Dasa Uranium Project On Schedule to Produce
Yellowcake in Q1 2025
TORONTO, May 11, 2023
/CNW/ - Global Atomic Corporation ("Global Atomic" or the
"Company"), (TSX: GLO) (OTCQX: GLATF) (FRANKFURT: G12) announced
today its operating and financial results for the quarter ended
March 31, 2023.
HIGHLIGHTS
Dasa Uranium Project
- The Company revised its Dasa Project, Phase 1, Feasibility
Study which:
-
- confirmed a reserve for the Dasa Project of 4.1 million tonnes
grading 5,267 ppm for a total of 47.2 million pounds
U3O8.
- outlines an initial, Phase 1, 12-year mine schedule at a
production throughput of 1,000 tonnes per day to produce 44.1
million pounds U3O8.
- estimates cash costs, including royalties and all Niger off-site costs, of US$19.02/lb U3O8 and an
all-in sustaining cost of US$22.13/lb
U3O8.
- estimates initial capital expenditures to be US$208 million.
- Calculated for Phase 1 using a U3O8 price
of US$35/lb an after-tax NPV8 of
US$147 million and an after-tax IRR
of 22.3% and using a U3O8 price of
US$50/lb an after-tax IRR of 44.4%
and at US$60 the after-tax IRR would
be 56.9%.
- The access ramp to the underground Dasa deposit has progressed
325 meters at the end of April 2023,
about 40% complete before reaching the ore level.
Dasa Uranium Project: Subsequent events
- On May 8, 2023, the Company
formalized its June 2022 Letter of
Intent by signing a definitive agreement with a second major North
American utility for their procurement of up to 2.1 million pounds
U3O8 from Dasa within a multi-year delivery
window beginning in 2025.
- The Company is in the process of completing a revised Mineral
Resource Estimate ("MRE") for the Dasa Project to include results
from the 16,000-meter drill program initiated at the end of
2021.
- Long-lead items have been selected and are in the process of
being ordered.
Turkish Zinc Joint Venture
- In early March 2023, the
recycling plant resumed operation following a thorough inspection
and assessment of the facility after the earthquake of February 6, 2023.
- The Turkish Zinc Joint Venture ("BST" or the "Turkish JV")
plant processed 6,125 tonnes EAFD in Q1 2023 as the plant was
shutdown at the time of the initial earthquake and remained down
until regional infrastructure could support a safe resumption of
operations in early March.
- The Company's share of the Turkish JV EBITDA was a loss of
$0.4 million in Q1 2023 ($3.4 million gain in Q1 2022).
- The zinc contained in concentrate sales in Q1 2023 was 3.7
million pounds.
- The average monthly LME zinc price was US$1.42/lb in Q1 2023.
- The revolving credit facility of the Turkish JV was
US$12.47 million at the end of Q1
2023 (Global Atomic share – US6.1 million)
- The cash balance of the Turkish JV was US$0.6 million at the end of Q1 2023.
Corporate
- The Company completed a bought deal short form prospectus
offering of 18,666,667 Units on March 17,
2023, at a price of $3.00 per
Unit for gross proceeds of $56,002,501. Each Unit comprised one common share
and one-half warrant exercisable at $4.00 per common share.
- Global Atomic continues to receive quarterly management fees
and monthly sales commissions from the Turkish JV ($131,000 in Q1 2023 compared to $423,000 in Q1 2022), helping to offset corporate
overhead costs.
- Cash balance at March 31, 2023,
was $52 million.
Global Atomic President and CEO, Stephen
G. Roman commented, "I am pleased to report on how well
the Dasa Project development is progressing. Our current cash
position allows us to continue with project development on schedule
and our bank financing is progressing. We continue to advance
our ramp access to the orebody, are placing orders for long-lead
plant equipment and have already built out a full in-country mining
team with experienced miners and a complement of trainees from the
villages near the Project. The ramp development now exceeds
325 meters and is expected to reach the top of the ore body in Q4
2023."
"We are pleased to report that mill equipment costs to date
are in line with our Feasibility Study estimates which were
calculated at the peak of inflation for equipment and shipping
costs that have since declined to near pre-pandemic
levels.
Further, our estimated cost structure allows the Dasa Project
to be profitable at a uranium price of US$35/lb, improving to an IRR of over 44% at
today's current spot price, now over US$50/lb. Having signed two off-take
agreement with Western utilities at favourable prices and based on
positive discussions at the recent World Nuclear Fuel Cycle
conference in The Hague, we expect
additional offtake agreements will materialise as we continue to
de-risk the Dasa Project".
OUTLOOK
Dasa Uranium Project
- The Company's banking syndicate is now expected to finalize a
term sheet by the end of Q2 2023 and to approve the debt facility
of the Project Financing prior to the end of Q3 2023.
- Additional uranium sales contracts with international electric
utilities are expected once Project Financing details are
announced.
- The Company plans to issue a newly updated MRE in Q2 2023,
followed by a revised Feasibility Study in Q4 2023.
- Detailed engineering is in progress with earthworks underway
and civil works expected to begin in Q4 2023. Components for the
Dasa Plant construction will begin to arrive on site by the end of
Q4 2023.
- The Main Decline to the Dasa deposit is expected to reach the
top of the Flank Zone ore in Q4 2023, when initial Development Ore
will be brought to surface.
Turkish Zinc Joint Venture
- The Electric Arc Furnace Dust ("EAFD") recycling plant is
expected to operate at full capacity through to the end of
May 2023, however supply
interruptions of EAFD are expected to continue until Turkish steel
mills resume historic operating levels.
COMPARATIVE RESULTS
The following table summarizes comparative results of operations
of the Company:
MD&A TABLE -
HIGHLIGHTS
|
|
|
|
|
|
|
|
Three months ended
March 31,
|
(all amounts in
C$)
|
|
2023
|
|
2022
|
|
|
|
|
|
Revenues
|
|
$
130,841
|
|
$
432,116
|
|
|
|
|
|
General and
administration
|
|
2,832,831
|
|
3,176,234
|
Share of equity loss
(earnings)
|
|
1,388,274
|
|
(1,433,337)
|
Other
expense
|
|
-
|
|
606,711
|
Finance
income
|
|
(71,468)
|
|
(29,817)
|
Foreign exchange
loss
|
|
1,210,716
|
|
180,921
|
Net
loss
|
|
$
(5,229,512)
|
|
$
(2,068,596)
|
Net loss attributable
to:
|
|
|
|
|
Shareholders of the
Company
|
|
(5,237,663)
|
|
(2,068,596)
|
Non-controlling
interests
|
|
8,151
|
|
-
|
Other comprehensive
income (loss)
|
|
$
2,718,776
|
|
$
(2,248,684)
|
Comprehensive
loss
|
|
$
(2,510,736)
|
|
$
(4,317,280)
|
Comprehensive loss
attributable to:
|
|
|
|
|
Shareholders of the
Company
|
|
(2,518,218)
|
|
(4,317,280)
|
Non-controlling
interests
|
|
7,482
|
|
-
|
|
|
|
|
|
Basic and diluted net
loss per share
|
|
($0.03)
|
|
($0.01)
|
|
|
|
|
|
Basic
weighted-average
number of shares outstanding
|
|
184,583,128
|
|
174,878,070
|
Diluted
weighted-average
number of shares outstanding
|
|
184,583,128
|
|
174,878,070
|
|
|
|
|
|
|
|
March
31,
|
|
December
31,
|
|
|
2023
|
|
2022
|
|
|
|
|
|
Cash
|
|
$ 52,053,620
|
|
$
8,400,008
|
Property, plant and
equipment
|
|
91,353,371
|
|
82,234,716
|
Exploration &
evaluation assets
|
|
1,193,347
|
|
1,115,983
|
Investment in joint
venture
|
|
16,587,783
|
|
16,387,040
|
Other assets
|
|
3,316,136
|
|
2,118,258
|
Total
assets
|
|
$
164,504,257
|
|
$
110,256,005
|
|
|
|
|
|
Total
liabilities
|
|
$
10,665,997
|
|
$
8,746,681
|
|
|
|
|
|
Shareholders' equity
|
|
$
153,838,260
|
|
$
101,509,324
|
The consolidated financial statements reflect the equity method
of accounting for Global Atomic's interest in the Turkish JV. The
Company's share of net earnings and net assets are disclosed in the
notes to the financial statements. See also the commentary
above under "Turkish Zinc EAFD Operations."
Revenues include management fees and sales
commissions received from the joint venture. These are based on
joint venture revenues generated and zinc concentrate tonnes
sold.
General and administration costs at the corporate
level include general office and management expenses, stock option
awards, depreciation, costs related to maintaining a public
listing, professional fees, audit, legal, accounting, tax and
consultants' costs, insurance, travel, and other miscellaneous
office expenses.
Share of net earnings from joint
venture represents Global Atomic's equity share of net
earnings from the Turkish JV. In view of limited production,
lower zinc prices in 2022, extraordinary expenses due to the
earthquake, resulting in a negative equity income of $1.4 million.
Uranium Business
Mineral Resources and Reserves
On January 9, 2023, the Company
revised its Dasa Project, Phase 1, Feasibility Study ("Feasibility
Study"), which was revised primarily to apply "zero grade" to
Inferred Resources included in certain stopes of the Phase 1 Mine
Plan.
The Zones shown in the above section vary in grades, with Zone 1
(Flank Zone) contributing the largest portion of the
U3O8 tonnes:
|
|
|
|
Feasibility Study
including
Inferred Resources
|
Revised Feasibility
Study with
"zero grade" Inferred
Resources
|
Zone
|
In-situ
Tonnes
|
U3O8 PPM
|
RoM
Tonnes
|
RoM
U3O8 PPM
|
RoM
U3O8
Tonnes
|
RoM
U3O8
PPM
|
RoM
U3O8
Tonnes
|
1
|
2,464,615
|
6,980
|
2,316,047
|
6,887
|
15,950
|
6,847
|
15,856
|
2
|
264,339
|
3,621
|
256,078
|
3,574
|
915
|
3,540
|
906
|
3
|
656,114
|
3,093
|
633,541
|
3,056
|
1,936
|
2,480
|
1,571
|
4
|
604,673
|
3,003
|
584,616
|
2,966
|
1,734
|
2,872
|
1,679
|
5
|
478,916
|
3,312
|
463,345
|
3,269
|
1,515
|
3,031
|
1,405
|
Total
|
4,468,657
|
5,279
|
4,253,626
|
5,184
|
22,050
|
5,035
|
21,417
|
The inferred resources, representing 4.4% of total mineral
resources to be mined in Phase I, was treated as zero grade waste
in the revised feasibility study. Impacts of this grade change are
summarized in the table below:
|
Original
Feasibility
Study
|
Revised
Feasibility
Study
|
Average mill feed grade
(ppm)
|
5,184
|
5,267
|
Total production over
12-year Phase 1 mine plan (Mlb)
|
45.4
|
44.1
|
Average cash
cost1 (US$/lb)
|
18.91
|
19.02
|
Average AISC
(US$/lb)
|
21.93
|
22.13
|
Internal After-tax Rate
of Return ("IRR") @ $US35/lb
|
22.7 %
|
22.3 %
|
After-tax Net Present
Value ("NPV8") (US$ millions) @ $US35/lb
|
157
|
147
|
Internal Rate of Return
("IRR") @ $US50/lb
|
44.6 %
|
44.4 %
|
After-tax Net Present
Value ("NPV8") (US$ millions) @ $US50/lb
|
468
|
456
|
Reserve Expansion
The Company completed a 15,000-meter drill program at its Dasa
Project that began in Q4 2021, which due to its success was
expanded to include another 1,000 meters. Drill results indicate
that Zones 2, 2a and 2b now represent
a contiguous zone that joins up with Zone 3 and is estimated to be
approximately three times larger than initially defined (see the
longitudinal depiction below). Recent drilling has also targeted
the extension of Zone 4.
On the strength of results from the overall drill program,
Global Atomic is updating the Dasa Mineral Resource Estimate
("MRE") and will in turn update its Mine
Plan which is expected to result in larger and
contiguous mining Zones, reduced underground development work
between the Zones, lower operating costs and an increase in
mineable reserves.
The updated MRE is expected to be completed in Q2 2023. The
Company plans to use the revised MRE to complete a revised mine
plan for the Dasa Project, followed by a revised Feasibility Study
in Q4 2023.
Niger Mining Company
Under Niger's Mining Code, a
Niger mining company must be
incorporated to carry out mining activities. Société Minière de
Dasa S.A. ("SOMIDA") was incorporated on August 11, 2022. The Republic of Niger received its 10% free carried interest
in the shares of SOMIDA and elected to subscribe for an additional
10%, resulting in a total ownership of 20% of the shares. Under the
terms of the Company's Mining Agreement, the Republic of
Niger commits to fund its
proportionate share of capital costs and operating deficits for the
additional 10% interest. The Republic of Niger has no further option to increase its
ownership.
Dasa Mine Development and Construction
The Company has entered into an agreement with CMAC-Thyssen
International Inc. ("CMAC"), a contract miner based in Val d'Or, Quebec to provide contract mining
services in the development of the Dasa underground mine over the
first 24 months of mining. Following the March 2020 closure of the Cominak underground
uranium mine in Arlit, there is a pool of skilled miners available
to the Company in Niger.
CMAC is providing training, development and oversight of the
Niger workforce with the new
equipment that will be used at site. Initial mining will
comprise only ramp development during the first 12 months, followed
by access and level development.
The first blast of the portal took place on November 5, 2022, marking the start of the
underground development. Surface infrastructure to support CMAC was
completed during 2022. At the Dasa Mine, operations are
proceeding on schedule with 325 meters of underground development
completed at the end of April 2023 on
the decline ramp plus for re-muck and safety bays.
The Company engaged DCPL and Lycopodium to commence the EPCM
process to build Dasa's ore processing plant. DCPL is focusing on
the Basic and Detailed Engineering required for the final design of
the Dasa Process Plant. Lycopodium is providing project management,
procurement, project controls and a project execution plan
services. Lycopodium's engagement is expected to extend to
construction management in view of their extensive West African
experience.
Project Financing
Global Atomic has received a Letter of Interest ("LOI") from
Export Development Canada ("EDC") confirming their interest in
working with the Company on project financing US$75 million of the Dasa Project. On
June 15, 2022, Global Atomic also
received additional Letters of Intent such that a syndicate has
been formed to finance the Dasa Project. The syndicate is comprised
of North American financial institutions, including EDC.
Due diligence has been underway since June 2022 and has largely been completed. The
Company's banking syndicate is expected to finalize a term sheet by
the end of Q2 2023 and to complete documentation and close the debt
facility by the end of Q3 2023.
Turkish Zinc EAFD Operations
The Company's Turkish EAFD business operates through a joint
venture with Befesa Zinc S.A.U. ("Befesa"), an industry leading
Spanish company that operates a number of Waelz kilns throughout
Europe, North America and Asia. On October 27,
2010, Global Atomic and Befesa established joint venture,
known as Befesa Silvermet Turkey, S.L. ("BST" or the "Turkish JV")
to operate an existing plant and develop the EAFD recycling
business in Türkiye. BST is held 51% by Befesa and 49% by Global
Atomic. A Shareholders Agreement governs the relationship between
the parties. Under the terms of the Shareholders Agreement,
management fees and sales commissions are distributed pro rata to
Befesa and Global Atomic. Net income earned each year in Türkiye,
less funds needed to fund operations, must be distributed to the
partners annually, following the BST annual meeting, which is
usually held in the second quarter of the following year.
BST owns and operates an EAFD processing plant in Iskenderun,
Türkiye. The plant processes EAFD containing 25% to 30% zinc that
is obtained from electric arc steel mills, and produces a zinc
concentrate grading 65% to 68% zinc that is then sold to zinc
smelters.
Global Atomic holds a 49% interest in the Turkish JV and, as
such, the investment is accounted for using the equity basis of
accounting. Under this basis of accounting, the Company's share of
the BST's earnings is shown as a single line in its Consolidated
Statements of Income (Loss).
The following table summarizes comparative operational metrics
of the Iskenderun facility.
SUMMARY OF
OPERATIONS
|
|
|
|
|
|
|
|
|
Three months ended
March 31,
|
|
2023
|
|
2022
|
|
100 %
|
|
100 %
|
|
|
|
|
Exchange rate (C$/TL,
average)
|
13.96
|
|
11.02
|
Exchange rate (US$/C$,
average)
|
1.35
|
|
1.27
|
|
|
|
|
Exchange rate (C$/TL,
period-end)
|
14.18
|
|
11.75
|
Exchange rate (US$/C$,
period-end)
|
1.35
|
|
1.25
|
|
|
|
|
Average monthly LME
zinc price (US$/lb)
|
1.42
|
|
1.70
|
|
|
|
|
EAFD processed
(DMT)
|
6,125
|
|
19,785
|
|
|
|
|
Production
(DMT)
|
1,812
|
|
5,695
|
Sales (DMT)
|
2,479
|
|
5,589
|
|
|
|
|
Sales (zinc content
'000 lbs)
|
3,656
|
|
8,183
|
In Q1 2023, world steel production decreased by 0.1% over the
comparable 2022 period. The impact by region was mixed. In Q1 2023
compared to Q1 2022: Chinese production increased 6.1%; European
Union production decreased 10.1%; North American production
decreased 4.1%, and Turkish production decreased by 21.5%.
In April 2023, the World Steel
Association published its short-term outlook for demand, which
projected 2.3% overall global demand growth in 2023 and a further
growth of 1.7% in 2024. Sharp decreases in construction activities
due to the Turkish Lira's devaluation and high inflation lead a
decrease in steel demand in 2022. However, the construction sector
is expected to grow by 15% due to the rebuilding and reinforcing
efforts in high earthquake-risk areas.
The impact of the Ukrainian conflict on global steel markets is
uncertain, however as exports from Russia and Ukraine have historically accounted for 10% of
global steel exports, it is likely a material percentage of this
supply will be replaced by increased production in other
countries.
The following table summarizes comparative results for Q1 2023
and Q1 2022 of the Turkish Zinc JV at 100%.
TURKISH
JV
|
|
|
|
|
|
|
|
|
Three months ended
March 31,
|
|
2023
|
|
2022
|
|
100 %
|
|
100 %
|
Net sales
revenues
|
$
5,836,394
|
|
$
14,348,723
|
Cost of
sales
|
6,671,321
|
|
7,416,981
|
Foreign exchange
gain
|
76,065
|
|
45,235
|
EBITDA(1)
|
$
(758,862)
|
|
$
6,976,977
|
|
|
|
|
Management fees &
sales commissions
|
384,014
|
|
1,022,164
|
Depreciation
|
968,502
|
|
394,208
|
Interest
expense
|
550,124
|
|
304,057
|
Foreign exchange loss
on debt and cash
|
322,358
|
|
1,441,259
|
Monetary
gain
|
1,095,707
|
|
-
|
Tax expense
(recovery)
|
945,059
|
|
890,111
|
Net income
(loss)
|
$
(2,833,212)
|
|
$
2,925,179
|
Global Atomic's equity
share
|
$
(1,388,274)
|
|
$
1,433,338
|
|
|
|
|
Global Atomic's share
of EBITDA
|
$
(371,842)
|
|
$
3,418,719
|
|
|
(1)
|
EBITDA is a non-IFRS
measure, does not have a standardized meaning prescribed by IFRS
and may not be comparable to similar terms and measures presented
by other issuers. EBITDA comprises earnings before income taxes,
interest expense (income), foreign exchange loss (gain) on debt and
bank, depreciation, management fees, sales commissions, losses
(gains) on sale of property, plant and equipment.
|
Zinc concentrates are sold to smelters in US dollars. Because
the Turkish Lira is the functional currency of the Turkish
operations, sales are converted to Turkish Lira at the date of the
sale when funds are subsequently received. When the Turkish Lira
depreciated in both Q1 2022 and Q1 2023, exchange gains were
recognized on those sales. In calculating EBITDA, these exchange
changes related to the functional and reporting currencies are
treated as operations related (i.e., above the EBITDA
subtotal).
All the financial statement line items included in the Turkish
Zinc JV consolidated statements of income (loss) for the three
month period ended March 31, 2023
include hyperinflation impact for the three month period ended
March 31, 2023 and the impact of
inflation on income and expenses recognised in the Q1 2022 are not
restated because it has already been presented in the stable
currency.
The Turkish Zinc JV incurred significant deterioration in
revenues in Q1 2023 compared to Q1 2022, due to processing less
EAFD and lower zinc prices. Sales are recorded upon receipt at the
smelter, which means that recorded sales in any given month
generally represent the concentrate from EAFD processed in the
prior month. Sales for Q1 2023 were produced in only December 2022 whereas sales for Q1 2022 were
produced in December 2021 through
February 2022. The plant was under a
scheduled maintenance shutdown in January
2023. Due to the earthquake on February 6, 2023, the recycling plant resumed
operation following a thorough inspection in March 2023 where revenue from the March 2023 production will be recognized in Q2
2023.
The Turkish Zinc JV realized significant increases in expenses.
The Ukrainian conflict, post-COVID demand increases, raw material
shortages and global logistics challenges resulted in substantial
inflationary pressures on all costs. Moreover, The Turkish Zinc JV
also incurred extraordinary expenses related to the massive
earthquake like financial support to the employees, fixed costs
incurred due to the unplanned stoppage have in combination resulted
in a negative EBITDA.
The cash balance of the Turkish JV was US$0.6 million at March
31, 2023.
The local Turkish revolving credit facility balance was
US$12.4 million at March 31, 2023 (December
31, 2022 - US$8.3 million) and
bears interest at 10%.
QP Statement
This news release has been reviewed and approved by Mr. A.
Christophe Din, MSc, MAus, IMM,
Exploration Manager at Global Atomic's subsidiary, SOMIDA, in the
Republic of Niger, who is a
"qualified person" under National Instrument 43-101 – Standards of
Disclosure for Mineral Properties. Mr. Din holds a Diplôme de
Formation Spécialisée from École Nationale Supérieure des Mines de
Paris and is a member of the
Australian Institute of Geoscientists.
About Global Atomic
Global Atomic Corporation (www.globalatomiccorp.com) is a
publicly listed company that provides a unique combination of
high-grade uranium mine development and cash-flowing zinc
concentrate production.
The Company's Uranium Division includes four deposits with the
flagship project being the large, high-grade Dasa Project,
discovered in 2010 by Global Atomic geologists through grassroots
field exploration. With the issuance of the Dasa Mining Permit and
an Environmental Compliance Certificate by the Republic of
Niger, the Dasa Project is fully
permitted for commercial production. The Phase 1 Feasibility
Study for Dasa was filed in December
2021 and estimates yellowcake delivery to utilities to
commence in 2025. Mine excavation began in Q1 2022.
Global Atomic's Base Metals Division holds a 49% interest in the
Befesa Silvermet Turkey, S.L. (BST) Joint Venture, which operates a
modern zinc production plant, located in Iskenderun, Türkiye. The
plant recovers zinc from Electric Arc Furnace Dust (EAFD) to
produce a high-grade zinc oxide concentrate which is sold to zinc
smelters around the world. The Company's joint venture partner,
Befesa Zinc S.A.U. (Befesa) holds a 51% interest in and is the
operator of the BST Joint Venture. Befesa is a market leader in
EAFD recycling, with approximately 50% of the European EAFD market
and facilities located throughout Europe, Asia
and the United States of
America.
The information in this release may contain forward-looking
information under applicable securities laws. Forward-looking
information includes, but is not limited to, statements with
respect to completion of any financings; Global Atomics'
development potential and timetable of its operations, development
and exploration assets; Global Atomics' ability to raise additional
funds necessary; the future price of uranium; the estimation of
mineral reserves and resources; conclusions of economic evaluation;
the realization of mineral reserve estimates; the timing and amount
of estimated future production, development and exploration; cost
of future activities; capital and operating expenditures; success
of exploration activities; mining or processing issues; currency
exchange rates; government regulation of mining operations; and
environmental and permitting risks. Generally,
forward-looking statements can be identified by the use of
forward-looking terminology such as "plans", "is expected",
"estimates", variations of such words and phrases or
statements that certain actions, events or results "could",
"would", "might", "will be taken", "will begin", "will include",
"are expected", "occur" or "be achieved". All information
contained in this news release, other than statements of current or
historical fact, is forward-looking information.
Statements of forward-looking information are subject to known and
unknown risks, uncertainties and other factors that may cause the
actual results, level of activity, performance or achievements of
Global Atomic to be materially different from those expressed or
implied by such forward-looking statements, including but not
limited to those risks described in the annual information form of
Global Atomic and in its public documents filed on SEDAR from time
to time.
Forward-looking statements are based on the opinions and
estimates of management at the date such statements are made.
Although management of Global Atomic has attempted to identify
important factors that could cause actual results to be materially
different from those forward-looking statements, there may be other
factors that cause results not to be as anticipated, estimated or
intended. There can be no assurance that such statements will
prove to be accurate, as actual results and future events could
differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance upon
forward-looking statements. Global Atomic does not undertake
to update any forward-looking statements, except in accordance with
applicable securities law. Readers should also review the
risks and uncertainties sections of Global Atomics' annual and
interim MD&As.
The Toronto Stock Exchange has not reviewed and does not accept
responsibility for the adequacy and accuracy of this news
release.
SOURCE Global Atomic Corporation