Endeavour Silver Provides Terronera Progress Update
08 January 2025 - 10:50PM
Endeavour Silver Corp.
("Endeavour" or the
"Company") (NYSE: EXK; TSX: EDR) provides
an update on the progress at its Terronera project.
The Terronera project experienced delivery
delays during December of critical path structural steel components
required for the lower platform construction and tailing filter
area installations. This has adversely impacted overall project
productivity and expected commissioning timelines. In light of
these delays, management reduced the site workforce over the
holiday season from December 20, 2024 to January 6, 2025 as a cost
saving measure. The lower platform construction and filter area
installation is the critical path to wet commissioning, which
is now expected in early Q2 2025.
Following Mexico’s lifting of the transport
restrictions, critical steel deliveries and installation resumed
this week. The earthworks team has the tailings dam ready for use,
and the operational readiness team continues the dry commissioning
of the upper platform. Above ground ore stockpiles, including
crushed ore are nearing capacity, while the mine personnel will
continue stope preparation on multiple levels and advancing mine
development. Commissioning of the grinding circuit commenced with
SAG and ball mills being successfully tested for multiple hours at
full operating speed to check bearing temperatures, vibrations and
lubrication systems under no-load conditions.
Management will provide a Q4 construction update
similar to previous quarterly updates later this month, including a
photo gallery and updated site overhead costs to be incurred over
Q1 2025.
Don Gray, Chief Operating Officer commented,
“Unfortunately, the revised timing of structural steel deliveries
coincided with the holiday season transport restrictions, resulting
in supply-chain delivery interruptions and limited availability of
key support technicians. Once it was clear that site productivity
would be impacted, we felt it prudent to maintain a smaller
workforce and temporarily reduce manpower costs. This gave
our construction team an opportunity to re-charge for the
final effort in bringing Terronera to a
successful completion.”
About Endeavour Silver:
Endeavour is a mid-tier precious metals company committed to
sustainable and responsible mining practices. With operations in
Mexico and the development of the new cornerstone mine in Jalisco
State, the Company aims to contribute positively to the mining
industry and the communities in which it operates. In addition,
Endeavour has a portfolio of exploration projects in Mexico, Chile,
and the United States, which has helped it achieve its goal of
becoming a premier senior silver producer.
Contact InformationAllison Pettit, Director of
Investor RelationsTel: (604) 640 4804Email:
apettit@edrsilver.comWebsite: www.edrsilver.com
Cautionary Note Regarding
Forward-Looking Statements
This news release contains "forward-looking
statements" within the meaning of the United States Private
Securities Litigation Reform Act of 1995 and "forward-looking
information" within applicable Canadian securities legislation.
Such forward-looking statements and information herein include but
are not limited to statements regarding the development of the
Terronera project, the anticipated timing of wet commissioning at
the Terronera project, the anticipated timing of the Company’s
quarterly construction updates, the Terronera project's forecasted
operations, costs and expenditures, and the timing and results of
various related activities. The Company does not intend to and does
not assume any obligation to update forward-looking statements or
information other than as required by applicable law.
Forward-looking statements or information
involve known and unknown risks, uncertainties, and other factors
that may cause Endeavor's actual results, level of activity,
production levels, performance, or achievements, and its operations
to be materially different from those expressed or implied by such
statements. Such factors include but are not limited changes in
production and costs guidance; the ongoing effects of inflation and
supply chain issues on mine economics; national and local
governments, legislation, taxation, controls, regulations and
political or economic developments in Canada, Chile, the USA and
Mexico; financial risks due to precious metals prices; operating or
technical difficulties in mineral exploration, development and
mining activities; risks and hazards of mineral exploration,
development and mining; the speculative nature of mineral
exploration and development; risks in obtaining necessary licenses
and permits; satisfaction of conditions precedent to drawdown under
the project loan debt facility; the ongoing effects of inflation
and supply chain issues on the Terronera project economics;
fluctuations in the prices of silver and gold, fluctuations in the
currency markets (particularly the Mexican peso, Chilean peso,
Canadian dollar and US dollar); and challenges to the Company's
title to properties; as well as those factors described in the
section "risk factors" contained in the Company's most recent form
40F/Annual Information Form filed with the SEC and Canadian
securities regulatory authorities.
Forward-looking statements are based on
assumptions management believes to be reasonable, including but not
limited to the continued operation of the Company's mining
operations, no material adverse change in the market price of
commodities forecasted Terronera mine economics as of 2024, mining
operations will operate, and the mining products will be completed
under management's expectations and achieve their stated production
outcomes, and such other assumptions and factors as set out herein.
Although the Company has attempted to identify important factors
that could cause actual results to differ materially from those
contained in forward-looking statements or information, other
factors may cause results to be materially different from those
anticipated, described, estimated, assessed, or intended. There can
be no assurance that any forward-looking statements or information
will be accurate, as actual results and future events could differ
materially from those anticipated in such statements or
information. Accordingly, readers should not place undue reliance
on forward-looking statements or information.
Endeavour Silver (TSX:EDR)
Historical Stock Chart
From Dec 2024 to Jan 2025
Endeavour Silver (TSX:EDR)
Historical Stock Chart
From Jan 2024 to Jan 2025