27 February 2025
Kore Potash Plc
("Kore Potash" or
the "Company")
Kola Project Optimised DFS
update
Kore Potash, the potash development company
with 97% ownership of the Kola and DX Potash Projects in the
Sintoukola Basin, located within the Republic of Congo
("RoC"), is pleased to
provide an update in relation to the optimised Kola Definitive
Feasibility Study ("Optimised DFS") for the Kola Project
("Kola" or "Kola Project") further to the
announcement regarding the signing of the Engineering, Procurement
and Construction contract ("EPC") for the Kola Project with
PowerChina International Group Limited ("PowerChina") on 20 November
2024.
Prior to signing an EPC agreement, two studies
have been completed by the Company: the Kola Definitive Feasibility
Study ("DFS") in January
2019 and the Kola Project Optimisation Study ("Optimisation Study") in June 2022, details of both
of which have been released to AIM, JSE and ASX on 29 January 2019
and 28 June 2022 respectively. Following signing of the EPC
contract, the Company undertook an exercise to optimise the DFS to
account for the EPC contract, including updating the Kola
production schedule and the forecast financial information. The
Company has now completed its review of the Optimised DFS, with the
results summarised herein by way of update.
The results of the Optimised DFS incorporate
the most current information available to the Company, and have
been updated from the DFS and Optimisation Study to ensure
compliance with the latest applicable listing rule requirements and
other regulatory policies of the Australian Stock Exchange Limited,
and therefore should be considered as superseding the results of
both the DFS and the earlier Optimisation Study.
Unlike the DFS and the Optimisation Study, the
Optimised DFS is based on a production period which utilizes all
Proved and Probable Ore Reserves and only 6% of Inferred
Minerals Resources, giving a Life of Mine
("LoM") of 23
years.
Kore Potash considers there is strong potential
for the mine plan on which this Optimised DFS is based to be
extended beyond 23 years by upgrading a portion of the 340 Mt of
Inferred Mineral Resources to Measured or Indicated Resources
through further exploration during the 23 years of
operations.
Highlights of
the Optimised DFS
·
|
Capital cost of US$2.07 billion
(nominal basis) on a signed fixed price EPC basis, including
owner's costs.
|
·
|
Assumed construction start date of 1
January 2026, with construction period of 43 months.
|
·
|
Kola designed with a nameplate
capacity of 2.2 million tonnes per annum ("Mtpa") of Muriate of Potash
("MoP").
|
·
|
Average MoP production per year of
2.2 Mtpa of MoP for total MoP production of 50Mt over a 23-year
life of mine.
|
·
|
Average cost of MoP delivered to
Brazil is US$128/t. Based on an independent MoP market study
commissioned by the Company, management considers Kore Potash is
projected to become one of the lowest cost producers in the global
agricultural market to Brazil.
|
·
|
Average annual EBITDA is
approximately US$733 million. Kore Potash is projected to continue
to enjoy a very high average EBITDA margin of 74%.
|
·
|
Key financial metrics, at MoP CFR
Brazil pricing averaging US$449/tonne and on a 90% attributable
basis (reflecting Kore's future holding of 90% and the RoC
government 10%):
|
|
o -
Kola NPV10% (real)
post-tax US$1.7 billion
|
|
|
o -
IRR 18% (real) on ungeared post-tax basis
|
|
·
|
Kola is designed as a conventional
mechanised underground potash mine with shallow shaft access. Ore
from underground is transported to the processing plant via an
approximately 25.5 km long overland conveyor. After processing, the
finished product is conveyed 8.5 km to the marine export facility.
MoP is transferred from the storage area onto barges via a
dedicated barge loading jetty before being transhipped into
ocean-going vessels for export.
|
Cautionary
Statement:
The
production target (and the forecast financial information derived
from this production target) includes all of Kore Potash's reported Ore
Reserve estimates, together with a proportion of Inferred Mineral
Resources. The production target includes relative portions of ore
by category of Proved and Probable Ore Reserves (94%) and Inferred
Mineral Resources (6%). The Company is satisfied that the
proportion of Inferred Mineral Resources is not the determining
factor in project viability as the project demonstrates positive
economic outcomes with the Inferred Mineral Resources excluded.
There is a low level of geological confidence associated with
Inferred Mineral Resources and there is no certainty that further
exploration work will result in the determination of Indicated
Mineral Resources or that the production targets will be
realised.
The forecast
financial information derived from the production target uses Argus
Media Marketing's forecast annual MoP CFR Brazil
prices to 2047 and then an
incremental increase of US$2/t annually post 2047, which annual
prices imply an average MoP CFR Brazil price of US$449/t over the
23 years of scheduled production in the Optimised DFS. As discussed
in section 12 (Potash Marketing), Kore Potash has concluded it has
a reasonable basis for the use of those prices, but there is no
guarantee that such prices will be realised and lower product
pricing will significantly affect the financial performance of the
Kola Project. Refer to the sensitivity analysis in section 14
(Economic Evaluation) for further details, together with the
Forward Looking Statements notice below.
To achieve
the range of outcomes indicated in the Optimised DFS, the Optimised
DFS estimates that funding in the order of US$2.07 billion (nominal
basis) in construction capital will be required. Shareholders and
investors should be aware that there is no certainty that Kore
Potash will be able to raise the required funding when needed and
it is possible that such funding may only be available on terms
that may be highly dilutive or otherwise adversely affect Kore
Potash shareholders' exposure to the Kola Project economics. Whilst
the Company has made progress towards financing the development of
the Kola Project as discussed further in section 15 (Project
Funding) of Appendix A, those arrangements are currently
non-binding and therefore there is currently no certainty that the
Company will be able to raise the funds required to develop the
Kola Project, or if funding is available, the terms of such
funding.
Andre Baya,
Chief Executive Officer of Kore Potash,
commented:
"The Kola Project is of global
significance as the security of the world's food supply is at the
mercy of global disruptions to fertilizer supply. Recent
geopolitical events have highlighted this risk as potash production
is concentrated among a small number of companies and
countries.
Furthermore,
to reduce the carbon footprint of our industry, new potash
producers need to be geographically closer to end users with
reduced freight cost and environmental impact. In that sense,
Kola's location is ideal to supply environmentally-friendly potash
to meet the growing demand of the Brazilian
market.
As our
operating cost, inclusive of freight, is of USD 128.19/MT (CFR
Brazil), we can vie for a higher profit margin than any existing
potash mine worldwide when it comes to serving our target market.
With an NPV10 of USD 1.7 Billion for our production target, the
Kola project reaches an enticing IRR of 18%.
The execution
of the Kola EPC contract with PowerChina now moves Kore Potash one
gigantic step closer to production and we eagerly await financial
close to start construction."
Kola Project
Optimised DFS update, EPC
On 6 April 2021, Kore Potash announced the
signing of a non-binding Memorandum of Understanding ("MoU") with the Summit Consortium
("Summit") to arrange the
full financing required for the construction of the Kola
Project.
The Optimisation Study, which represented the
first part of the financing process, was undertaken by SEPCO
Electric Power Construction Corporation ("SEPCO"). PowerChina is SEPCO's parent
company. The key goals of the Optimisation Study were to improve
Kola's value through reductions in capital costs and by shortening
the construction schedule.
During the Optimisation Study, SEPCO employed
two key subcontractors: China ENFI Engineering Corporation to
review the mining, processing, and infrastructure aspects of the
Project, and CCCC-FHDI Engineering Co Limited to optimise the
marine facilities.
The optimisations continued in 2023 and 2024
and included in-country work to better define geotechnical
conditions. These works culminated in signing a US$1.929 billion
fixed-cost EPC agreement on 19 November 2024. The EPC
included refined cost
estimates with a knowledge of conditions at each construction
location. The Company worked with certain potential suppliers and
vendors to refine the Kola Project requirements and obtained
pricing updates where necessary.
A summary of the key Kola Project parameters
and assumptions adopted in the Optimised DFS update post signing
EPC agreement are summarised in Table 1
below.
Table 1: Key
Project Parameters and Assumptions
Result
|
Unit
|
Production Target
|
Total MOP production
|
Mt
|
50
|
Initial project life
|
Years
|
23
|
Average scheduled mining rate
|
Mtpa ore
|
7.0
|
KCl recovery in process plant
|
% KCl
|
89.9%
|
Average MOP production per year
|
Mtpa
|
2.20 Mtpa
|
Capital Cost EPC basis (real)*
|
US$
billion
|
2.01
|
Sustaining capital
|
US$/t MOP
|
13.06
|
Construction schedule
|
months
|
43
|
Steady state operating cost (Mine
gate)
|
US$/t MOP
|
74.94
|
Operating cost (CFR Brazil)
|
US$/t MOP
|
128.19
|
Forecast average MoP granular price (CFR
Brazil)**
|
US$/t MOP
|
449
|
Post tax, real un-geared
NPV10%
|
US$
million
|
1,675
|
Post tax, real un-geared IRR
|
%
|
18%
|
Average EBITDA per annum real
|
US$
million
|
733
|
Average EBITDA margin
|
%
|
74%
|
Notes:
* The
US$2.01 billion capital cost (real) includes US$141 million for
Kore's owner's costs during the EPC phase.
** US$449/t is Argus Media Group's forecast real average future potash CFR
Brazil prices over the project life. Further details in Item
12 Potash Marketing
below.
Key assumptions related to the ore reserves,
production schedules and financial evaluation of the project have
been updated in Appendix B of this announcement.
Ore Reserves
and Mineral Resources
The Kola Potash Ore Reserves (Table 2) are
based on the Kola Sylvinite Mineral Resources (Table 3) as
confirmed on 27 Feb 2025. Further detail on the Ore Reserve
Estimate is provided in Appendix B: Summary of Information required
according to ASX Listing Rule 5.9.1 and Appendix C: JORC 2012 -
Table 1, Section 4 Ore Reserves. All of the Ore Reserves and
Mineral Resources reported here for Kola are Sylvinite.
Table 2: Kola
Sylvinite Ore Reserves
Classification
|
Ore Reserves
(Mt)
|
KCl grade
(% KCl)
|
Mg
(% Mg)
|
Insolubles
(% Insol.)
|
Proved
|
61.8
|
32.1
|
0.11
|
0.15
|
Probable
|
90.6
|
32.8
|
0.10
|
0.15
|
Total Ore
Reserves
|
152.4
|
32.5
|
0.10
|
0.15
|
Table 3: Kola
Sylvinite Mineral Resources (inclusive of Ore Reserves)
*
Classification
|
Million Tonnes
(Mt)
|
KCl
(% KCl)
|
Mg
(% Mg)
|
Insoluble
(% Insol.)
|
Total Measured
|
215.7
|
35.0
|
0.08
|
0.13
|
Total Indicated
|
292.0
|
35.7
|
0.06
|
0.14
|
Total Inferred
|
340.0
|
34.0
|
0.08
|
0.25
|
Total Mineral
Resources
|
847.7
|
34.9
|
0.08
|
0.18
|
* The Kola Mineral Resource Estimate
was confirmed on 27 Feb 2025 in an announcement titled
"Confirmation of Mineral Resource for Kola Deposit".
Production
targets and forecast financial information derived from
production targets
This release contains information that
constitutes a production target for the Kola Project (and forecast
financial information derived from that production target) for the
purposes of the ASX Listing Rules.
Ore Reserve and Mineral Resource estimates
underpinning the production target for the Kola Project referred to
in this release were prepared by, or under the supervision of, a
Competent Person in accordance with the JORC Code, 2012 Edition.
Competent Person's statements are set out on page 6. Details of
those Ore Reserves and Mineral Resources are set out in this
announcement (including, in relation to the Ore Reserves, the
details in Appendix B and Appendix C).
The production target includes relative
portions of ore by category of Proved and Probable Ore Reserves
(94%) and Inferred Mineral Resources (6%).
The material assumptions applied in the
estimation of the production target for the Kola Project project
and forecast financial information derived from those production
target are set out in the summaries of the study outcomes
accompanying this announcement.
The Company is satisfied that in each case, the
proportion of Inferred Mineral Resources is not the determining
factor in project viability as the project demonstrates positive
economic outcomes with the Inferred Mineral Resources excluded.
There is a low level of geological confidence associated with
Inferred Mineral Resources and there is no certainty that further
exploration work will result in the determination of Indicated
Mineral Resources or that the production target will be
realised.
Market Abuse
Regulation
This announcement contains inside information
for the purposes of Article 7 of the Market Abuse Regulation (EU)
596/2014 as it forms part of UK domestic law by virtue of the
European Union (Withdrawal) Act 2018 ("MAR"), and is disclosed in accordance
with the Company's obligations under Article 17 of MAR.
This announcement has been approved
for release by the Board.
For further information, please
visit www.korepotash.com
or contact:
Kore Potash
Andre Baya, CEO
|
|
Andrey Maruta, CFO
|
Tel: +44 (0) 20 3963 1776
|
Tavistock Communications
Emily Moss
Nick Elwes
Josephine Clerkin
|
Tel: +44 (0) 20 7920 3150
|
SP
Angel Corporate Finance - Nomad and
Broker
Ewan Leggat
Charlie Bouverat
Grant Barker
|
Tel: +44 (0) 20 7470 0470
|
Shore Capital - Joint
Broker
Toby Gibbs
James Thomas
|
Tel: +44 (0) 20 7408 4050
|
Questco Corporate Advisory -
JSE Sponsor
Doné Hattingh
|
Tel: +27 63 482 3802
|
END
Competent Persons Statement
The estimated Ore Reserves and
Mineral Resources underpinning the production target have been
prepared by a competent person in accordance with the requirements
of the 2012 Edition of the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves
(JORC Code, 2012
Edition).
The information relating to
Exploration Results and Mineral Resources in this announcement is
based on, or extracted from previous reports referred to herein,
and available to view on the Company's website
https://korepotash.com.
The Kola Mineral Resource Estimate was confirmed on 27 Feb 2025 in
an announcement titled "Confirmation of Mineral Resource for Kola
Deposit". The Company confirms that it is not aware of any new
information or data that materially affects the information
included in the original market announcements and that all material
assumptions and technical parameters underpinning the estimates in
the relevant market announcement continue to apply and have not
materially changed. The Company confirms that the form and context
in which the Competent Person's findings are presented have not
been materially modified from the original market
announcement.
The information in this announcement
that relates to Mineral Resources is based on information compiled
or reviewed by, Garth Kirkham, P.Geo., who has read and understood
the requirements of the JORC Code, 2012 Edition. Mr. Kirkham is a
Competent Person as defined by the JORC Code, 2012 Edition, having
a minimum of five years of experience that is relevant to the style
of mineralization and type of deposit described in this
announcement, and to the activity for which he is accepting
responsibility. Mr. Kirkham is member in good standing of Engineers
and Geoscientists of British Columbia (Registration Number 30043)
which is an ASX-Recognized Professional Organization (RPO). Mr.
Kirkham is a consultant engaged by Kore Potash Plc to review the
documentation for Kola Deposit, on which this announcement is
based, for the period ended 29 October 2018. Mr. Kirkham has
verified that this announcement is based on and fairly and
accurately reflects in the form and context in which it appears,
the information in the supporting documentation relating to
preparation of the review of the Mineral Resources.
The information in this announcement
that relates to Ore Reserves is based on information compiled or
reviewed by, Mo Molavi, P. Eng., who has read and understood the
requirements of the JORC Code, 2012 Edition. Mr. Molavi is a
Competent Person as defined by the JORC Code, 2012 Edition, having
a minimum of five years of experience that is relevant to the style
of mineralization and type of deposit described in this
announcement, and to the activity for which he is accepting
responsibility. Mr. Molavi is member good standing of
Engineers and Geoscientists of British Columbia (Registration
Number 37594) which is an ASX-Recognized Professional Organization
(RPO). Mr. Molavi is a consultant engaged by Kore Potash Plc to
review the documentation for Kola Deposit, on which this
announcement is based, for the period ended 29 October 2018. Mr.
Molavi has verified that this announcement is based on and fairly
and accurately reflects in the form and context in which it
appears, the information in the supporting documentation relating
to preparation of the review of the Ore Reserves.
Forward-Looking Statements
This announcement contains certain
statements that are "forward-looking" with respect to the financial
condition, results of operations, projects and business of the
Company and certain plans and objectives of the management of the
Company. Forward-looking statements include those containing words
such as: "anticipate", "believe", "expect," "forecast",
"potential", "intends," "estimate," "will", "plan", "could", "may",
"project", "target", "likely" and similar expressions identify
forward-looking statements. By their very nature forward-looking
statements are subject to known and unknown risks and uncertainties
and other factors which are subject to change without notice and
may involve significant elements of subjective judgement and
assumptions as to future events which may or may not be correct,
which may cause the Company's actual results, performance or
achievements, to differ materially from those expressed or implied
in any of our forward-looking statements, which are not guarantees
of future performance. There are a number
of risks, both specific to Kore Potash, and of a general nature,
which may affect the future operating and financial performance of
Kore Potash, and the value of an investment in Kore Potash
including and not limited to title risk, renewal risk, economic
conditions, stock market fluctuations, commodity demand and price
movements, timing of access to infrastructure, environmental risks,
regulatory risks, operational risks, reliance on key personnel, Ore
Reserve estimations, local communities risks, foreign currency
fluctuations, and mining development, construction and
commissioning risks.
Neither the Company, nor any other
person, gives any representation, warranty, assurance or guarantee
that the occurrence of the events expressed or implied in any
forward-looking statement will occur. Except as required by
law, and only to the extent so required, none of the Company, its
subsidiaries or its or their directors, officers, employees,
advisors or agents or any other person shall in any way be liable
to any person or body for any loss, claim, demand, damages, costs
or expenses of whatever nature arising in any way out of, or in
connection with, the information contained in this
document.
In particular, statements in this
announcement regarding the Company's business or proposed business,
which are not historical facts, are "forward-looking" statements
that involve risks and uncertainties, such as Mineral Resource
estimates market prices of potash, capital and operating costs,
changes in project parameters as plans continue to be evaluated,
continued availability of capital and financing and general
economic, market or business conditions, and statements that
describe the Company's future plans, objectives or goals, including
words to the effect that the Company or management expects a stated
condition or result to occur. Since forward-looking statements
address future events and conditions, by their very nature, they
involve inherent risks and uncertainties. Actual results in each
case could differ materially from those currently anticipated in
such statements. Shareholders are cautioned not to place undue
reliance on forward-looking statements, which speak only as of the
date they are made. The forward-looking statements are based on
information available to the Company as at the date of this
release. Except as required by law or regulation (including the ASX
Listing Rules), the Company is under no obligation to provide any
additional or updated information whether as a result of new
information, future events, or results or otherwise.
Summary information
Kore Potash plc has prepared this
announcement. This document contains general background information
about Kore Potash plc current at the date of this announcement. It
does not constitute or form part of any offer or invitation to
purchase, otherwise acquire, issue, subscribe for, sell or
otherwise dispose of any securities, nor any solicitation of any
offer to purchase, otherwise acquire, issue, subscribe for, sell,
or otherwise dispose of any securities. The announcement is in
summary form and does not purport to be all-inclusive or complete.
It should be read in conjunction with the Company's other periodic
and continuous disclosure announcements, which are available to
view on the Company's website https://korepotash.com.
The announcement, publication or
distribution of this announcement in certain jurisdictions may be
restricted by law, and therefore, persons in such jurisdictions
into which this announcement is released, published or distributed
should inform themselves about and observe such
restrictions.
Not
financial advice
This document is for information
purposes only and is not financial product or investment advice,
nor a recommendation to acquire securities in Kore Potash plc. It
has been prepared without considering the objectives, financial
situation or needs of individuals. Before making any investment
decision, prospective investors should consider the appropriateness
of the information having regard to their own objectives, financial
situation and needs and seek legal and taxation advice appropriate
to their jurisdiction.
Appendix A: Summary of Kola Project Optimised DFS update -
December 2024
1.
|
Project Introduction:
|
|
Kore Potash is a mineral exploration
and development company that is incorporated in the United Kingdom
and listed on the AIM (a sub-market of the London Stock Exchange,
as KP2), the Australian Securities Exchange (ASX, as KP2),
the Johannesburg Stock Exchange (JSE,
as KP2) and A2X Proprietory Limited (an independent stock exchange
in South Africa, A2X, as KP2) Markets.
|
|
|
|
The primary asset of Kore is the
Kola Project located in the RoC, held by the 97%-owned Sintoukola
Potash SA ("SPSA"). SPSA
has 100% ownership of the Kola Mining Lease, on which the Kola
Project is located.
|
|
|
|
The Kola Project is situated in the
Kouilou Province of the RoC, within 40 km of the Atlantic Coast and
approximately 70 km north of the port city of Pointe
Noire.
|
|
|
|
The Kola DFS considers the mining of
the Kola Sylvinite, and the production of approximately 2.2 Mtpa of
MoP and its export to its target markets and considers all
associated infrastructure. It delivers an economic model based on
life of project of 23 years that is based upon 23 production years
exploiting Ore Reserves of 152.4 Mt and 9.7 Mt of Inferred Mineral
Resource.
|
|
In 2017, Kore commissioned a
consortium of French companies ("FC") to conduct a DFS for the Kola
Project. The FC included: Technip France ("TPF"), Vinci Construction Grands
Projets ("VCGP"), Egis
International ("EGIS") and
Louis Dreyfus Armateurs ("LDA").
Met-Chem DRA Global ("MTC") and AMC Consulting ("AMC") were appointed by the FC as their
specialist subconsultants.
Kore directly contracted with MTC
for the Mineral Resource Estimate ("MRE"), and SRK Consulting (UK) Limited
("SRK") for undertaking the
Environmental and Social Impact Assessment ("ESIA").
The Kola DFS was finalised in
January, 2019.
|
|
On 6 April 2021, Kore Potash
announced the signing of a non-binding MoU with Summit to arrange
the full financing required for the construction of the Kola
Project.
The Optimisation Study, which
represented the first part of the financing process, has been
undertaken by SEPCO. PowerChina is SEPCO's
parent company. The key goals of the
Optimisation Study were to improve the value of Kola through
reductions in the capital cost and by shortening the construction
schedule.
During the Optimisation
Study, SEPCO employed two key sub-contractors, China ENFI Engineering
Corporation to review the mining, processing and infrastructure
aspects of the Project and CCCC-FHDI Engineering Co Limited to
consider the optimisation of the marine facilities.
A Deepening Design Study phase was
conducted in 2023 and included in-country work to better define
geotechnical conditions. The Deepening Design Study also refined
cost estimates with a knowledge of conditions at each construction
location. These works culminated in signing
a US$1.929 billion fixed-cost EPC agreement on 19 November
2024. The Company worked with certain
potential suppliers and vendors to refine the Kola Project
requirements and obtained pricing updates where
necessary.
|
|
Prior to 2019, Kore directly
contracted with MTC for the Mineral Resource Estimate, and SRK for
undertaking an ESIA. The ESIA received a 25-year approval from the
Congolese Environmental authorities and while still valid, it will
require a minor amendment linked to the change of location of the
Process plant. The MRE has remained unchanged and has been
incorporated into the Optimisation Study update together with the
ESIA recommendations.
Figure 1 shows the Location Map for
the Optimised Kola Project
|
Figure 1: Location Map
showing Optimised Kola Project

2. Mineral Resource
The Kola Mineral Resources are
summarised in Table 4 below.
The total Measured and Indicated
Mineral Resources are 508 Mt with an average grade of 35.4% KCl and
provides the basis for the Ore Reserve statement. Sections 1
to 3 of the JORC 2012 Table 1 Checklist of Assessment and Reporting
Criteria for that Mineral Resource estimate remain unchanged as
confirmed to shareholders on 27 Feb 2025, and can be found in
Appendix D.
The Company confirms there has been
no material change to those Mineral Resources. The Company advises
that the Mineral Resources are inclusive of Mineral Resources to
which modifying factors have been applied to be reported as Ore
Reserves.
In accordance with JORC 2012, the
Competent Persons ("CP")
for the Kola MRE is:
o Mr. Kirkham P.
Geo of MTC. Mr Kirkham is a member of good standing of the
Association of Professional Engineers and Geoscientists of British
Columbia.
Table 4 July
2017 Kola Mineral Resources for Sylvinite
July 2017 -
Kola Deposit Potash Mineral Resources - SYLVINITE
|
|
Million Tonnes
|
KCl
|
Mg
|
Insoluble
|
|
Mt
|
%
|
%
|
%
|
Hanging wall Seam
|
Measured
|
‒
|
‒
|
‒
|
‒
|
Indicated
|
29.6
|
58.5
|
0.05
|
0.16
|
Inferred
|
18.2
|
55.1
|
0.05
|
0.16
|
Total Mineral
Resources
|
47.8
|
57.2
|
0.02
|
0.16
|
Upper Seam
|
Measured
|
153.7
|
36.7
|
0.04
|
0.14
|
Indicated
|
169.9
|
34.6
|
0.04
|
0.14
|
Inferred
|
220.7
|
34.3
|
0.04
|
0.15
|
Total Mineral
Resources
|
544.3
|
35.1
|
0.04
|
0.14
|
Lower Seam
|
Measured
|
62.0
|
30.7
|
0.19
|
0.12
|
Indicated
|
92.5
|
30.5
|
0.13
|
0.13
|
Inferred
|
59.9
|
30.5
|
0.08
|
0.11
|
Total Mineral
Resources
|
214.4
|
30.6
|
0.13
|
0.12
|
Footwall Seam
|
Measured
|
‒
|
‒
|
‒
|
‒
|
Indicated
|
‒
|
‒
|
‒
|
‒
|
Inferred
|
41.2
|
28.5
|
0.33
|
1.03
|
Total Mineral
Resources
|
41.2
|
28.5
|
0.33
|
1.03
|
Total Measured
+ Indicated
|
507.7
|
35.4
|
0.07
|
0.14
|
Total
Inferred
|
340.0
|
34.0
|
0.08
|
0.25
|
Total Mineral
Resources
|
847.7
|
34.9
|
0.08
|
0.18
|
3. Ore Reserves
The Kola Ore Reserves are summarised
in Table 5 below.
The Kola Sylvinite Ore Reserves are
152.4 Mt with average grade of 32.5% KCl. Section 4 of the JORC
2012 Table 1 as reported to shareholders on 29 January 2019 has
been updated based on the Optimised DFS and is included in this
announcement in Attachment C.
The original statement of Ore
Reserves was prepared by Met-Chem DRA Global and was reported in
accordance with JORC 2012.
In conjunction with the Optimised
DFS the Ore Reserves have been reviewed and restated in accordance
with JORC 2012 by the CP for the Kola Ore Reserves:
o Mr. Molavi P.
Eng. of AMC, for the Reserve Review ("RR"). Mr Molavi is a member of
good standing of the Association of Professional Engineers and
Geoscientists of British Columbia.
There is no change to the Kola Sylvinite Ore
Reserves from those previously reported.
Table 5: Kola
Sylvinite Ore Reserves
Seam
|
Classification
|
Ore Reserves
Tonnage
(Mt)
|
KCl
(%KCl)
|
Mg
(%Mg)
|
Insolubles
(%Insol)
|
Upper
Seam Sylvinite
|
Proved
|
47.3
|
33.43
|
0.08
|
0.15
|
Probable
|
58.7
|
31.83
|
0.06
|
0.15
|
Total
|
106.0
|
32.54
|
0.07
|
0.15
|
Lower
Seam Sylvinite
|
Proved
|
14.5
|
27.88
|
0.20
|
0.13
|
Probable
|
23.4
|
28.35
|
0.08
|
0.14
|
Total
|
37.9
|
28.17
|
0.13
|
0.14
|
Hanging
Wall Seam Sylvinite
|
Proved
|
|
|
|
|
Probable
|
8.4
|
52.09
|
0.47
|
0.19
|
Total
|
8.4
|
52.09
|
0.47
|
0.19
|
TOTAL
|
Proved
|
61.8
|
32.13
|
0.11
|
0.15
|
Probable
|
90.6
|
32.81
|
0.10
|
0.15
|
Total Ore Reserves
|
152.4
|
32.54
|
0.10
|
0.15
|
All Sylvinite in the Measured and
Indicated Resource category was considered for Ore Reserve
conversion because of the sharp grade boundaries of the Sylvinite
seams and the fact that the economic Cut- off Grade ("CoG") is below the Mineral Resources CoG of 10% KCl.
Table 6. Kore's Sylvinite Mineral Resources and Ore
Reserves
KOLA
SYLVINITE DEPOSIT
|
|
|
|
|
|
Gross
|
Net Attributable (90%)
|
Mineral
Resource Category
|
Million Tonnes
|
Grade KCl %
|
Contained KCl million
tonnes
|
Million Tonnes
|
Grade KCl %
|
Contained KCl million
tonnes
|
Measured
|
216
|
34.9
|
75
|
194
|
34.9
|
68
|
Indicated
|
292
|
35.7
|
104
|
263
|
35.7
|
94
|
Sub-Total
Measured + Indicated
|
508
|
35.4
|
180
|
457
|
35.4
|
162
|
Inferred
|
340
|
34.0
|
116
|
306
|
34.0
|
104
|
TOTAL
|
848
|
34.8
|
295
|
763
|
34.8
|
266
|
|
|
|
|
|
|
|
|
Gross
|
Net Attributable (90%)
|
Ore Reserve
Category
|
Million Tonnes
|
Grade KCl %
|
Contained KCl million
tonnes
|
Million Tonnes
|
Grade KCl %
|
Contained KCl million
tonnes
|
Proved
|
62
|
32.1
|
20
|
56
|
34.9
|
19
|
Probable
|
91
|
32.8
|
30
|
82
|
35.7
|
29
|
TOTAL
|
152
|
32.5
|
50
|
137
|
35.4
|
49
|
Table provided
as Gross and Net Attributable (reflecting Kore's future holding of
90% and the RoC government 10%), prepared and reported according to
the JORC Code, 2012 edition. Table entries are rounded to the
appropriate significant figure.
Ore Reserves
are not in addition to Mineral Resources but are derived from them
by the application of modifying factors.
|
4. Mining
The Kola mine design utilised in the
Optimised DFS remains materially unchanged from the design used in
the DFS and is described below:
The Kola orebody is planned to be
mined using conventional underground mechanised methods, extracting
the ore within 'panels', using Continuous Miner ("CM") machines of the drum-cutting type.
This is the most widely used method of potash mining world-wide and
is considered a low-risk method. The mine design adopts a
relatively typical layout including panels, comprised of rooms and
pillars. Pillars are the support rock left in place to provide
stable ground support during the operation of the mine.
The mine design is based on a
minimum mining height of 2.5 m with mining being undertaken by a CM
which is capable of mining seam heights of between 2.5 m and 6 m.
Each panel is accessed by 4 entries. Each entry is 8m wide and 3m
to 6m high depending on the seam height. The rooms are mined in a
chevron pattern at an angle of 65 degrees from the middle entry,
each with a length of approximately 150 m.
Key geotechnical parameters
evaluated in the mine design were:
o support
interval between potash seams to be minimum of 3 m
thick,
o 8 m wide
pillar between consecutive production rooms (of 8 m
each)
o 50 m wide
pillar between Production Panels and between the side of the
Production Panel and the Main Haulage
o minimum
thickness of 10 m to 15 m of the Salt Member between the mine
openings and the floor of the overlying Anhydrite Member (referred
to as the 'salt back')
o stand-off
distance of 20 m from any exploration holes
o stand-off
distance of between 30 m - 60 m from significant geological
anomalies
o pillar of 300
m in radius around Shafts
Mine access is provided by two
vertical Shafts, each 8 m in diameter. The shafts will be sunk near
the center of the orebody. To provide access to the underground,
the Intake Shaft will be equipped with a hoist and cage system for
transportation of persons and material. The Exhaust Shaft will be
equipped with a Pocket Lift conveyor system to continuously convey
the mined-out ore to the surface. Both shafts are approximately 270
m deep.
Mining equipment selected for the
Kola Project Mine includes a fleet of 7 electrically powered
continuous miners. Ore haulage from the CMs to the feeder breaker
apron feeder will be done using electrically-powered Shuttle Cars,
with a rated payload of 30 t and a 250 m power supply
cable.
Underground conveyor belts will be
used for ore transportation to the shaft. The belt conveyors are
distributed in the haulages and into the working panels near the CM
working face. The ore will be placed on the belts from feeder
breakers that are fed by the Shuttle Cars. Belt conveyors will
carry the ore loaded by the feeder breakers to the ore bins. The
ore is then conveyed from the ore bins to the vertical conveyor (Pocket Lift) system located in the
Exhaust Shaft.
5. Life of Project
schedule
The LoM production schedule reported
in the Optimised DFS is as summarized below.
The project LoM production schedule,
including tonnes of ROM, tonnes of MoP product, and the average KCl
grade of the Run-Of-Mine ("ROM") material, is summarized in Figure
2.
The Life of Ore Reserves for the
Kola Project is estimated at 23 years, and full-scale production
averaging approximately 2.1 million tonnes per annum of MoP
from Ore Reserves occurs for approximately
21 years post commissioning and ramp up.
During the exploitation of Ore Reserves, 9.7 Mt of Inferred Mineral
Resources are scheduled to be mined and processed. This represents
approximately 6.0% of the total amount of
ROM material processed in the first 23 years. This
portion of the Inferred Mineral Resources is at the periphery of
the Mineral Resources envelope and immediately adjacent to the Ore
Reserves and logically would be extracted in conjunction
with the adjacent Ore Reserves.
In preparing the production target
and economic evaluation, each of the modifying factors was
considered and applied and the Company considers there are
reasonable grounds for the inclusion of Inferred Mineral Resources
in the production target for the Kola Project.
There is a low level of geological
confidence associated with Inferred Mineral Resources and there is
no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the production
target itself will be realized.
The Ore Reserves (Proved and
Probable) and Inferred Mineral Resources underpinning the
production target have been prepared by a competent person in
accordance with the requirements of JORC 2012. Details of those Ore
Reserves and Mineral Resources are set out in this announcement
(including, in relation to the Ore Reserves, the details in
Appendix B and Appendix C).
No Exploration Target material has
been included in the economic evaluation for the Kola
Project.
Figure 2 - Life-of-Mine Production Summary of the Kola
Mine

Kore Potash believes there is a
strong potential for the LoM Production to be extended beyond 23
years by upgrading a portion of the 340Mt of Inferred Mineral
Resources to Measured or Indicated resource, through further
exploration during operations.
6. Hydrogeology
The DFS hydrogeological investigations have
been used in the Optimised DFS and there are no changes to the
information or assumptions related to hydrogeology. The
hydrogeology test work that was carried out, is summarised
below:
1. Identify sources of fresh water
supply for construction and operations.
These tests concluded that process plant area
water supply is available at required rate of 150 m3/hr
utilising 5 wells at a depth of 120 m. Similarly, the required
water supply at the mine site of 30 m3/hr can be
supplied via 2 wells sunk to 120 m depth. Hydrogeological modelling
indicates that extraction of these quantities of water over the
project life will not adversely impact the aquifers and minor
drawdown in the aquifers is expected over the life of the
project.
2. Understand the risk that
aquifer system poses to mining operations and how
to mitigate this
risk.
The risk of water ingress to
the mining areas is a common
risk in almost all
salt and potash mines. These mines are
typically overlain by water-bearing sediments. At operating potash
mines in Canada and Europe, the hydrogeological risk is considered
higher in areas of disturbance of the stratigraphy, referred to as
geological or subsidence anomalies. At Kola, a detailed
understanding of the aquifers overlying the evaporite rocks, as
well as of the aquitards (or barriers to water flow), has been
developed over a number of years. The conclusions drawn following
hydrogeological testing were:
o A problematic
water ingress is considered a low probability as no linear faults
have been identified and all potential subsidence features can be
accurately delineated using (proposed 50 m spaced line) 3D seismic
surveying, to add to the existing 186 km of seismic survey data
over the Deposit.
o No mining or
shaft sinking is planned within areas of subsidence. In addition,
horizontal 'cover drilling' and ground penetrating radar ("GPR")
will be employed as forward-looking actions to improve
understanding of ground conditions in advance of mining and further
mitigate the risk of intersecting a structure or area of
disturbance.
o The mine
design incorporates a 10-15 m minimum 'salt-back' barrier between
the mining area and the anhydrite aquitard, effectively reinforcing
the anhydrite member aquitard
layer.
3. Understand the impacts of
groundwater composition and the aquifers on the shaft
sinking
operation.
The results of this testing
confirmed:
o That ground
freezing during shaft sinking will not be impacted by hydraulic
flow or high salinity in the deep aquifer. In fact, low
permeability, and low total dissolve solids ("TDS") and salinity in both aquifers is
to be expected, supporting the planned freeze-hole spacing and
comparatively low energy consumption for the ground freezing
operation.
o The presence
of a thick Anhydrite Member (12 m) overlying the salt member which
acts as an aquitard and reduces risk of water inflow into the salt
member.
7. Metallurgy and Process
Ore from underground is transported to the process
plant via an overland conveyor approximately 24 kilometers
long.
A conventional potash flotation plant with a maximum
designed production of 2.2 million tonnes per annum of MoP has been
designed for the Kola Project. As a result of the low Insolubles
content, no separate process circuit is required to remove
Insoluble material.
The final MoP product is then
transported 11 km by conveyor belt from process plant to the marine
export facility at the coast.
A schematic of the full process to extract ore and
produce MoP product is shown in Figure 3.
Figure 3: Process
flow from mine to ship

The design strategy adopted delivers a Process Plant
designed to produce 2.2 Mtpa of MoP at a KCl grade of 95.3 %w and
that will accommodate the variety of ROM feedstock characteristics
expected to be encountered during the Life of the project.
The optimised process design
references the DFS metallurgical test work in 2017 and 2018. The
description of the test work used in the Optimised DFS is
summarised below.
Characterisation tests were
performed on pure seam samples (USS, LSS and HWS) expected to be
mined as part of the mine schedule. Composite samples of multiple
seams, prepared to be as representative as possible of the expected
range of Run of Mine Ore characteristics foreseen in the mine
schedule, were prepared from the seam samples.
The insoluble content of the
samples was less than 0.5%w and close to 0.1%w in the composite
from the USS and LSS. The characterisation of both the composite
samples and the pure seam samples established that the KCl content
in the composite was 32.2%w.
A process plant KCl recovery rate
of 89.9% has been used in the economic evaluation.
8. Marine Facilities
The marine facility used in the
Optimised DFS was based on the DFS design. A summary of the design
is given below.
A trans-shipment arrangement has
been designed whereby MoP for export is
loaded from a dedicated Jetty into self-propelled shuttle Barges
(two units), which then travel to the Ocean-Going Vessels
("OGVs") anchored 11
nautical miles (20 km) offshore at a dedicated transshipment zone.
The MoP is transferred from the Barges to the OGVs using a Floating
Crane Transhipper Unit ("FCTU").
Transshipping was selected over
direct ship loading from the export jetty. The ocean depth along
the coastline is shallow and it was not considered feasible to
construct the length of jetty required to facilitate direct ship
loading.
To ensure sufficient year-round
operational availability of the Jetty, a breakwater structure has
been designed to shelter the berthing area for Barge loading
operations.
The Jetty has been widened to
accommodate both a Seawater Intake ("SWI") and a Seawater Outfall
("SWO") system.
9. Residue and Brine
Disposal
The Kola Project's process residue
is combined into a single waste stream composed of the NaCl (the
brine from product and salt de-brining - bulk of the effluent) and
the residue stream which originates from the insoluble de-brining
circuit within the Process Plant. The residue is collected in
onshore dissolution/dilution tanks and then discharged at sea via
the SWO pipe and diffuser. The discharge stream's dispersion
characteristics comply with the applicable environmental
criteria.
Ecotoxicological test work of the
expected discharge confirms that the discharge at sea of the
combined salt and insoluble tails stream does not place undue
stress on the marine environment.
No onshore tails storage facility is
therefore required for the Kola Project.
10. General Infrastructure
There have been no material changes
to the mining, processing, export and marine facility locations
since the Optimisation Study in 2022.
a. Mine Site -
Infrastructure
The Mine Site is located near the
village of Koutou and the current KP2 Exploration Camp. It is
24 km north and inland of the Project
Process Plant Site.
The sites can be accessed from
Pointe Noire through the existing National Road (Route Nationale) RN5 which crossses
Madingo Kayes and then by driving into RN6 as from Kilounga
village.
The Mine Site surface facilities
and infrastructure provides access and support facilities for the
Underground Mining operations.
No permanent living accommodation
is planned at the Mine Site for the Operational phase of the
Project.
b. Process Plant Site
- Infrastructure
The Process Plant Site is located
11 km inland from the marine facilities, next to the village of
Tchizalamou, approximately 60 km northwest of Pointe Noire.
ROM ore is transferred
from the Mine Site via the Overland Long Conveyor ("OLC").
The Process Plant Site facilities
and infrastructure produces granular MoP, which is transferred to
the Marine Facilities for export. The main administration, control
and support functions (Maintenance, Storage, Logistics, Training,
etc.) are also located within the Process Plant Site.
c. Mining
Complex & Off-Site - Infrastructure
The operation of the Kola Project's Mine and
Process Plant sites are supported by ancillary sites (Accommodation
Camp and Solid Waste Management Centre) and interconnecting
infrastructures (Roads, Power, Water and Gas supply, and
Communications).
The permanent accommodation camp
will be located approximately 3 km from the Process Plant and will
accommodate up to 950 people.
d.
Power
Operational electrical power is
guaranteed from the RoC national grid. This would require a 57 km
long 220 kV transmission line to be built from the Mongo Kamba II
substation, situated north of Pointe Noire, to the Process Plant.
The power demand is estimated to be 25 MVA at the Mine Site and 50
MVA at the Process Plant.
To reduce the Kola Project's
environmental footprint, the Company initiated discussions with a
new local oil and gas producer in RoC. This potential new
supplier's project includes both gas and electricity. As a result
of preliminary negotiations, the Company received competitive
rates, which were used in the revised economics.
e. Natural
Gas
Initially, the natural gas needed
for product drying was to be supplied by a 73-kilometer pipeline
from the M'Boundi gas treatment plant. However, a recent marketing
decision by this potential supplier has reduced availability in the
country, as the supplier now plans to export at higher
prices.
In the above context, the new local
oil and gas producer (cited in the Power paragraph above) stepped
in to propose gas from the oilfield they are developing. This
potential supplier plans to start production before Kola
does.
f.
Water
Raw water
will be supplied from wells located at the Mine Site (2 wells), the process plant site (5 wells) and at the Accommodation Camp (4 wells).
11. Environmental and Social Impact
Assessment
The ESIA was prepared managed by SRK
Consulting (UK) Limited's environmental and social (E&S) team.
SRK partnered with "Cabinet Management & Etudes
Environnementales S.A.R.L." ("CM2E"), which acted as the
Congolese-registered consultancy.
The Kola ESIA, initially approved on
10 October 2013, was amended to reflect the design changes made to
the Kola Project as part of the DFS and has been amended to include
the service corridors for a gas pipeline and overhead power line.
The application and terms of reference for amending the ESIA were
approved on 12 April 2018 by the Minister of Tourism and
Environment.
The ESIA for the Kola Mining License
was approved on 31 March 2020 granting a 25-year
approval.
The change of location of the
process plant, accommodation camp and some other minor OLC track
changes which occurred prior to the 2022 Optimization Study require
an ESIA update which shall be effected in the first half of the
2025 calendar year.
There have also been conflicting
reports as to whether part of the transshipment route between the
proposed jetty and the offshore transshipment location being
converted into a marine reserve. If confirmed during the ESIA
update, this might require a small diversion of the route to be
taken by barges transporting the finished product to ocean-going
vessels.
The Company shall carry out their
construction operations In compliance with the environmental and
social management plan as part of the approved ESIA and will be
subject to Regulator's environmental management compliance
audits.
12. Potash Marketing
Kore's potash marketing strategy
recognises the supply opportunities arising from MoP market growth
in Brazil, the project's proximity to Brazil and African markets
and the cost competitiveness of the Kola Project. The DFS,
Optimisation Study and Optimised DFS demonstrate that the Kola
project can deliver MoP into Brazilian and ports on the west coast
of Africa at lower cost than all other international suppliers.
Figure 4 shows a comparison of delivered MoP costs to
Brazil.
Figure 4 - Brazil delivered MoP cost
comparison

Source: August 2024 Argus Media
Marketing Report. Kore Potash CFR Cost Brazil calculated per Table
8.
In August 2024, the Company
commissioned a MoP market study and specification marketing report
("Argus Media Marketing Report") from one of the leading global
consultancy firms, Argus Media Group. According to this report,
Kore Potash is ideally located for exports to Brazil from an inland
and seaborne freight perspective. The Argus Media Marketing Report
indicates that the Company has the shortest distance to the
Paranagua port in Brazil and that, in 2023, 59% of Brazil MoP
imports entered via three key ports: Santos, Paranagua and Rio
Grande. The total estimated approximate 4,600km transportation
distance from the Kola mine is the shortest distance among all key
exporting mines globally to Paranagua, Brazil. While Canpotex is
the largest exporter to Brazil in the year 2023 and K+S fifth
largest importer in 2023 via Vancouver, Canada, to Paranagua, port
total transportation distance is approximately 12,000km, which is
almost triple the distance from the Kola Project mine.
The design of the processing plant
allows Kore to produce red MoP granular for the Brazil
market.
Potash market research specialist
Argus Media provided the Company with historical and forecast pricing trends for the
MoP CFR Brazil benchmarks over the
period up to 2047 (see Figure 5 below).
The Argus Media Marketing Report's estimates are
provided in MoP CFR Brazil Real US$/t 2023 values for calendar
years 2024 to 2047. The Company considers that it is reasonable to
apply Argus Media's estimates over that period given Argus Media is
independent and reputable international market research group which
has deep knowledge of the current potash market and its trends.
After 2047, prices are indexed by the Company using a US$2/t
incremental annual increase to the 2047 price as in the Argus Media
Marketing Report. As a result, the estimated forecast average
granular MoP price is US$449/t (see Appendix A, section 12) for the
life of the mine operations (with the US$449/t being the simple
average of the forecast price in each year of production over the
23 years of scheduled production, where the forecast price in each
year to 2047 is that in the Argus Media Marketing Report and for
each year after 2047, is the forecast 2047 price with a US$2/t
incremental annual increase applied in each year, as discussed
above).
It should be noted that current red
granular MoP CFR Brazil prices are around c.US$300/t, which is less
than the average of the granular MoP prices used in the Optimised
DFS (being US$449/t). There is no guarantee that the forecast
annual granular MoP prices used in the Optimised DFS will be
realised and lower realised prices will adversely affect the
financial performance of the Kola Project as demonstrated in the
sensitivity analysis in section 14(b) below. The price at which
Kola Project NPV10% is greater than zero is flat
c.US$271/t MoP CFR for the life of the mine operations.
Please also refer to the Cautionary Statement on page 3 of this
announcement.
Figure 5 -
Historical and forecast MoP CFR Brazil Real US$/t 2023. Extract
from Argus Media Marketing Report

As stated in the Argus Media
Marketing Report MoP prices are currently reaching their lowest
levels over the past 5 years. Short-term pricing in the next 12
months is based on the current market developments, such as weather
events, planned or unplanned plant outages and market participant
sentiment. Argus Media sees limited upside in medium-term (5 - 7
years) as the market reaches floor around the year 2028 with the
ramp-up of BHP's Jansen project in Canada. The potash market is
facing transition to supply surplus with recovering Russian and
Belarusian and new capacity in Canada and Laos. Argus Media
believes that the long-term price of MoP is dictated by the
industry's Long-Run Marginal Cost ("LRMC") for adding new potash
supply.
Total LRMC is the sum
of:
·
Mine capital costs, adjusted for location and the
weighted average cost of capital, amortised over the mine's life
span;
·
Mine operating costs, including fuel, labour,
materials, sustaining capital and royalties; and
·
Value-in-use considerations, crediting or debiting
total cost to consider access to target markets.
The LRMC base year is then inflated
by Argus Media over the forecast period to provide their long-term
price forecast. Each LRMC element is inflated using the appropriate
inflator from Argus Media's forecasts of fuel, energy and macro
inflators. The LRMC is a long-term trend forecast, meaning Argus
Media expects short-term oscillations around the calculated LRMC,
driven by factors such as weather and supply disruptions that
cannot be predicted this far in advance. Russian MoP development is
no longer included in the LRMC set. As the war in Ukraine
continues, Argus Media assumes the impact on Russia as a
destination for investment will be more prolonged and this is
reflected in a higher-risk premium. Argus Media's view is that
incremental tonnage from Canada and Israel are expected to dictate
long-run LRMC.
13. Capital and Operating Costs
a. Capital
Cost
The pre-production capital cost for the Kola
Project is now estimated at US$2.07 billion (nominal basis), which
includes a fixed price EPC contract of US$1.929 billion and US$141
million owner's costs. The breakdown of the EPC capital cost is
presented in Table 7 below.
The EPC fixed price is of significant benefit
to the Company, as it minimises the risk of cost overruns. Of the
total Contract Price, approximately US$708.9 million is allocated
for building transportation links and utility pipelines, which will
make the Kola Project self-reliant without depending on state
infrastructure except for the RoC national grid. The Company
considers this to be a significant advantage compared to other
potash projects worldwide. To accelerate progress during the
financing process, Kore Potash and PowerChina have committed to an
Early Works Agreement ("EWA"), which forms part of the EPC and
is targeted to be completed by the end of June 2025.
The owner's costs during the 43-month
construction period are projected to be approximately US$141
million. The EPC also includes provisions for penalties in the
event of delayed completion and non-compliance to performance
metrics.
Table 7 - Breakdown of Contract Price
Description
|
Amount (US$ million)
|
Underground Works (shafts and mine face
preparation)
|
319.7
|
Processing plant and auxiliary
facilities
|
609.6
|
Surface over land belt conveyor transportation
(OLC)*
|
229.3
|
Marine Works*
|
223.1
|
Roads*
|
111.3
|
Utilities (electricity overhead line & gas
pipeline) *
|
145.2
|
Administration facilities
|
58.9
|
General items
|
231.9
|
Total
|
1,929.0
|
* Total US$708.9 million for
transportation and related utilities.
Sustaining Capital Costs of US$924 million
have been included in the financial analysis, which is equivalent
to US$13.06/t MoP and disclosed in Table 8 below.
Sustaining capital costs cover expenditures
required to ensure the operation can sustain the production at
nameplate capacity. These costs include overhaul parts and labour,
replacement of equipment, maintenance of infrastructures (road,
jetty etc.), shut down costs, additional continuous miner and
additional underground conveyor costs, and the inspection and
maintenance of the trans-shipment vessels
b. Operating
Cost
The Operating Costs are expressed in US
dollars on a real basis and are based on average annual production
of 2.2 Mtpa of MoP over the life of mine. All costs have been
prepared on an owner operated basis and are shown in Table
8.
Table 8 -
Summary of Operating Costs
Cost
Category
|
Real costs
|
(US$/t MOP)
|
Opex
|
|
Mining Cost
|
25.17
|
Process Cost
|
29.08
|
Other Cost
|
20.69
|
Mine Gate
Operating Costs
|
74.94
|
Sustaining Capex
|
13.06
|
Product Realisation Charges and
Allowances
|
4.08
|
Royalties
|
11.74
|
Ex Works
Cost
|
103.81
|
Logistics to FOB point
|
5.81
|
Ocean Shipping
|
18.58
|
CFR Cost
(Landed in Brazil)
|
128.19
|
14. Economic Evaluation
a. Summary
Economics
The economic evaluation delivers a
post-tax NPV10% (real 2024) of
US$1.7 billion and a real ungeared IRR of 18% on a 90% attributable
basis. The evaluation is based on a forecast average MoP granular
price of US$449/t MoP CFR Brazil (real 2024) as outlined in section
12 above.
The key assumptions underpinning the economic
evaluation are as follows:
· Construction
start date: 1 January 2026.
· 23-year project
life from first production based on depletion of Ore
Reserves.
· 2.2 Mtpa average
production of MoP.
· Granulated MoP
represents 100 % of total MOP production and sales.
· All cashflows are
on a real 2024 basis
· NPVs are ungeared
and calculated after-tax applying a real discount rate of
10%.
· NPVs are
calculated at a base date of 1 January 2026 prior to the potential
dates for commencement of project construction
· Fiscal regime
assumptions are aligned with the recently finalised Mining
Convention:
o
Corporate tax of 15% of taxable profit with concessions for
the first 10 years of production (0% for the first 5 years and 7.5%
for years 6 - 10).
o Mining
royalty of 3% of the Ex-Mine Market Value (defined as the value of
the Product (determined by the export market price obtained for the
Product when sold) less the cost of all Mining and Processing
Operations, all costs of Transport (including any demurrage), and
all insurance costs).
o
Exemption from withholding taxes during the term of the
Mining Convention.
o
Exemption from VAT and import duty during construction;
and
o Congo
Government receives 10% of the shares in KPM which owns the Kola
Project.
The forecast project cash flow on a 90%
attributable basis for 23 years of production is illustrated in
Figure 6.
Figure 6 -
Project Cash Flow Forecast (real 2024) on a 90% Attributable
Basis

b. Sensitivity
Analysis
Kola Project returns have been
calculated on a real 10% post-tax unleveraged basis with the key
financial results and assumptions provided in Table 1. Figure 7
below shows the sensitivity to the four variables that have the
most impact on the real post-tax NPV10% and 90%
attributable basis (reflecting Kore's future holding of 90% and the
RoC government 10%) of the project, in descending order of most
sensitive to least sensitive. No capital cost sensitivities were
included as the EPC is a fixed price contract. The financial
outcomes of the project are most sensitive to changes in revenue
and, therefore, future MoP prices as well as KCl recovery in the
process plant.
Figure 7 -
NPV real 10% post-tax US$'000 movement
sensitivities*.

* KCl recovery sensitivities are in
incremental steps of 5%, 10% and 15% increases or decreases
relative to the base of 89.9%; increases are: +5% = 94.9%, +10% =
99.9%, +15% = 100% maximum. All other sensitives are % changes on
the base number.
15. Project Funding
As announced on 6 April 2021, a non-binding
memorandum of understanding was signed with Summit to arrange the
full financing required for the construction of the Kola Project
("Summit MOU").
In line with this memorandum of understanding,
following signing the EPC, Summit is expected to deliver a
non-binding financing term sheet within three months. This term
sheet will be subject to the completion of detailed and definitive
legal documentation.
The Company confirms its confidence in the
Summit Consortium as a financier for the construction of the Kola
Project. This confidence is based on the Company having worked with
the Summit Consortium for the past 10 years and their track record
in assisting with financing for Kore Potash including sourcing the
approximately US$40 million equity investment provided by the Oman
Investment Authority ("OIA") and Sociedad Quimica
y Minera de Chile S.A. ("SQM") in 2016. OIA and SQM
are among top three largest shareholders of the Company who
together hold 27.58% in the issued share capital of the
Company.
The material terms of the Summit MOU were set
out in the 6 April 2021 announcement and are reaffirmed as
follows:
·
The Summit MOU outlines a roadmap to optimise the capital
design to fully finance and construct Kola via a mix of debt and
royalty financing.
·
Under the proposed financing arrangements, the RoC Government
will retain their 10% shareholding in Kola.
·
Under the Summit's proposed financing structure, the Company
will not contribute to the capital needed to build the Kola Project
and will retain a 90% equity interest in Kola.
The Company retains the right not to accept
any finance proposal presented by Summit and there is no guarantee
that any proposal or legally binding agreement will be forthcoming.
The Company provides no assurance to shareholders that the
Summit Consortium will provide the financing required on terms
which are acceptable to the Company. If the Summit Consortium does
not provide an acceptable financing package leading to binding
legal documents, the Company will need to explore other debt,
equity and structured finance alternatives having regard to then
prevailing capital market conditions.
The Company expects any financing provided by
the Summit Consortium to be subject to the Summit Consortium being
granted full security over the Kola Project, however (as noted
above) the full terms of any financing proposal from the Summit
Consortium (including any security package) will be subject to
further discussions.
As previously announced on 30 January 2025 the
Summit Consortium was expected to deliver this financial proposal
by the end of February 2025. Due to delay in publication of the
Kola Project Optimised DFS update the new expected delivery date of
the financial proposal is now before the end of March
2025.
The Company confirms the Summit Consortium is
not a related party of the Company.
Further details about the financing
arrangements will be notified to the market in accordance with the
Company's continuous disclosure obligations
Appendix B: Summary of Information required under ASX
Listing Rule 5.9.1 (Ore Reserves), Listing Rule 5.16.1 (production
target) and Listing Rule 5.17.1 (forecast financial information
derived from a production target).
Pursuant to ASX Listing Rules 5.9.1,
5.16.1 and 5.17.1, and in addition to the information contained in
the body of this release, the Company provides the following
summary information.
Kola
Project Ore Reserves and related production target and forecast
financial information derived from the production
target
Summary of Material Assumptions
Material assumptions relating to the
Kola Project are summarised below:
· Production life - LoM of 23 years at an average annual
production of 2.2 Mtpa MoP production. The production life fully
depletes Ore Reserves and incorporates a portion of Inferred
Mineral Resource into the production target.
· Product pricing - Potash market
research specialist Argus Media provided the Company with
historical and forecast pricing trends for the MoP CFR Brazil
benchmarks over the period up to 2047 (see Figure 5 above). Kola's
proposed mine life covers the period from 2029 through to 2052 (23
years). The Argus Media Marketing Report's estimates are provided
in MoP CFR Brazil Real US$/t 2023 values for calendar years 2024 to
2047. After 2047, prices are indexed by the Company using a US$2/t
incremental annual increase to the 2047 price as in the Argus Media
Marketing Report. As a result, the estimated forecast average red
granular MoP price is US$449/t for the life of the mine
operations. For more details on product
pricing refer to Section 12.
· MoP
Product - The process design is based on a single product type, Red
Granular MOP. (The MoP produced will comprise at least 95.3% KCl,
with a maximum of 0.2% Mg and 0.3% Insolubles).
· Project duration - A project execution duration of 43 months
was specified in the EPC contract.
· Project Capital - The total nominal Project Capital of US$2.07
billion includes both EPC costs and owner's cost.
· Working capital assumptions - Working capital based on 30 days
Debtors and Creditors, 60 days Stores.
· Operating cost - mine gate operating cost of US$74.94/t and
CFR cost of US$128.19/t were reported in the Kola Project Optimised DFS update.
· Shipping costs - LoM Shipping costs (trans-shipment and sea
freight) of US$24.38 /MoP t were based on updated ocean freight
quotations received in 2024.
· Fiscal
parameters - The mining convention between the Company and the
Republic of Congo specifies the fiscal parameters summarised
below:
o Company tax rate (15%),
o Initial tax rates (5 years at 0% + 5 years at 7.5%)
o Royalties (3% of revenue) (Mining Convention)
o Government free carry (10%) (Mining Convention)
o Other minor duties and taxes (Mining Convention)
Criteria for Mineral Resource and Ore Reserve
Classification
The criteria for Mineral Resource
and Ore Reserve Classification remain unchanged from the
DFS.
The Ore Reserve estimate is based on
the Kola Sylvinite Indicated and Measured Mineral Resources
reported by Met-Chem DRA in accordance with the JORC Code (2012
edition) and confirmed by the Company on 27 Feb 2025.
Drill-hole and seismic data were
relied upon in the geological modelling and grade estimation.
Across the deposit the reliability of the geological and grade data
is high. Grade variation is small within each domain reflecting the
continuity of the depositional environment and 'all or nothing'
style of Sylvinite formation.
Drill hole data spacing determines
confidence in the interpretation of the seam continuity and
therefore confidence and classification; the further away from
seismic and drill-hole data the lower the confidence in the Mineral
Resource classification. In the assigning confidence category, all
relevant factors were considered, and the final assignment reflects
the Competent Person's view of the deposit.
Table B1:
Summary of Criteria used for the Classification of the Kola Mineral
Resource
|
Drill-hole required
|
Seismic data required
|
Classification extent
|
Measured
|
Average of 1 km spacing
|
Within area of close spaced 2010/2011 seismic
data (100 - 200 m spacing)
|
Not beyond the seismic requirement
|
Indicated
|
1-1.5 km spacing
|
1 to 2.5 km spaced 2010/2011 seismic data
and 1 to 2 km spaced oil
industry seismic data
|
Maximum of 1.5 km beyond the seismic data
requirement if sufficient drill-hole support
|
Inferred
|
Few holes, none more than 2 km from
another
|
1-3 km spaced oil industry seismic
data
|
Seismic data required and maximum of 3.5 km
from drill-holes
|
The Measured and Indicated Mineral
Resources for sylvinite are hosted by 3 layers (or 'seams') which
are from uppermost; the Hanging Wall Seam (HWS), the Upper Seam
(US) and the Lower Seam (LS), each separated by rock-salt (a
rock-type typically comprised of >95% halite).
Magnesium and insoluble content are
considered deleterious but are present in only very small amounts
in the ore (average of 0.07% and 0.14%respectively).
The Mineral Resource Estimate was
delivered to the Ore Reserve consultants in the form of a standard
block model, blocks having dimensions 250 x 250 x 1 m, each block
having a KCl grade, a density, and magnesium and insoluble
content.
The Mineral Resources are inclusive
of the Ore Reserves i.e. the Ore Reserves are the mineable part of
the Mineral Resources after the application of technical, economic
and other modifying factors.
Areas of potential structural
disturbance, referred to as geological anomalies were excluded from
the Measured and Indicated Mineral Resource. They were identified
from seismic data as is standard in potash mining districts
elsewhere.
A 10% CoG was used in the Mineral
Resource Estimate.
Mining Method and assumptions
The mining method and assumptions
remain unchanged from the DFS.
Mining factors and assumptions have
been derived from the historical information available for mature
potash mines, and the current best mining practices. The Kola
orebody will be mined using conventional underground ("UG") mining method consisting of room
and pillar in a 'chevron' (or herringbone) pattern, with Continuous
Miners ("CM") mining
machines of the drum-cutting type.
Most of the mining will be on one
level only where only the US will be extracted. In some areas, both
the US and the LS will be mined, in which case the LS will only be
mined after the US. In other areas only the HWS will be
mined.
In determining the Ore Reserves, a
minimum mining height of 2.5 m was selected based on capability of
the selected CM which is also capable of mining up to 6 m.
Areas of the Mineral Resource with a seam height of less than 2.5 m
were excluded from the Ore Reserves.
The mine design is typical of potash
mines, having 4 entries for accessing panels. Each drive will
typically be 8 m wide and 3 m to 6 m high depending on the seam
height. The typical configuration for the chevron pattern is an
angle of 65 degrees from the middle entry, and length of 150 m
approximately.
The Mine design relies on
geotechnical modelling, carried out in FLAC 3D software. The
modelling was based on geotechnical test-work carried out on
representative core samples from the sylvinite seams and host rocks
(rock-salt and lesser carnallitite). The geotechnical modelling
established that the mine design is stable over the LoM and
includes the following geotechnical parameters:
· Where
both the US and LS seams are to be mined, the support interval
between the US and LS must be at least 3 m thick.
· An 8 m
wide pillar between two consecutive production rooms (of 8 m
each).
· A 50 m
wide pillar between two production panels. Similarly, a 50 m wide
pillar will be left in place between the side of the production
panel and the main haulage access drift.
· The
interval of rock-salt between the mine openings and the floor of
the overlying anhydrite member is referred to as the 'salt back'.
This is typically over 30 m but is less in some areas. The DFS
design allows that it may be a minimum of 15 m unless the Anhydrite
Member is well developed where it may be 10 m. This is based on the
results of the geotechnical model.
· A
stand-off distance of 20 m radius from the exploration
holes.
· A
stand-off distance of 30 m radius from class 2 geological anomalies
and 60 m radius from class 3 geological anomalies.
· A
pillar of 300 m in radius around the exhaust and intake
shafts.
Based on the selected CMs, it is
anticipated that a good cutting selectivity would be achieved, and
that a maximum of 0.2 m of dilution material above and/or below the
potash seam is likely. Carnallitite is present in the floor of the
seam in some areas. The roof is always of rock-salt.
On average, the dilution material is
equivalent to approximately 10% of the tonnage of the Ore Reserves.
Dilution material was assigned a grade of 3% KCl if rock-salt and
0% KCl if Carnallitite.
Based on the configuration of the
proposed mining layout, and the anticipated fleet of mining
equipment, it is assumed that the mining recovery in the different
extraction chambers will be 90% on average (i.e. mining losses will
be 10%). This considers the mining action which will lead to some
losses such as material being excavated and left in the production
chamber, or mineralized material left in the floor or roof,
etc.
The Global extraction ratio is 30%
(25% in the LS, 33% in the US and 28% in the HWS). This is after
the removal from Ore Reserves of all pillars (pillars around the
geological anomalies, the barrier pillars, the shaft pillar, the
pillars between chevrons and main access drifts), the stand-off
distance around boreholes, mining losses and the exclusion of
sylvinite <2.5 m thick.
Two vertical shafts, each of 8 m
internal diameter, will be sunk at a central location in the Ore
Reserves, to provide access to the underground. The intake shaft
will be equipped with a hoist and cage system for transportation of
persons and material, while the exhaust shaft will be equipped with
a vertical conveyor system to convey the mined-out ore to the
surface. Both shafts are approximately 270 m deep.
Ore haulage from the CMs to the
feeder breaker apron feeder will be done using electrically-powered
Shuttle Cars.
Underground conveyor belts will be
used for ore transportation in all the areas of the mine. The belts
are distributed in the mains and submains and ultimately in the
working panels near the CM working face. The ore will be placed on
the belts from the feeder breakers that were fed by the shuttle
cars.
The belt conveyors will carry the
ore loaded by the feeder breakers to the ore bins. Then the ore is
conveyed from the ore bins to the Pocket Lift system located in the
exhaust shaft.
Processing Method and Assumptions
The changes to the processing method
and assumptions arising from the Optimisation Study are as
follows.
· The
product will be granular MoP K60, comprising at least 95.3% KCl.
The Optimisation Study design allows for the production of a single
product, red granular MOP.
· The
process flow sheets were optimised to produce a maximum of 2.2 Mtpa
of MoP, at 95.3% KCl purity, with a minimum KCl recovery of 89.9%
of the KCl content in the ROM fed to the Process Plant.
· Eight
key areas of process design were changed in the Optimisation
Study
o The
crushing circuit was changed from 3 stage crushing to 2 stage
crushing
o The
mixing tanks post crushing were replaced with a combination of
screens and tanks
o The
scrubbing capacity has been reduced
o The
thickening capacity has been increased
o Column cells have been replaced with floatation
cells
o Re-grind flows have been re-routed
o Tailings centrifuges has been replaced with a belt
filters
o Compaction circuit has been simplified
A conventional flotation process
will be utilised for potash concentration. This method is well
established and is the most widely used method in the potash
industry.
The metallurgical test work
campaigns were based on representative core samples of the three
seams, collected from the exploration drill hole cores. They
comprised US (114.5 kg), LS (102.0 kg) and HWS (10.3 kg). All test
work was carried out at the Saskatchewan Research Council
("SRC") laboratory in
Saskatoon, Canada.
Two metallurgical test work
campaigns were conducted during the DFS in 2017 and 2018. The main
philosophy of the first DFS test work campaign was to prepare
representative test feedstocks for each seam, confirm KCl
liberation, characterize the feedstock, perform flotation tests,
optimize the operating conditions, optimize reagent consumption for
optimum KCl recovery and grade performance, perform a sensitivity
test on flotation.
The objective of the second test
work campaign was to optimize the flotation process and improve the
plant recovery from the initial flow sheet. The results of this
second test work campaign demonstrated that the new flotation
process performed above the project performance minimum
target.
Magnesium and insoluble material are
considered deleterious. The extremely low content of these
materials in the ore mean that their removal is relatively
straightforward. Insoluble material is removed by attrition
scrubbing and magnesium removed by brine purge.
Cut-off Grades
The cut off grades remain consistent
with the original DFS Ore Reserves.
A CoG of 10% KCl has been calculated
within the process to state Ore Reserves. The CoG calculation
included all operating costs associated with the extraction,
processing and marketing of ore material. The cut-offs are based on
a MoP price of US$250 per tonne of MoP. Inputs to the calculation
of CoG included:
o Mining costs
o Metallurgical recoveries
o Processing costs
o Shipping costs
o General and administrative costs
All sylvinite of the Measured and
Indicated Resource is above 9.9% KCl (the Ore Reserve calculated
CoG), therefore all the Measured and Indicated Sylvinite Resources
have been considered for the Ore Reserve Estimate by application of
the other modifying factors.
The uniformly very low content of
deleterious elements (magnesium and insoluble material) meant that
these did not require consideration in the CoG
determination.
Cost
Estimation Methodology
Capital Cost:
· The
pre-production nominal capital cost for the Kola Project is now
estimated at US$2.07 billion, which includes a fixed price EPC
contract of US$1.929 billion and US$141 million owner's costs.
Operating Cost:
· Operating Cost covering the Life of Mine (23 years) was
estimated in US dollars and reported in the Kola DFS in 2019. They
include costs for Electric power, Fuel, Gas, Labour, Maintenance
parts, Operating Consumables, General and Administration costs and
Contract for Employee Facilities.
· These
2019 Operating Costs were all revised to reflect current
conditions, as follows:
o Exchange rates (vs US$) for Euro, British Pound, Canadian
Dollar, South African Rand, and Congolese Franc (Central African
Franc) were updated;
o Production split was updated to 100% red granular
MOP;
o Plant KCl recovery was reduced from 91.9% to 89.9%;
o Plant operating hours were updated according to PC's
assumption of 7,920 h/y;
o Electricity costs were updated according to current budgetary
pricing;
o Natural gas costs were updated according to current budgetary
pricing;
o Labour costs were escalated a flat 10%, in consultation with
third-party labour experts;
o All
other operating costs were escalated a flat 25% to simulate US
CPI.
· Transshipment costs were supplied by an experienced marine
broker.
· Ocean
Freight Transportation estimate produced were based on work done by
the marine brokers.
· Mine
Closure cost is estimated in accordance with the Conceptual
Rehabilitation and Closure Plan developed by SRK Consulting during
the DFS, assuming a Mine Closure duration of 24 months (2
years).
· For
the purpose of Operating Cost and Sustaining Capital, the
quantities of equipment, materials and works were directly assessed
from the Material Take-off prepared within the framework of the
Kola DFS.
· State
mineral royalties of 3% of Net Revenue were applied
· Measured Mineral Resources were used for the estimation of the
Proved Ore Reserves. Indicated Mineral Resources were used for the
estimation of Probable Ore Reserves.
· The
conversion of Measured and Indicated Mineral Resource to Proved and
Probable Ore Reserve reflects the Competent Person's view of the
deposit.
· 40.6%
of the Ore Reserves are classified in the Proved category and 59.4%
of the Ore Reserves are classified in the Probable
category
Material Modifying Factors
· Status of Environmental
Approvals
The Kola ESIA, initially approved
on 10 October 2013, was amended to reflect the design changes made
to the Kola Project as part of the DFS and has been amended to
include the service corridors for a gas pipeline and overhead power
line. The application and terms of reference for amending the ESIA
were approved on 12 April 2018 by the Minister of Tourism and
Environment.
The ESIA for the Kola Mining
License was approved on 31 March 2020 for 25 years.
The proposed new position of the
process plant resulting from the Optimisation Study creates a
requirement to issue an addendum to the ESIA. It is intended that
work on this addendum will commence in the second half of
2025.
· Status of Mining Tenements
and Approvals
Kore has a 97%-holding in SPSA, a
company registered in the RoC. The remaining 3% in SPSA is held by
"Les Establissements Congolais MGM" (RoC). SPSA in turn has a 100%
interest in its two ROC subsidiaries, Kola Potash Mining SA
("KPM") and Dougou Potash
Mining SA ("DPM").
The Mining Convention includes a requirement for 10% of
free-carry shares in KPM and DPM to be assigned to the Government
of the Congo. The Company is currently awaiting Government
instructions as to the share transfer process.
The Kola Deposit is within the Kola
Mining Lease which is 100% owned by KPM
o In
May 2008, a non-exclusive Prospecting Authorisation was granted to
Sintoukola Potash covering an area of 1,436.5 km2. On 13
August 2009, this was changed to a "Permis de Recherches"
(Exploration Permit) named 'Permis Sintoukola' under decree No.
2009-237 giving the Company exclusive rights to explore.
o On
27 November 2012, the first renewal of the permit was made, by
decree No. 2012-1193 and reduced in size to 1,408
km2.
o On
the 9 August 2013, a Mining Lease for Kola issued under decree No.
2013-312, totaling 204.52 km2 falling entirely within
the Exploration Permit.
· Déclaration d'Utilité
Publique or "DUP"
Exclusive land acquisition rights
have been granted to the Project company for plant development
through ministerial order gazetted on 30 August 2018 (the
"Déclaration d'Utilité
Publique" or "DUP")
valid for three years and renewable once for a two-year
period.
As a result of the optimization of
the processing plant and camp location, a new DUP process needs to
be initiated with the approval and support of the Government after
receipt and acceptance of the financing proposal from Summit. A
subcontractor with prior experience on the previous DUP is awaiting
the greenlight of Kore to start the work.
· Other Governmental
Factors
The Company entered into a mining
convention with RoC government on 8 June 2017 and it was gazetted
into law on 7 December 2018. The Mining Convention provides
certainty and enforceability of the key fiscal arrangements for the
development and operation of the Kola Project. This includes
clarifying import duty and VAT exemptions and agreed tax rates
during mine operations. The Mining Convention provides strengthened
legal protection of the Company's investments in the RoC through
the settlement of any disputes by international
arbitration.
Infrastructure Requirements for Selected Mining, Processing
and Product Transportation to Market
The project infrastructure is
comprised of the mine-site (shaft and offices), the process plant
24 km from the mine and a product and marine export facility at the
coast (at Tchiboula), the 34 km infrastructure corridor between
these (including the overland conveyor, service road and power
line), the gas line from M'boundi gas field, overhead line from the
MKII substation, the accommodation and administrative camp and the
transshipment facilities.
Changes to the infrastructure
requirements that arise from the Optimisation Study and Optimised
DFS, and are thus different from the DFS are summarised
below.
· The
process plant position has been moved 11 km inland which has
allowed optimisation of the foundation design, the resultant
infrastructure at the coast consists of the product storage
building and marine export facilities. The design of the barge
loading jetty has also been optimised.
· Road
access to the Kola Potash Project sites will be via the existing
Route Nationale 5 (RN5). Two external access roads will be built,
which are respectively connected from RN5 to the mining site and
from RN5 to the mineral processing site and living quarter, with a
length of 2.0 km and 4.3 km respectively. Two maintenance roads for
long-distance belt conveyors will be built. One of the roads for
RoM belt conveyor maintenance is about 24.0 km, connecting Koutou
camp and the mineral processing site. The other road is for MOP
belt conveyor maintenance,
· Raw
Water will be supplied from wells located at the Mine Site and at
the Accommodation Camp close to the Process Plant Site.
· The
Accommodation Camp has been sized for a capacity of 950 beds and
will be located about 2 km away from the Process Plant
· Electrical Power will be sourced from the ROC national grid. A
57 km long 220 kV transmission line will be built from the Mongo
Kamba II substation north of Pointe Noire to the Process Plant
Site. A second 34 km long 220 kV transmission line will be built
from the Process Plant Site to the Mine Site and the marine
facility at the coast.
· The
Natural Gas needed for product drying will be supplied by a local
Oil and Gas producer who has plans to build a gas treatment plant
some 35 km away from the Kore processing plant. The same company is
also planning to supply electricity to the Kola Project from the
same offtake point. This will be an interesting option to the Mongo
Kamba II substation as it has a lower environmental impact.
The infrastructure requirements that
have not been modified in the Optimisation Study or Optimised DFS,
and thus remain the same as the DFS are summarised
below.
· Ongoing operational labour will be a combination of permanent
employees, permanent contract services, and part-time contract
services for intermittent needs. The total requirement for
permanent employees is expected to be 731. Local labour
resources will be used for the majority of labour requirements,
while some selected positions are planned as expat
roles.
· The
Kola Potash Project intends to export up to 2.2 Mt MoP to world
markets each year. A transshipment solution has been developed,
whereby MoP for export is loaded at a dedicated jetty onto
self-propelled shuttle barges (two units), which will then travel
to OGVs anchored 11 nautical miles (20 km) offshore in a dedicated
transshipment area. The cargo will be transferred from the Barges
to the OGVs using a Floating Crane Transhipper Unit ("FCTU").