OSLO,
Norway, July 6, 2023 /PRNewswire/ -- BlueNord ASA
("BlueNord" or the "Company") is pleased to announce significant
progress of the two gas turbine generators (GTGs) on Tyra II which
have now been powered up.
Once Tyra II is producing again, the two gas turbine
generators will, on a continuous basis and with the highest
environmental standards, convert natural gas to mechanical energy,
enabling production and export from the Tyra field. In addition, a
third GTG will be on stand-by.
The powering up of the two gas turbine generators marks a
crucial step towards first gas, and the next step for the GTGs
to be available for continuous operations is completion of the
installation of the sea water lift pumps. The second GTG was
powered up a month ahead of schedule, and further safeguards first
gas from Tyra II in December
2023.
Reference is made to Tyra II's
website: https://tyra2.dk/en/tyra-ii-is-ready-to-be-powered-up/
BlueNord will announce its second quarter results on
12 July 2023.
Contact:
Cathrine Torgersen, EVP Investor
Relations & ESG
Phone: +47 915 28 501
Email: cathrine.torgersen@bluenord.com