Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) “Monument” or
the “Company” today announced its financial results for the three
months (“Q2 FY 2025”) and six months ended December 31, 2024 (“YTD
FY 2025”). All amounts are in United States dollars unless
otherwise indicated (refer to www.sedar.com for full financial
results).
President and CEO Cathy Zhai commented, "Q2 FY
2025 focused on sustaining stable gold production at the Selinsing
Gold Mine, delivering healthy cash flow and building a solid cash
balance to fund business development. During the quarter cash
reserves increased by $5.2 million to $23.08 million and working
capital increased by $7.2 million to $31.92 million. The Murchison
Project review continued including economic assessment of a
potential production restart for a second source of cash flow as
gold price approaching $3,000 per ounce.”
Second Quarter Highlights:
- $23.08 million cash on hand, $5.20
million increase from $17.88 million during Q2 FY 2025, compared to
$4.84 million cash on hand, $0.30 million decrease during Q2 FY
2024;
- $31.92 working capital, $11.37
million or 55% increase from $20.55 million at the end of June 30,
2024;
- Net profit of $8.84 million, or
$0.03 per share for Q2 FY 2025, compared to net loss of ($0.60
million), or ($0.00)/share for Q2 FY 2024;
- Gross margin of 11.54 million for
Q2 FY 2025, 1.4 times more than $4.77 million in Q2 FY 2024;
- Production performance:
- 8,613 ounces of gold produced (Q2
FY 2024: 6,809 ounces);
- 8,987 ounces of gold sold at a
record average realized price of $2,678/oz for gross revenue of
$19.80 million (Q2 FY 2024: 6,967 ounces sold at an average
realized price of $1,946/oz for gross revenue of $11 million);
- Cash cost of $918 per ounce sold
(Q2 FY 2024: $894/oz);
- All in sustaining cost of $1,201
per ounce sold for Q2 FY 2025, 2% increase compared to $1,175/oz in
Q2 FY 2024;
- Planning of mineral resource
in-fill and step-out drilling programs to increase the Selinsing
mine life underway and expected to commence in Q3 FY 2025.
Second Quarter and YTD Fiscal Year 2025
Production and Financial Highlights
|
Three months ended Dec.31, |
Six months ended Dec.31, |
|
2024 |
2023 |
2024 |
2023 |
Production |
|
|
|
|
Ore mined
(tonnes) |
177,296 |
332,684 |
315,228 |
589,588 |
Waste removed
(tonnes) |
2,061,571 |
2,673,041 |
4,374,570 |
4,788,251 |
Gold
Sulphide Production |
|
|
|
|
Ore processed (tonnes) |
169,636 |
192,217 |
359,312 |
369,711 |
Average mill feed grade (g/t) |
1.83 |
1.55 |
1.78 |
1.68 |
Processing recovery rate (%) |
86.09 |
71.10 |
81.01 |
70.34 |
Gold produced (oz) (1) |
8,613 |
6,809 |
16,672 |
14,052 |
Gold sold (oz) |
8,987 |
6,967 |
18,257 |
11,574 |
|
|
|
|
|
Financial(expressed in thousands of US$) |
$ |
$ |
$ |
$ |
Revenue |
19,796 |
10,997 |
39,167 |
17,908 |
Gross margin from
mining operations |
11,541 |
4,769 |
23,152 |
7,778 |
Net Income before
other items |
8,424 |
1,818 |
17,025 |
2,891 |
Net income
(loss) |
8,839 |
(595) |
11,836 |
(680) |
Cash flows
provided by operations |
8,722 |
2,414 |
18,398 |
2,434 |
Working
capital |
31,926 |
14,252 |
31,926 |
14,252 |
|
|
|
|
|
Earnings (Loss) per share – basic and diluted (US$/share) |
0.03 |
(0.00) |
0.04 |
(0.00) |
|
|
|
|
|
Weighted
average gold price |
US$/oz |
US$/oz |
US$/oz |
US$/oz |
|
|
|
|
|
Realized price –
sulphide production |
2,678 |
1,946 |
2,613 |
1,940 |
|
|
|
|
|
Cash cost
per ounce sold |
|
|
|
|
Mining |
242 |
298 |
243 |
285 |
Processing |
313 |
341 |
299 |
344 |
Royalties |
290 |
172 |
260 |
172 |
Operations |
73 |
83 |
75 |
74 |
Total cash
cost per ounce sold (2) |
918 |
894 |
877 |
875 |
|
|
|
|
|
Operation expenses |
4 |
5 |
5 |
6 |
Corporate expenses |
10 |
8 |
6 |
6 |
Accretion of asset retirement obligation |
6 |
8 |
6 |
9 |
Exploration and evaluation expenditures |
8 |
2 |
4 |
2 |
Sustaining capital expenditures |
255 |
258 |
260 |
190 |
Total all-in sustaining costs per ounce
sold(3) |
1,201 |
1,175 |
1,158 |
1,088 |
(1) Out of total 8,613 ounces of gold production
reported in Q2 FY 2025, of which 660 ounces were production
adjustments(2) Total cash cost for sulphide plant production
includes production costs such as mining, processing, tailing
facility maintenance and camp administration, royalties, and
operating costs such as storage, temporary mine production closure,
community development cost and property fees, net of by-product
credits. Cash cost excludes amortization, depletion, accretion
expenses, capital costs, exploration costs and corporate
administration costs.(3) All-in sustaining cost per ounce includes
total cash costs, operation expenses, and adds sustaining capital
expenditures, corporate administrative expenses for the Selinsing
Gold Mine including share-based compensation, exploration and
evaluation costs, and accretion of asset retirement obligations.
Certain other cash expenditures, including tax payments and
acquisition costs, are not included.
GOLD PRODUCTION RESULTS
Second quarter gold
production
- The sulphide flotation plant
produced 8,613 ounces of gold, including 660 ounces adjustments.
The mill processed 169,636 tonnes of sulphide ore at an improved
average recovery of 86.09% because of plant improvements and
optimization, the use of new reagents including ethylene glycol
frother, and the treatment of higher-grade transition and fresh
sulphide ore. Further, higher grade transition and fresh sulphide
ore at 1.83 g/t were treated compared to Q2 FY 2024.
- During Q2 FY 2025, mining
activities continued to focus on Buffalo Reef and Felda Block 7.
Ore mined in the quarter was 47% lower than in Q2 FY 2024,
primarily due to avoidance of excessive ore stockpiles and a
reduction of stockpile turnover caused by processing plant downtime
resulting from a power supply failure and primary ball mill CPU
fault and motor replacement. The heavy rainfall also disrupted
blasting in certain areas and caused blockages in the crusher.
- The ore processed during the
quarter was 12% less than in Q2 FY 2024 due to the primary ball
mill CPU failure and motor replacement, and a bottleneck at the
filter press.
YTD FY 2025 gold production
- Mine production included total
material mined of 4,689,798 tonnes (six months ended December 31,
2023 (“YTD FY 2024”): 5,377,839 tonnes), comprising to 315,228
tonnes of ore (YTD FY 2024: 589,588 tonnes) and 4,374,570 tonnes of
waste (YTD FY 2024: 4,788,251 tonnes). The stripping ratio
increased to 13.88 compared to 8.12 during YTD FY 2024.
- The mill processed 359,312 tonnes
of sulphide ore during YTD FY 2025, averaging a head grade of 1.78
g/t and a recovery of 81.01%. This compares with 369,711 tonnes of
sulphide ore at a head grade of 1.68 g/t and a recovery rate of
70.34% processed during YTD FY 2024.
FINANCIAL RESULTS
Second Quarter financial
results
- Q2 FY 2025 gold sales generated
revenue of $19.80 million from 8,987 oz gold sold at a record
average realized price of $2,678 per ounce (Q2 FY 2024: 6,967 oz at
$1,946 per ounce for gross revenue of $11.00 million) from the
sulphide flotation plant.
- Mining operations before non-cash
amortization and depreciation generated a gross margin of $11.54
million, 1.4 times more than $4.77 million in Q2 FY 2024.
- The cash cost from the sulphide
gold production is controlled to $918/oz compared to $894/oz in the
Q2 FY 2024.
- Net cash generated from operating
activities of $8.72 million in the quarter, an increase of $6.31
million compared to $2.41 million of net cash generation during Q2
FY 2024, which was mainly led by higher gross margin from more gold
concentrate sales at higher realized gold prices.
- The Company’s cash and cash
equivalents as at December 31, 2024 were $23.08 million, an
increase of $12.22 million from $10.86 million as at June 30, 2024.
And current assets exceeded current liabilities by $31.92 million
(June 30, 2024: $20.55 million) demonstrating a strong net working
capital position.
YTD FY 2025 financial
results
- Revenue of $39.17 million from the
sale of gold concentrates, containing 18,257 oz of gold sold at the
average realized gold price of $2,613/oz (YTD FY 2024: revenue of
$17.91 million for 11,574 oz of gold sold at the average realized
price at $1,940 per ounce).
- Total mining cost of $4.43 million
compared to $3.30 million during YTD FY 2024.
- Total processing costs related to
the sulphide operations were $5.46 million compared to $3.99
million during YTD FY 2024.
- Mining operations before non-cash
amortization and depreciation generated a gross margin of $23.15
million, an increase of $15.37 million from $7.78 million during
YTD FY 2024.
- The cash cost from the sulphide
flotation gold production was $877/oz (YTD FY2024: $875/oz for the
gold concentrate).
MINE DEVELOPMENT AND
EXPLORATION
Selinsing Gold Mine
Pre-stripping and cut-back, and mining
methods
Mining at Buffalo Reef and Felda Block 7
continued and reached the high-grade portion of the orebody. The
stripping ratio is expected to decline during the remainder of
fiscal 2025 after the cutback activities are conducted as per the
mining schedule.
Tailing Storage Facility Upgrade
Raising the TSF main embankment to 540m RL was
completed to accommodate an additional three-year’s of TSF capacity
in relation to the sulphide concentrate production and a spillway
was constructed to 539.2m RL in the saddle dam. A buttress along
the toe of the main embankment was completed using waste material
from the Buffalo Reef pits to raise the factor of safety ahead of
the next construction raise planned for 2025. TSF stage 6 seepage
and drainage work were completed in September 2024 and stage 7 has
been planned to commence after Q2 FY 2025.
Flotation Plant and Related Facilities
During Q2 FY 2025, plant optimization
improvements included: a new primary mill drive motor and CPU
parts, crushing and flotation plant modifications including
installation of new jaw crusher liner plates, cone crusher concave
and mantle liners, certain conveyor belts and gearbox, cyclone feed
pump repair, secondary ball mill discharge pump repair, Knelson
tail launder, filter feed tank agitator blades, water recovery
thickener underflow pump repair, rougher tailings sump pump, and
other pumps and pipelines. The 1,600 kW primary mill motor was
replaced with the spare unit and a new 75 kW motor was installed
for the TSF booster pump. Further upgrades to the filter press
operation including a new filter press, new compressor and new
concentrate surge tank have been planned and are expected to be
completed and commissioned in the third quarter of fiscal 2025
after further optimization design and electrical control
centralization.
Exploration
During the second quarter the Company continued
a review process for the potential expansion of mineral resources
at Selinsing, and a proposal of drill holes for Buffalo Reef
resource conversion drilling has been reviewed. An exploration team
has been recruited for exploration programs and a core logging,
cutting and sampling facility has been established. A new drilling
program is expected to commence in the third quarter, which will
aim to identify additional oxide and sulphide mineralisation,
upgrade the resources outside of the current pit-shell and
potentially increase the life of mine.
Murchison Gold Project
At the Murchison Gold Project the Company has
continued a review of the historic resources at Gabanintha and
resources at Burnakura during the quarter, including analysis of
historical data received from regulators in Q2 FY 2024; completed
the initial planning work to identify the step out drilling targets
at both Burnakura and Gabanintha as opportunity for extension of
the mineralization.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE:D7Q1)
is an established Canadian gold producer that 100% owns and
operates the Selinsing Gold Mine in Malaysia and the Murchison Gold
Project in the Murchison area of Western Australia. It has 20%
interest in Tuckanarra Gold Project jointly owned with Odyssey Gold
Ltd in the same region. The Company employs approximately 250
people in both regions and is committed to the highest standards of
environmental management, social responsibility, and health and
safety for its employees and neighboring communities.
Cathy Zhai, President and CEOMonument Mining
LimitedSuite 1580 – 1100 Melville StreetVancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web
site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver
T: +1-604-638-1661
x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release."
Disclaimer Regarding Forward-Looking
Statements
This news release includes statements containing
forward-looking information about Monument, its business and future
plans ("forward-looking statements"). Forward-looking statements
are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the
Company's plans with respect to its mineral projects, expectations
regarding the completion of the ramp-up period to target production
level at Selinsing and the timing thereof, expectations regarding
the Company’s continuing ability to source explosives from
suppliers, expectations regarding completion of the proposed
storage shed and ammonium nitrate depot and the timing thereof, and
the timing and results of the other proposed programs and events
referred to in this news release. Generally, forward-looking
information can be identified by the use of forward-looking
terminology such as "plans", "expects" or "does not expect", "is
expected", "budget", "scheduled", "estimates", "forecasts",
"intends", "anticipates" or "does not anticipate", or "believes",
or variations of such words and phrases or state that certain
actions, events or results "may", "could", "would", "might" or
"will be taken", "occur" or "be achieved". The forward-looking
statements in this news release are subject to various risks,
uncertainties and other factors that could cause actual results or
achievements to differ materially from those expressed or implied
by the forward-looking statements. These risks and certain other
factors include, without limitation: risks related to general
business, economic, competitive, geopolitical and social
uncertainties; uncertainties regarding the results of current
exploration activities; uncertainties in the progress and timing of
development activities, including those related to the ramp-up
process at Selinsing and the completion of the proposed storage
shed and ammonium nitrate depot; uncertainties and risks related to
the Company’s ability to source explosives from suppliers; foreign
operations risks; other risks inherent in the mining industry and
other risks described in the management discussion and analysis of
the Company and the technical reports on the Company's projects,
all of which are available under the profile of the Company on
SEDAR at www.sedar.com. Material factors and assumptions used to
develop forward-looking statements in this news release include:
expectations regarding the estimated cash cost per ounce of gold
production and the estimated cash flows which may be generated from
the operations, general economic factors and other factors that may
be beyond the control of Monument; assumptions and expectations
regarding the results of exploration on the Company's projects;
assumptions regarding the future price of gold of other minerals;
the timing and amount of estimated future production; assumptions
regarding the timing and results of development activities,
including the ramp-up process at Selinsing and the completion of
the proposed storage shed and ammonium nitrate depot; expectations
that the Company will continue to be able to source explosives from
suppliers in a timely manner; costs of future activities; capital
and operating expenditures; success of exploration activities;
mining or processing issues; exchange rates; and all of the factors
and assumptions described in the management discussion and analysis
of the Company and the technical reports on the Company's projects,
all of which are available under the profile of the Company on
SEDAR at www.sedar.com. Although the Company has attempted to
identify important factors that could cause actual results to
differ materially from those contained in forward-looking
statements, there may be other factors that cause results not to be
as anticipated, estimated or intended. There can be no assurance
that such statements will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue
reliance on forward-looking statements. The Company does not
undertake to update any forward-looking statements, except in
accordance with applicable securities laws.
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Feb 2025 to Mar 2025
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Mar 2024 to Mar 2025