23 September 2024
Adriatic Metals
PLC
("Adriatic Metals" or the "Company")
Operations
Update
Adriatic Metals plc ("Adriatic" or
"the Company") is pleased to announce an operations update for the
Vares Silver Operation. The Company will host an associated webinar
on Monday 23 September at 8am BST / 5pm AEST. The presentation is
open to sell-side analysts and investors. To register and submit a
question, please contact Burson Buchanan via
adriatic@buchanan.uk.com
Mining
August was a milestone month at the
Rupice Mine. The first stope was brought into production and
resulted in record ore production of 25,514t, compared to 5,595t in
July and a total of 9,513t across H1 2024. Mined grades were higher
than expected and exceeded the monthly plan on a contained metal
basis. Development rates also increased to a record high of 318m in
August, 6% above the forecasted 300m/month.
Over the coming months, the mine is
on track to increase the number of active stopes from one per month
to two by December 2024. The number of available headings
will rise from 11 to 15, which will allow the mine to ramp up from
current rates towards commercial production levels by the end of
the year.
Figure 1
- YTD Production Metrics
Month-to-date mining in September
has produced approximately 26,000t at 500g/t AgEq, averaging
1,250tpd, with grades reconciling well to the reserve model. While
mining rates continue to ramp-up, due to development delays
experienced in earlier quarters, Adriatic expects full-year 2024
mine production to be approximately 180,000t, which is below the
lower end of guidance provided in January 2024. Guidance for 2025
remains unchanged at 750,000-800,000t, and the Company will provide
updated long-term guidance after reaching commercial production,
anticipated in Q4.
Processing and Concentrate Sales
The Vares Processing Plant continues
to ramp-up and process higher grade feed now containing stoping
ore, which has led to increased concentrate production. The
crushing and haulage processes are working well and continue to
ramp up to meet the increasing supply of ore from the mine. Head
grades month-to-date are 10.8% Zn, 6.9% Pb, 292g/t Ag, 3.4g/t
Au.
Recoveries recorded month-to-date
are 66% Zn, 54% Pb, 86% Ag and 60% Au into their respective
concentrates. These are below design rates but are as expected
during the initial ramp-up phase of processing. With increasing
stabilisation of feed grade, base metal recoveries are expected to
improve to over 70% through Q4 as the plant moves to 24/7
operations.
The stockpile at Rupice currently
contains approximately 37,000t at 6.5% Zn, 4.9% Pb, 302g/t Ag,
2.8g/t Au, which will allow for blended plant feed closer to design
head grades. As stoping ore increases, grade variability will
decrease which will further optimise recoveries.
Concentrate grades have been good,
averaging 47% Zn, 2,200g/t Ag and 44% Pb month-to-date. Sales are
also progressing well with no issues on concentrate spec, and all
logistical aspects (truck, rail, port) are working as expected as
shipment volumes continue to increase. During September, the first
full train shipment of 36 containers moved concentrate to the
port.
Ausenco are currently completing a
study on increased plant throughput at a range of different rates
from the current capacity of 800ktpa, aligning with expanded mine
production from the additional reserves added at Rupice Northwest
in 2023. The Company will provide an update on this organic growth
opportunity and how it fits into the strategy for future value once
the study is completed.
Constitutional Court Ruling Impacts
The Constitutional Court decision
regarding access to state forestry land in July 2024 has impacted
the Company's ability to use the planned Tailings Storage Facility
('TSF') and waste rock storage facility. Therefore, Adriatic is
progressing plans for an alternative TSF at the former Veovaca open
pit site, as well as permitting for the waste rock area.
The new Veovaca TSF area is located
approximately 2km from the Vares Processing Plant. It is within the
existing concession boundary, does not involve the use of state
forestry lands and the Company owns the surface rights. The
required water and environmental permits are in progress, the
design is in its final stages and the construction approval is
expected in October. Early surface works and procurement are
ongoing, and permitted construction on road access has
commenced.
The current operating TSF has a
maximum capacity of approximately 133,000t, which on current
projections will allow tailings deposition into mid-Q1 2025.
Adriatic expects construction at the Veovaca TSF will be completed
by the end of 2024 and does not expect any impact on production
from lack of access to TSF capacity.
Financial
The Company's balance sheet remains
strong with $35.6m in cash as of the end of August and an
additional $25m in liquidity from the Orion facility (subject to
conditions precedent), which can be drawn until 31 December.
Combined with revenue from current stockpiles and ongoing
production, the Company expects to have sufficient liquidity to
ramp up to commercial production and cover debt repayments.
The first quarterly debt repayment to Orion of
approximately $18m is scheduled for 31 December 2024.
Laura Tyler, Interim Chief Executive Officer
commented:
"Adriatic has achieved a major milestone with mining its first
ore stopes in August, leading to a record month of production, in
addition to record development metres. Production in September has
already exceeded that total, another positive step as we continue
to ramp up towards nameplate production.
Over the last few weeks, I have spent time across the
operation, meeting our leaders, employees and contractors. It has
been awesome to see the connection they have to our values and
their pride in the Vares Silver Operation and its success. I have
also taken time to understand the support in the communities and
government - building a mining project is not easy, but the support
in Bosnia & Herzegovina is tremendous and the Company is
grateful for such unwavering endorsement.
We
are continuing to ramp up production - the heavy lifting of
construction has been completed and while there are a few elements
of infrastructure remaining to be finished, there is nothing in the
way of achieving commercial production over the coming
months.
We
have made excellent progress on the Veovaca tailings facility, with
early works started and permits expected in October. With the
continued use of the current temporary TSF into Q1 2025, I expect
production to be uninterrupted by tailings capacity issues through
2025 and beyond.
I
look forward to welcoming investors and analysts to site this week
to show them how Vares is now delivering critical metals to Europe,
and continuing to provide long term value for all our
stakeholders."
The webinar presentation is
available at: https://www.adriaticmetals.com/investors/corporate-presentations.
A recording of the webinar will be also published on the Adriatic
website post the event.
-ends-
Authorised by Laura Tyler, Interim CEO
For further information please
visit: www.adriaticmetals.com;
email: info@adriaticmetals.com,
@AdriaticMetals
on Twitter; or contact:
Adriatic Metals PLC
|
|
Klara Kaczmarek
GM - Corporate
Development
|
Tel: +44 (0) 7859 048228
Klara.kaczmarek@adriaticmetals.com
|
|
|
Burson Buchanan
|
Tel: +44 (0) 20 7466 5000
|
Bobby Morse / Christopher
Jones
|
adriatic@buchanan.uk.com
|
Morgans Corporate Limited
|
|
Rob Douglas / Sam Warriner / Mitch
Duffy
|
Tel: +61 7 3334 4888
|
|
|
RBC
Capital Markets
|
|
Farid Dadashev / James Agnew / Jamil
Miah
|
Tel: +44 (0) 20 7653 4000
|
|
|
Stifel Nicolaus Europe Limited
|
Ashton Clanfield / Callum Stewart /
Varun Talwar
|
Tel: +44 (0) 20 7710 7600
|
|
|
Sodali & Co
|
|
Cameron Gilenko
|
Tel: +61 466 984 953
|
ABOUT ADRIATIC METALS
Adriatic Metals Plc (ASX:ADT,
LSE:ADT1, OTCQX:ADMLF) is a precious and base metals developer that
is advancing the world-class Vares Silver Project in Bosnia &
Herzegovina, as well as the Raska Zinc-Silver Project in Serbia.
First concentrate production took place in February 2024 and the
Vares Silver Operation is fully funded to nameplate production,
which is expected in Q4 2024. Concurrent with ongoing operational
activities, the Company continues to explore across its highly
prospective 44km2 concession package.
MARKET ABUSE REGULATION DISCLOSURE
The information contained within
this announcement is deemed by the Company (LEI:
549300OHAH2GL1DP0L61) to constitute inside information for the
purpose of Article 7 of EU Market Abuse Regulation (EU) No.
596/2014 as it forms part of UK domestic law by virtue of the
European Union (Withdrawal) ACT 2018, as amended. The person
responsible for arranging and authorising the release of this
announcement on behalf of the Company is Laura Tyler, Interim
CEO.