Cornish Metals Inc. (
AIM/TSX-V:
CUSN) (“Cornish Metals” or the “Company”), a mineral
exploration and development company focused on advancing the South
Crofty tin project (“South Crofty” or the “Project”) located in
Cornwall, United Kingdom, to a construction decision, is pleased to
provide an update on the progress of activities and outlook for
2024.
Highlights
- Important
Milestones Achieved in 2023:
- Updated Mineral Resource Estimate
(“MRE”) for South Crofty Mine with a 31.6% increase to contained
tin in the Indicated Mineral Resource category for the Lower
Mine;
- Construction and commissioning of
the Water Treatment Plant (“WTP”);
- Installation and commissioning of
submersible pumps in New Cook’s Kitchen (“NCK”) shaft;
- Commencement of dewatering of South
Crofty Mine with the water level currently down to 257 metres below
the NCK shaft collar level;
- Completion of metallurgical
testwork drilling programme;
- Better than expected results from
X-Ray Transmission ("XRT") ore sorting testwork confirming the
potential to materially reduce tonnes milled, and reduce process
plant capital and operating costs;
- Installation of two single drum
winders for shaft re-access;
- Commencement of an exploration
drilling programme at the Wide Formation target.
- 2024
Outlook:
- Mine dewatering:
- Dewater to 195-fathom level (~360
metres below surface) and refurbish the pump station;
- Progress to the second stage of
dewatering of the deeper levels of the mine;
- Commence underground infill
drilling;
- Advance the South Crofty
Feasibility Study: all study components, with the exception of
infill drilling, expected to be completed in H1 2024;
- Preliminary Economic Assessment
(“PEA”) for South Crofty planned before end of H1 2024 to provide
interim guidance prior to the publication of the Feasibility
Study;
- Complete the 14-hole / 9,000 metre
Wide Formation exploration drill programme.
Richard Williams, CEO and Director of
Cornish Metals, stated: “The Cornish Metals team worked
tirelessly in 2023, achieving numerous important milestones, while
further advancing and de-risking the South Crofty project. Chief
among these are the construction of the WTP and commencement of
dewatering of the mine that continues to progress extremely well
with water levels drawing down as expected. Activity levels are
expected to remain high through 2024 with more important milestones
to be met as we work to further progress the South Crofty project
towards a construction decision.”
Mine Dewatering Progressing
Well
- Mine dewatering and water treatment
to remove dissolved metals and suspended solids prior to discharge
has been underway since early November 2023 with up to 25,000m3 per
day of water being pumped and treated from South Crofty Mine;
- Progress is good, with the water
level in the mine currently ahead of projections despite the recent
wet weather;
- On January 17th the water level
stood at 257 metres below the NCK shaft collar level;
- Water levels in historic mines
adjacent to South Crofty remain unchanged while South Crofty water
levels fall, confirming that South Crofty is not hydrologically
connected to neighbouring historic mines and that the dewatering
only comprises South Crofty Mine;
- Treated water from the WTP is being
discharged into the Red River, having a positive effect on the
water quality of the river downstream of the discharge point;
- The treated water from South Crofty
passes through a 75-kW hydro-turbine located ahead of the discharge
point that generates up to 20% of the power consumed by the WTP.
Other renewable energy opportunities are being explored;
- At current rates, the first stage
dewatering to the 195-fathom level (approximately 360 metres below
surface) is anticipated to be completed in early Q2-2024;
- Refurbishment of the 195-fathom
pump station and installation of permanent pumps is planned to take
place during Q2 / Q3-2024;
- Lowering of the submersible pumps
to below the 400-fathom level (approximately 730 metres below
surface) and commencement of the second stage of dewatering is
planned to commence in Q3-2024;
- The Company maintains guidance of
18-months (from the commencement of dewatering in November 2023) to
complete dewatering of South Crofty Mine to the 400-fathom
level.
Feasibility Study Progress
The Company is making good progress advancing
the South Crofty Feasibility Study with a substantial amount of the
study completed. All study components, with the exception of infill
drilling, are expected to be finalised in H1 2024.
The following Feasibility Study components have
been completed:
- Geotechnical testwork - televiewer
investigations and geotechnical rock testing to confirm known
historical structural and rock mass property data;
- Headframe structural modelling and
refurbishment;
- Schedule and costing for the
refurbishment and recommissioning of NCK and New Roskear
shafts;
- Numerical modelling of the proposed
underground mining methods and stope designs;
- Phase 1 of the metallurgical
testwork programme (mineralogy, physical competency,
characterisation XRT, heavy liquid separation and gravity response
testwork);
- Concept engineering on paste
backfill options and sighter testwork;
- Ground investigations for the new
mineral processing plant; and
- Mineral processing plant design and
layout, incorporating the results of the metallurgical testwork
programme and potential future throughput expansions;
The following Feasibility Study components are
underway:
- Underground mine design and
optimisation using the September 2023 South Crofty updated Mineral
Resource Estimate;
- A mine ventilation study,
underground infrastructure design and hoisting analysis;
- A Feasibility Study level
engineering design for the paste backfill plant;
- Hydrogeology, environmental,
social, market and closure studies; and
- Underground
drilling options review started.
Wide Formation Target Exploration
Drilling
- A 14-hole / 9,000 metre drilling
programme at the Wide Formation target in the Carn Brea South
exploration area commenced in late summer 2023;
- Drill programme to test the
geometry and the continuity of tin mineralisation within the Wide
Formation target – testing an area measuring 2,500m along strike
(northeast to southwest) and 500m downdip (north to south);
- Two drills are on-site with holes
No. 7 and No. 8 currently underway;
- Great Flat lode and Wide Formation
mineralisation structures have been intersected where
expected;
- 4,700 metres drilled to date and
assays will be reported when available;
- Drilling programme expected to be
completed in summer 2024.
ABOUT CORNISH METALS
Cornish Metals is a dual-listed company (AIM and
TSX-V: CUSN) focused on advancing the South Crofty high-grade,
underground tin Project through to a construction decision, as well
as exploring its additional mineral rights, all located in
Cornwall, United Kingdom.
- South Crofty is a historical, high-grade, underground tin mine
that started production in 1592 and continued operating until 1998
following over 400 years of continuous production;
- The Project possesses Planning Permission for underground
mining (valid to 2071), to construct new processing facilities and
all necessary site infrastructure, and an Environmental Permit to
dewater the mine;
- South Crofty has the 4th highest grade tin Mineral Resource
globally and benefits from existing mine infrastructure including
multiple shafts that can be used for future operations;
- Tin is a Critical Mineral as defined by the UK, USA, and
Canadian governments, with approximately two-thirds of the tin
mined today coming from China, Myanmar and Indonesia;
- There is no primary tin production in Europe or North
America;
- Tin connects almost all electronic and electrical
infrastructure, making it critical to the energy transition –
responsible sourcing of critical minerals and security of supply
are key factors in the energy transition and technology
growth;
- South Crofty benefits from strong local community and regional
and national government support.
- Cornish Metals has a growing team of skilled people, local to
Cornwall, and the Project could generate 250 – 300 direct
jobs.
An updated Mineral Resource was completed in
September 2023 with a 39% increase in tonnes and 32% increase in
contained tin in the Indicated category for the Lower Mine (see
news release dated September 13, 2023) as summarised below:
South Crofty Summary (JORC 2012) Mineral Resource
Estimate |
Area |
Classification |
Mass(kt) |
Grade |
Contained Tin / Tin Equivalent
(kt) |
Lower Mine |
Indicated |
2,896 |
1.50% Sn |
43.6 |
Inferred |
2,626 |
1.42% Sn |
37.4 |
Upper Mine |
Indicated |
260 |
0.99% SnEq |
2.6 |
Inferred |
465 |
0.91% SnEq |
4.2 |
The Mineral Resource Estimate for South Crofty
is available in a report titled “South Crofty Tin Project - Mineral
Resource Update NI 43-101 Technical Report”, dated October 27,
2023, co-authored by Mr. N. Szebor (MCSM, MSc, BSc, CGeol, EurGeol,
FGS) and Mr. R. Chesher (FAusIMM(CP), RPEQ, MTMS) of AMC
Consultants, and can be accessed through the above link and on the
Company’s SEDAR+ page.
TECHNICAL INFORMATION
The technical information in this news release
has been compiled by Mr. Owen Mihalop who has reviewed and takes
responsibility for the data and geological interpretation. Mr. Owen
Mihalop (MCSM, BSc (Hons), MSc, FGS, MIMMM, CEng) is Chief
Operating Officer for Cornish Metals Inc. and has sufficient
experience relevant to the style of mineralisation and type of
deposit under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined under the
JORC Code (2012) and as a Qualified Person under NI 43-101. Mr.
Mihalop consents to the inclusion in this announcement of the
matters based on his information in the form and context in which
it appears.
ON BEHALF OF THE BOARD OF
DIRECTORS
“Richard D. Williams”Richard D. Williams,
P.Geo
For additional information please contact:
Cornish Metals |
Fawzi Hanano |
investors@cornishmetals.com |
|
Irene Dorsman |
info@cornishmetals.com |
|
|
Tel: +1 (604) 200 6664 |
|
|
|
SP Angel Corporate Finance LLP |
Richard Morrison |
Tel: +44 203 470 0470 |
(Nominated Adviser & Joint Broker) |
Charlie Bouverat |
|
|
Grant Barker |
|
|
|
|
Hannam & Partners |
Matthew Hasson |
cornish@hannam.partners |
(Joint Broker) |
Andrew Chubb |
Tel: +44 207 907 8500 |
|
Jay Ashfield |
|
|
|
|
BlytheRay |
Tim Blythe |
tim.blythe@blytheray.com |
(Financial PR) |
Megan Ray |
megan.ray@blytheray.com |
|
|
Tel: +44 207 138 3204 |
|
|
|
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
Caution regarding forward looking
statements
This news release contains certain
“forward-looking information” and “forward-looking statements”
(collectively, “forward-looking statements”). Forward-looking
statements include predictions, projections, outlook, guidance,
estimates and forecasts and other statements regarding future
plans, the realisation, cost, timing and extent of mineral resource
or mineral reserve estimates, estimation of commodity prices,
currency exchange rate fluctuations, estimated future exploration
expenditures, costs and timing of the development of new deposits,
success of exploration activities, permitting time lines,
requirements for additional capital, future or estimated mine life
and other activities or achievements of Cornish Metals, including
but not limited to: mineralisation at South Crofty, mine dewatering
expectations, Cornish Metals’ exploration drilling programme,
timing and results of Cornish Metals’ feasibility study, strategic
vision of Cornish Metals and expectations regarding the South
Crofty mine, timing and results of projects mentioned.
Forward-looking statements are often, but not always, identified by
the use of words such as “seek”, “anticipate”, “believe”, “plan”,
“estimate”, “forecast”, “expect”, “potential”, “project”, “target”,
“schedule”, “budget” and “intend” and statements that an event or
result “may”, “will”, “should”, “could”, “would” or “might” occur
or be achieved and other similar expressions and includes the
negatives thereof. All statements other than statements of
historical fact included in this news release, are forward-looking
statements that involve various risks and uncertainties and there
can be no assurance that such statements will prove to be accurate
and actual results and future events could differ materially from
those anticipated in such statements.
Forward-looking statements are subject to risks
and uncertainties that may cause actual results to be materially
different from those expressed or implied by such forward-looking
statements, including but not limited to: risks related to receipt
of regulatory approvals, risks related to general economic and
market conditions; risks related to the availability of financing;
the timing and content of upcoming work programmes; actual results
of proposed exploration activities; possible variations in Mineral
Resources or grade; outcome of the current Feasibility Study;
projected dates to commence mining operations; failure of plant,
equipment or processes to operate as anticipated; accidents, labour
disputes, title disputes, claims and limitations on insurance
coverage and other risks of the mining industry; changes in
national and local government regulation of mining operations, tax
rules and regulations.
Cornish Metals’ forward-looking statements are
based on the opinions and estimates of management and reflect their
current expectations regarding future events and operating
performance and speak only as of the date such statements are made.
Although the Company has attempted to identify important factors
that could cause actual actions, events or results to differ from
those described in forward- looking statements, there may be other
factors that cause such actions, events or results to differ
materially from those anticipated. There can be no assurance that
forward-looking statements will prove to be accurate and
accordingly readers are cautioned not to place undue reliance on
forward-looking statements. Accordingly, readers should not place
undue reliance on forward-looking statements. Cornish Metals does
not assume any obligation to update forward-looking statements if
circumstances or management’s beliefs, expectations or opinions
should change other than as required by applicable law.
Market Abuse Regulation (MAR)
Disclosure
The information contained within this
announcement is deemed by the Company to constitute inside
information pursuant to Article 7 of EU Regulation 596/2014 as it
forms part of UK domestic law by virtue of the European Union
(Withdrawal) Act 2018 as amended.
Cornish Metals (TSXV:CUSN)
Historical Stock Chart
From Feb 2025 to Mar 2025
Cornish Metals (TSXV:CUSN)
Historical Stock Chart
From Mar 2024 to Mar 2025