged,
self-funded, process for years to come.”
About Galane Gold
Galane Gold is an un-hedged gold producer and
explorer with mining operations and exploration tenements in
Botswana and South Africa. Galane Gold is a public company and its
shares are quoted on the TSX Venture Exchange under the symbol “GG”
and the OTCQB under the symbol “GGGOF”. Galane Gold’s management
team is comprised of senior mining professionals with extensive
experience in managing mining and processing operations and
large-scale exploration programmes. Galane Gold is committed to
operating at world-class standards and is focused on the safety of
its employees, respecting the environment, and contributing to the
communities in which it operates.
Notes
(1) |
Total all in operating cash cost is a non-generally accepted
accounting principles ("GAAP") measure. Refer to “Non-GAAP
Measures” below and “Supplemental Information to Management’s
Discussion and Analysis – Cash Costs” in the Company’s Management’s
Discussion and Analysis for the three and nine months ended
September 30, 2020 (the “MD&A”), for reconciliation to measures
reported in the Company’s financial statements. |
(2) |
The deposits at the Galaxy mine are supported by a technical report
entitled “NI 43-101 Technical Report on the Galaxy Gold Mine, South
Africa” which was issued on July 3, 2020 (the “Technical Report”),
with an effective date of June 29, 2020, a copy of which is
available under the Company’s profile on www.sedar.com. The
preliminary economic assessment (“PEA”) supported by the Technical
Report is preliminary in nature as the resources included in the
PEA are comprised 54% of inferred mineral resources. Inferred
mineral resources are considered too speculative geologically to
have the economic considerations applied to them that would enable
them to be categorized as mineral reserves. There is no certainty
that the PEA will be realized. |
(3) |
This is forward-looking information and is based on a number of
assumptions. See “Cautionary Notes”. |
(4) |
The Company is not basing its decision to expand the throughput
capacity of the Galaxy mine’s processing plant to 50,000 tonnes per
month on a feasibility study of mineral reserves demonstrating
economic and technical viability of production at such levels, and
as a result there is increased uncertainty and there are multiple
technical and economic risks of failure which are associated with
producing at such plant’s throughput capacity. These risks, among
others, include applying economic analysis to resources and
reserves, more detailed metallurgy and a number of specialized
studies in areas such as mining and recovery methods, market
analysis, and environmental and community impacts. |
Non-GAAP Measures
This press release makes reference to certain
non-GAAP measures including operating cash cost. These measures are
not recognized measures under Canadian GAAP and do not have a
standardized meaning prescribed by GAAP. Therefore these measures
may not be comparable to similar measures presented by other
issuers. However, the Company believes that these measures are
useful to assist readers in evaluating the total costs of producing
gold from current operations. For more information regarding the
non-GAAP measures used by the Company, see the information under
the heading “Supplemental Information to Management’s Discussion
and Analysis” in the MD&A. The financial statements for the
three and nine months ended September 30, 2020, and the MD&A
are available on SEDAR at www.sedar.com.
Cautionary Notes
Certain statements contained in this press
release constitute “forward-looking statements”. All statements
other than statements of historical fact contained in this press
release, including, without limitation, those regarding the
Company’s future financial position and results of operations,
strategy, proposed acquisitions, plans, objectives, goals and
targets, and any statements preceded by, followed by or that
include the words “believe”, “expect”, “aim”, “intend”, “plan”,
“continue”, “will”, “may”, “would”, “anticipate”, “estimate”,
“forecast”, “predict”, “project”, “seek”, “should” or similar
expressions or the negative thereof, are forward-looking
statements. These statements are not historical facts but instead
represent only the Company’s expectations, estimates and
projections regarding future events. These statements are not
guarantees of future performance and involve assumptions, risks and
uncertainties that are difficult to predict. Therefore, actual
results may differ materially from what is expressed, implied or
forecasted in such forward-looking statements.
Additional factors that could cause actual
results, performance or achievements to differ materially include,
but are not limited to: the Company’s dependence on two mineral
projects; gold price volatility; risks associated with the conduct
of the Company’s mining activities in Botswana and South Africa;
regulatory, consent or permitting delays; risks relating to the
Company’s exploration, development and mining activities being
situated in Botswana and South Africa; risks relating to reliance
on the Company’s management team and outside contractors; risks
regarding mineral resources and reserves; the Company’s inability
to obtain insurance to cover all risks, on a commercially
reasonable basis or at all; currency fluctuations; risks regarding
the failure to generate sufficient cash flow from operations; risks
relating to project financing and equity issuances; risks arising
from the Company’s fair value estimates with respect to the
carrying amount of mineral interests; mining tax regimes; risks
arising from holding derivative instruments; the Company’s need to
replace reserves depleted by production; risks and unknowns
inherent in all mining projects, including the inaccuracy of
reserves and resources, metallurgical recoveries and capital and
operating costs of such projects; contests over title to
properties, particularly title to undeveloped properties; laws and
regulations governing the environment, health and safety; the
ability of the communities in which the Company operates to manage
and cope with the implications of COVID-19; the economic and
financial implications of COVID-19 to the Company; operating or
technical difficulties in connection with mining or development
activities; lack of infrastructure; employee relations, labour
unrest or unavailability; health risks in Africa; the Company’s
interactions with surrounding communities and artisanal miners; the
Company’s ability to successfully integrate acquired assets; risks
related to restarting production; the speculative nature of
exploration and development, including the risks of diminishing
quantities or grades of reserves; development of the Company’s
exploration properties into commercially viable mines; stock market
volatility; conflicts of interest among certain directors and
officers; lack of liquidity for shareholders of the Company; risks
related to the market perception of junior gold companies; and
litigation risk. Management provides forward-looking statements
because it believes they provide useful information to investors
when considering their investment objectives and cautions investors
not to place undue reliance on forward-looking information.
Consequently, all of the forward-looking statements made in this
press release are qualified by these cautionary statements and
other cautionary statements or factors contained herein, and there
can be no assurance that the actual results or developments will be
realized or, even if substantially realized, that they will have
the expected consequences to, or effects on, the Company. These
forward-looking statements are made as of the date of this press
release and the Company assumes no obligation to update or revise
them to reflect subsequent information, events or circumstances or
otherwise, except as required by law.
Information of a technical and scientific nature
that forms the basis of the disclosure in the press release has
been approved by Kevin Crossling MAusIMM, Pr. Sci. Nat. and
Business Development Manager for Galane Gold, and a “qualified
person” as defined by National Instrument 43-101 - Standards of
Disclosure for Mineral Projects. Mr. Crossling has verified the
technical and scientific data disclosed herein and has conducted
appropriate verification on the underlying data.
Neither the TSX Venture Exchange nor its
regulation services provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
For further information please
contact:Nick BrodieCEO, Galane Gold Ltd.+ 44
7905089878Nick.Brodie@GalaneGold.comwww.GalaneGold.com
Golconda Gold (TSXV:GG)
Historical Stock Chart
From Dec 2024 to Jan 2025
Golconda Gold (TSXV:GG)
Historical Stock Chart
From Jan 2024 to Jan 2025