Southern Pacific Resource Corp. ("Southern Pacific" or the
"Company") (TSX VENTURE: STP) is pleased to announce that it has
signed a definitive agreement with its working interest partner,
Bounty Developments Ltd. ("Bounty"), to acquire Bounty's entire 20%
working interest in 59 sections of land in the McKay block. As part
of the agreement, Southern Pacific will also purchase 20% of
Bounty's working interest in 32 sections of land adjacent to and
near Southern Pacific's MacKenzie block (the "Acquisition").
The entire package of reserves, resources and undeveloped land
will be purchased for a total of $33.0 million, consisting of 20%
equity ($6.6 million) and 80% cash ($26.4 million). The 20% equity
will be issued as common shares of the Company at a price
equivalent to the applicable 10 day volume weighted average trading
price of the shares which equals approximately 6.47 million shares
at a price of $1.02 per share. The effective and closing date of
the Acquisition is expected to be June 1, 2010. Funding for the
cash portion of the Acquisition will be made through Southern
Pacific's existing cash flow and debt facility.
The acquisition of Bounty's working interest at McKay results in
Southern Pacific having an undivided 100% working interest in all
its McKay lands, including the 10.5 sections within the Company's
STP-McKay Steam-Assisted Gravity Drainage ("SAGD") project. The
STP-McKay SAGD project is a 12,000 bbl/d in-situ thermal project
that is in the application approval process. Southern Pacific
submitted the application to Alberta Environment and the Alberta
Energy Resources Conservation Board in May 2009 with approval
expected in the second half of 2010. Construction of the project is
expected to commence this fall immediately after regulatory
approval is obtained. The acquisition of the remaining 20% working
interest ensures that the responsibility of funding the STP-McKay
project falls entirely within Southern Pacific's control. With
strengthening markets and cash flow from Senlac, Southern Pacific
remains confident that the funding requirements for STP-McKay will
be completed this year.
Within the Acquisition, Southern Pacific also acquired a 20%
working interest in 32 sections of land formerly operated by Patch
International Ltd., and known as Ells. There are 12 sections of
these lands directly adjacent to Southern Pacific's 18-section
MacKenzie block (100% working interest). These 12 sections have had
coreholes drilled and contingent resource has been assigned by an
independent reserves auditor. The acquired lands will allow
additional proprietary technical data to be incorporated into the
Company's records, and allow for lower cost exploration around its
100% working interest MacKenzie block, which has not yet been
explored.
The complete breakdown of Reserves and Contingent Resources
associated with the Acquisition are described in the tables
below:
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Working Interest Volumes MMbbl(3)(4)
----------------------------------------------------------------------------
McKay(1)
Probable Reserves (2P) 13.5
Best (P50) Estimate Contingent Resources 0.9
----
2P Reserves + Best Estimate Contingent 14.4
Probable and Possible Reserves (3P) 24.5
High (P10) Estimate Contingent Resources 2.6
----
3P Reserves + High Estimate Contingent 27.1
----------------------------------------------------------------------------
----------------------------------------------------------------------------
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Working Interest Volumes MMbbl(3)(4)
----------------------------------------------------------------------------
Ells(2)
Low (P90) Estimate Contingent Resources 23.4
Best (P50) Estimate Contingent Resources 34.8
High (P10) Estimate Contingent Resources 50.8
----------------------------------------------------------------------------
----------------------------------------------------------------------------
(1) McDaniel and Associates report effective June 30, 2009 completed for
Southern Pacific Resource Corp.
(2) McDaniel and Associates report effective May 31, 2007 completed for
Bounty Developments Ltd.
(3) The estimates of reserves for individual properties may not reflect the
same confidence level as estimates of reserves and future net revenue
for all properties, due to the effects of aggregation. There is no
certainty that it will be commercially viable to produce any portion of
the resources.
(4) Contingencies which prevent the classification as reserves for the
remaining portion of McKay and at Ells include the drilling of a greater
density of core holes throughout the areas with delineated contingent
resources and the submission of an application for a SAGD project on
such lands.
A short presentation, which includes details and maps
illustrating this acquisition, has been added to the Company's
website (www.shpacific.com) under the Presentations tab.
Mr. Jon Clark, an independent director of the Company, is a
shareholder of Tlell Developments Inc. Tlell Developments Inc. has
a 7.5% beneficial interest in Bounty's interest in the Ells block
and an 8.5% beneficial interest in Bounty's interest in the McKay
block. The board of directors of the Company has approved the
Acquisition, with Mr. Clark abstaining from voting on the matter.
The Company has determined that exemptions from the various
requirements of Multilateral Instrument 61-101 and TSX Venture
Exchange Policy 5.9 are available for the Acquisition. The
Acquisition is subject to TSX Venture Exchange acceptance.
Visit our website at: www.shpacific.com.
Readers' Advisory
Barrel of Oil Equivalent: Where amounts are expressed on a
barrel of oil equivalent ("boe") basis, natural gas volumes have
been converted to boe at a ratio of 6,000 cubic feet of natural gas
to one barrel of oil equivalent. This conversion ratio is based
upon an energy equivalent conversion method primarily applicable at
the burner tip and does not represent value equivalence at the
wellhead. Boe figures may be misleading, particularly if used in
isolation.
Definitions
"Best (P50)" means the best estimate of the quantity that will
actually be recovered. It is equally likely that the actual
remaining quantities recovered will be greater or less than the
best estimate. If probabilistic methods are used, there should be
at least a 50 percent probability (P50) that the quantities
actually recovered will equal or exceed the best estimate.
"Contingent Resources" means those quantities of petroleum
estimated, as of a given date, to be potentially recoverable from
known accumulations using established technology or technology
under development, but which are not currently considered to be
commercially recoverable due to one or more contingencies.
Contingencies may include factors such as economic, legal,
environmental, political, and regulatory matters or a lack of
markets. It is also appropriate to classify as contingent resources
the estimated discovered recoverable quantities associated with a
project in the early evaluation stage.
"High (P10)" means an optimistic estimate of the quantity that
will actually be recovered. It is unlikely that the actual
remaining quantities recovered will exceed the high estimate. If
probabilistic methods are used, there should be at least a 10
percent probability (P10) that the quantities actually recovered
will equal or exceed the high estimate.
"Low (P90)" means a conservative estimate of the quantity that
will actually be recovered. It is likely that the actual remaining
quantities recovered will exceed the low estimate. If probabilistic
methods are used, there should be at least a 90 percent probability
(P90) that the quantities actually recovered will equal or exceed
the low estimate.
"Probable reserves" means those additional reserves that are
less certain to be recovered than proved reserves. It is equally
likely that the actual remaining quantities recovered will be
greater or less than the sum of the estimated Proved plus Probable
reserves.
"Possible reserves" means those additional reserves that are
less certain to be recovered than probable reserves. It is unlikely
that the actual remaining quantities recovered will exceed the sum
of the estimated Proved plus Probable plus Possible reserves.
"Proved reserves" means those reserves that can be estimated
with a high degree of certainty to be recoverable. It is likely
that the actual remaining quantities recovered will exceed the
estimated Proved reserves.
Safe Harbour
This news release contains certain "forward-looking information"
within the meaning of such statements under applicable securities
law including estimates as to: future production, operations,
operating costs, commodity prices, administrative costs, commodity
price risk management activity, acquisitions and dispositions,
capital spending, access to credit facilities, income and oil
taxes, regulatory changes, and other components of cash flow and
earnings anticipated discovery of commercial volumes of bitumen,
the timeline for the achievement of anticipated exploration,
anticipated results from the current drilling program and, subject
to regulatory approval and commercial factors, the commencement or
approval of any SAGD project.
Forward-looking information is frequently characterized by words
such as "plan", "expect", "project", "intend", "believe",
"anticipate", "estimate", "may", "will", "potential", "proposed"
and other similar words, or statements that certain events or
conditions "may" or "will" occur. These statements are only
predictions. Forward-looking information is based on the opinions
and estimates of management at the date the statements are made,
and are subject to a variety of risks and uncertainties and other
factors that could cause actual events or results to differ
materially from those projected in the forward-looking statements.
These factors include, but are not limited to, the ability to
complete the Acquisition on the proposed terms or at all, the
inherent risks involved in the exploration and development of
conventional oil and gas properties and of oil sands properties,
difficulties or delays in start-up operations, the uncertainties
involved in interpreting drilling results and other geological
data, fluctuating oil prices, the possibility of unanticipated
costs and expenses, uncertainties relating to the availability and
costs of financing needed in the future and other factors including
unforeseen delays. As an oil sands enterprise in the development
stage, with some conventional production Southern Pacific faces
risks including those associated with exploration, development,
start-up, approvals and the continuing ability to access sufficient
capital from external sources if required. Actual timelines
associated may vary from those anticipated in this news release and
such variations may be material. Industry related risks could
include, but are not limited to, operational risks in exploration,
development and production, delays or changes in plans, risks
associated to the uncertainty of reserve estimates, health and
safety risks and the uncertainty of estimates and projections of
production, costs and expenses. For a description of the risks and
uncertainties facing Southern Pacific and its business and affairs,
readers should refer to Southern Pacific's most recent Annual
Information Form. Southern Pacific undertakes no obligation to
update forward-looking statements if circumstances or management's
estimates or opinions should change, unless required by law.
The reader is cautioned not to place undue reliance on this
forward-looking information.
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
Contacts: Southern Pacific Resource Corp. Byron Lutes President
& CEO 403-269-1529 blutes@shpacific.com Southern Pacific
Resource Corp. Dave Antony Chairman 403-269-5219
dantony@shpacific.com www.shpacific.com
Southern Pacific Resource Corp. (TSXV:STP)
Historical Stock Chart
From Dec 2024 to Jan 2025
Southern Pacific Resource Corp. (TSXV:STP)
Historical Stock Chart
From Jan 2024 to Jan 2025