Scatec JV reaches financial close for 56 MW BESS in the Philippines and prepares for construction start
17 February 2025 - 10:17PM
UK Regulatory
Scatec JV reaches financial close for 56 MW BESS in the Philippines
and prepares for construction start
Oslo, 17 February 2025: Scatec ASA’s joint venture with Aboitiz
Power in the Philippines has reached financial close and prepares
for construction start of the 16 MW Magat (phase 2) and 40 MW Binga
battery energy storage systems (BESS).
The battery systems will be connected to the Magat and Binga
hydro power plants, generating revenues from the highly attractive
ancillary services reserves market. The new capacity is building on
the success of the existing 24 MW BESS connected to the Magat power
plant, which has been generating solid ancillary services revenues
since start of operation in 2024.
Batteries are optimal for ancillary services due to their fast
response time to tackle fluctuations in grid frequency, flexibility
to perform multiple grid services, and cost competitiveness.
Ancillary services will be increasingly important over time in the
Philippines due to higher penetration of renewables driven by the
government’s ambitious renewables targets.
“We are very excited to start construction of the new BESS
projects in the Philippines. With the new batteries we will more
than triple our storage capacity to 80 MW, increasing the value of
our hydro power plants and strengthening our position as a leading
provider of ancillary services in the country. Ancillary services
in the Philippines is a highly attractive source of revenues and we
will continue to expand our storage capacity taking an even larger
share of the market over time,” says CEO Terje Pilskog.
The projects are owned by Scatec’s 50/50 joint venture with
Aboitiz Power in the Philippines and will be financed through
project debt drawn under the existing debt facilities related to
the Magat and Binga hydro power plants.
For further information, please contact:
For analysts and investors:
Andreas Austrell, VP IR
andreas.austrell@scatec.com
+47 974 38 686
For media:
Meera Bhatia, SVP External Affairs & Communications
meera.bhatia@scatec.com
+47 468 44 959
About Scatec
Scatec is a leading renewable energy solutions provider,
accelerating access to reliable and affordable clean energy
emerging markets. As a long-term player, we develop, build, own,
and operate renewable energy plants, with 5 GW in operation and
under construction across five continents today. We are committed
to growing our renewable energy capacity, delivered by our
passionate employees and partners who are driven by a common vision
of ‘Improving our Future’. Scatec is headquartered in Oslo, Norway
and listed on the Oslo Stock Exchange under the ticker symbol
‘SCATC’. To learn more, visit www.scatec.com or connect with
us on LinkedIn.
This information is subject to the disclosure requirements
pursuant to Section 5-12 the Norwegian Securities Trading Act
Scatec ASA (TG:66T)
Historical Stock Chart
From Feb 2025 to Mar 2025
Scatec ASA (TG:66T)
Historical Stock Chart
From Mar 2024 to Mar 2025