(TSX-V: GXS) (OTCBB: GXSFF) (FWB: G5M)
VANCOUVER, April 20, 2016 /CNW/ - Goldsource Mines Inc.
("Goldsource" or the "Company") is pleased to report on Phase I
commissioning activities at its Eagle Mountain Gold Project ("Eagle
Mountain") located in Guyana,
South America. Outlined below is a
summary of the most significant activities completed year to date
including start of commissioning, the first metal pour, and first
gold sale.
Phase I is based on a Preliminary Economic Assessment ("PEA")
dated June 15, 2014, which calls for
a 1,000 tonnes per day ("tpd") open pit ‑ gravity plant
with post-commissioning and ramp up cash operating costs of
US$500 to US$600 per ounce of gold.
Please refer to the Company's website at www.goldsourcemines.com
and Company filings on www.sedar.com for further information.
Yannis Tsitos, President,
commented, "We are very pleased with our progress during Q1, 2016.
All major equipment continues to operate well in both dry and wet
conditions. Onsite personnel have been able to maintain
infrastructure with minimal cost and disruption to operations. The
Company expects to add a second excavator in Q2, 2016 and with
planned installation of a larger feed pipe to the scrubber, the
Phase I design rate of 1,000 tpd of continuous production at Eagle
Mountain should be achieved in Q2, 2016. We currently have
CAD$1.4 million to meet our working
capital requirements and complete planned expansion over the next
several months."
Commercial production is anticipated in the second quarter of
2016, which will require achieving 80% of the 1000 tpd nameplate
capacity and 45% recovery in gold concentrate on average over a
period of 30 days.
Highlights for Year to Date (Commissioning-Stage):
- Start of commissioning on January 28,
2016.
- In February and March, re-designed and re-fabricated the mine
grizzly and processing gold room.
- Mined an estimated 17,919 tonnes year to date.
- Processed an estimated 16,726 tonnes grading 0.76 grams per
tonne ("gpt") gold year to date.
- Average of 236 tpd processed year to date. So far, for April,
an average of 470 tpd has been processed or 47% of nameplate
capacity.
- Estimated 45% gravity recovery for the plant year to date.
April recoveries are estimated to have increased to 50%.
- Estimated 58% gravity recovery from table concentrate year to
date. April recoveries are estimated to have increased to 68%.
- First gold pour on March 6,
2016.
- Produced 104 ounces of gold year to date.
- First gold shipment and sale on April
14, 2016 of 81.7 ounces of gold at US$1,240 per ounce with estimated inventory of
22.3 ounces of gold.
- Estimated 40,000 man-hours worked during commissioning, with no
lost time accidents.
Eagle Mountain
Gold Mine Operating Statistics
|
Q1, 2016
Total
|
April 1 -
17
Total
|
Year to Date
Total
|
Mined
tonnes
|
9,814
|
8,105
|
17,919
|
Processed tonnes at
minus 2mm
|
8,742
|
7,984
|
16,726
|
Average
tpd(1) processed
|
162
|
470
|
236
|
Average estimated
grade, gpt
|
0.76
|
0.76
|
0.76
|
Estimated gravity
recovery for plant
|
40%
|
50%
|
45%
|
Estimated gravity
recovery for table
|
50%
|
68%
|
58%
|
Gold ounces produced
at estimated 89% fine
|
38.1
|
65.9
|
104.0
|
Gold ounces
sold
|
38.1
|
43.6
|
81.7
|
(1)
based on PEA of 25 operating days per
month (2)
All numbers are rounded
|
Initial production (pre-commercial) commenced in late January
with 9,814 mined tonnes, 8,742 processed tonnes and 38.1 ounces of
gold poured in Q1, 2016 with 24.5 ounces of gold in inventory as at
March 31. From April 1 to April 17, 65.9 ounces of gold were
poured, including the March 31
inventory. On April 14, 2016, the
Company sold a total of 81.7 ounces of gold at US$1,240 per ounce. As of April 19, the Company has an estimated 22.3
ounces of gold in inventory.
Management continues to optimize the operation with peak daily
throughput of approximately 777 tonnes processed. Estimated gravity
recovery to concentrate increased from an estimated 40% in February
to currently 50%. The average tpd from April
1 to April 17 was 470 or 47% of nameplate capacity.
Significant increased capacity is anticipated in the next 30 days
with the installation of a re-designed larger diameter feed chute
to the scrubber, which is currently limiting daily production.
The average grade of the compliant saprolite resource is 1.2 gpt
gold. As anticipated, the current grades are lower at 0.6 to 0.8
gpt gold as tonnes were mined from areas close to the scrubber for
testing and commissioning purposes. Mine grades should start to
increase over the next 30 days as mining transitions into a higher
grade portion of the resource.
With the introduction of a second excavator and other ancillary
equipment, plans to start a second shift by the end of Q2 are being
accelerated. Originally, the plan and budget were scheduled for a
second shift in mid-Q3. With the inclusion of a second shift,
tonnage throughput should be increased significantly with
subsequent additional gold production.
The tailings storage facility is expected to be sufficient to
support operations for the next six months before expansion is
required. In addition, the Company has constructed a clarification
pond to reduce water turbidity prior to planned recycling or
discharge.
The Company continues to evaluate the potential to utilize low
impact intensive cyanide leaching of the gold concentrates to
improve the overall gold recovery and production for the Eagle
Mountain Gold Project.
The Qualified Person under National Instrument 43-101 –
Standards of Disclosure for Mineral Projects for this news
release is N. Eric Fier, CPG, P.Eng,
and Chief Operating Officer for Goldsource, who has reviewed and
approved its contents.
ABOUT GOLDSOURCE MINES INC.
Goldsource Mines Inc. (www.goldsourcemines.com) is a Canadian
resource company that is progressing its advanced-stage, 100%-owned
Eagle Mountain Gold Project, located in Guyana, towards initial staged production in
Q2, 2016. Goldsource is led by an experienced management team,
proven in making exploration discoveries and achieving project
construction on time and on-budget.
Ioannis (Yannis)
Tsitos
President
Goldsource Mines Inc.
Neither TSX-V nor its Regulation Services
Provider (as that term is defined in policies of the TSX-V) accepts
responsibility for the adequacy or accuracy of this
release.
FORWARD-LOOKING STATEMENTS
This news release contains "forward-looking
statements" within the meaning of Canadian securities legislation.
Such forward‑looking statements concern Goldsource's strategic
plans and expectations in the PEA for the development of the Eagle
Mountain Gold Project; the amount of future production of gold over
any period; cash operating costs per ounce of gold; life of mine;
estimated pre-production cost; the amount of expected grades
and ounces of metals, gold recoveries mine life and gold production
rates of the Eagle Mountain Gold Project; the Company's
expectations regarding its ability to commence commercial
production in Q2, 2016 and expectations regarding the Company's
ability to manage capital resources and meet working capital
requirements.. Such forward‑looking statements or
information are based on a number of assumptions, which may prove
to be incorrect. Assumptions have been made regarding, among other
things: conditions in general economic and financial markets;
ability to realize the PEA and develop and finance the project;
accuracy of the interpretations and assumptions used in calculating
inferred mineral resource estimates; availability of mining
equipment; availability of skilled labour; timing and amount of
capital expenditures; performance of available laboratory and other
related services; and future operating costs. The actual results
could differ materially from those anticipated in these
forward‑looking statements as a result of the risk factors
including: the timing and content of work programs; results of
exploration activities and development of mineral properties; the
interpretation of drilling results and other geological data; the
uncertainties of resource estimations; uncertainty as to actual
capital costs, operating costs, production and economic returns at
the Eagle Mountain Gold Project; reliance on the PEA;
and general market and industry conditions. Forward-looking
statements are based on the expectations and opinions of the
Company's management on the date the statements are made. The
assumptions used in the preparation of such statements, although
considered reasonable at the time of preparation, may prove to be
imprecise and, as such, readers are cautioned not to place undue
reliance on these forward-looking statements, which speak only as
of the date the statements were made. The Company undertakes no
obligation to update or revise any forward-looking statements
included in this news release if these beliefs, estimates and
opinions or other circumstances should change, except as otherwise
required by applicable law.
SOURCE Goldsource Mines Inc.