Alba Mineral Resources
plc
("Alba"
or the "Company")
HALF-YEARLY
REPORT FOR THE SIX MONTHS ENDED 31 MAY 2024;
FIRST BLAST SUCCESSFULLY
COMPLETED AT CLOGAU GOLD MINE
The Board of Directors of Alba
Mineral Resources plc (the "Company" or "Alba") is pleased to
report the Group's interim results for the six months ended 31 May
2024. The Company is also delighted to report on the successful
completion of the first blast at the Company's priority gold target
at the Clogau Gold Mine in north Wales ("Clogau" or the
"Mine").
COMPLETION OF FIRST BLAST AT CLOGAU
The Company is delighted to confirm
the successful completion of the first blast at the Llechfraith
Target at Clogau on 28 August 2024.
The first blast took place at No.
4.5 Level. Eight blast holes were drilled. All
detonated successfully, producing several tonnes of broken vein
ore. This material will be removed to surface in due course
and processed.
The next sequence of blasts is
expected to proceed at No.5 Level. While the Company will provide
periodic updates on the progress of operations on site, it will not
be providing reports on each individual blast.
George Frangeskides, Alba's
Executive Chairman, commented: "We are delighted to have successfully and
safely completed the first blast at our main gold target at Clogau,
the Llechfraith Target. To our knowledge, this is the first blast
to have taken place at Clogau since the 1980s and is a testament to
the skill and dedication of our mining personnel onsite. We
look forward now to continuing blasting operations on No.5
Level."
Figure 1: Historical section showing area, circled and
coloured pink, where first blast took place on 4.5 Level (labelled
"5 metre Level" on the drawing).
Figure 2: left, Mine & Operations Manager Kobus Byleveldt
inspecting quartz vein on No. 4.5 Level; right, broken quartz vein
on No. 4.5 Level post first blast.
HALF-YEARLY REPORT FOR THE SIX MONTHS ENDED 31 MAY
2024
CHAIRMAN'S STATEMENT
I am pleased to present shareholders
with a review of our activities in the six months to 31 May
2024.
1. REVIEW OF
ACTIVITIES
1.1 WELSH GOLD
PROJECTS
(Clogau-St David's, Gwynfynydd and Dolgellau Gold Exploration
Project) (100%)
In December 2023, revised discharge
and abstraction permits were granted to Alba, allowing the Company
to dewater the Lower Llechfraith workings at the Clogau-St David's
Gold Mine ("Clogau" or the "Mine") at a rate of up to 250 cubic
metres per day, a significant increase to the previous maximum of
up to 100 cubic metres per day. Consequently, the Company was
able to complete the dewatering of the Lower Llechfraith workings
down to No.4 Level in January 2024.
Simultaneously with the dewatering
exercise, the Company's specialist geotechnical contractors
completed the installation of new platforms and ladderways to allow
access to No.4 Level.
In February 2024, Alba announced
that it had taken more than 40 samples from No.4 Level at the
Llechfraith Target. These samples were processed at the Company's
onsite pilot processing plant and the resulting concentrates were
then assayed for their gold content at an independent laboratory.
As announced during March 2024, composites of the concentrates
returned exceptional gold grades:
- Composite 1: 3.1
grams of gold were recovered from 49.2 kg of sample (dry weight),
equating to a back-calculated head grade of 89.15 g/t or 2.87 troy
ounces per tonne (oz/t).
- Composite 2: 3.2
grams of gold were recovered from 34.4 kg of sample (dry weight),
equating to a back-calculated head grade of 111.63 g/t or 3.59
oz/t.
- Composite 3: 4.0
grams of gold were recovered from 36.9 kg of sample (dry weight),
equating to a back-calculated head grade of 133.73 g/t or 4.30
oz/t.
Also in February 2024:
- notification was
made under Permitted Development Rights in respect of the Company's
intention to proceed with the planned bulk sampling of the
Llechfraith Target, in accordance with the previously completed
Habitat Regulations Assessment ("HRA") and existing European
Protected Species Licence ("EPSL") permissions;
- the airborne
geophysical survey undertaken over Alba's key regional gold targets
across the Dolgellau Gold Belt ("DGB") was completed;
and
- following a
review of the plan for future exploitation of the historic waste
tip at Clogau ("Waste Tip"), the Company announced that it had
submitted a notification under Permitted Development Rights to
carry out a trenching programme prior to submitting a planning
application for the Waste Tip.
In April 2024, the Company announced
that three new gold targets had been identified from the review and
interpretation of the first part of the magnetic data generated
during Alba's airborne geophysical survey over the DGB. Two of the
targets are located within the envelope of the Clogau Mine and
represent the potential definition of new drill targets within the
Mine. The third target has been identified on a fault that extends
4 km northeasterly within the DGB and thus falls within the
Company's 100% owned Dolgellau Gold Exploration Project.
In May 2024, Alba announced that it
had excavated nearly 33 tonnes of <20mm material (or "fines")
from the Waste Tip. Four concentrates were produced from
composite samples of <20mm material taken from each trench,
three of which concentrates returned back-calculated head grades of
6.0 g/t, 17.22 g/t and 5.33 g/t respectively.
In July 2024 it was announced that
all fines from Trenches 1 and 3 at the Waste Tip had been processed
for their gold content. 16.4 grams of gold were produced from
Trench 1 and 14.2 grams from Trench 3, equating to back-calculated
head grade for the -20mm fines material of 3.83 g/t from Trench 1
and 2.68 g/t from Trench 3 (overall average 3.19 g/t).
At the end of the reporting period,
the Company appointed Kobus Byleveldt as Mine & Operations
Manager at Clogau. Mr Byleveldt has more than 26 years of mining
and management experience within the gold mining sector in South
Africa and Scotland, including in mine planning, construction and
development. His most recent role was as Mine Manager (for
approximately 2.5 years) at the Cononish Mine in Scotland, where he
also acted as Senior Production Supervisor and Process Plant
Manager.
Ongoing underground works in July
2024 have revealed significant completed historic development
between No. 4 and No.5 Levels, around 20m in length, which provides
further opportunities for sampling and access to the
payshoot. Further, the dewatering of No.5 Level has unearthed
substantial amounts of ore and tailings from previous mining which
is being removed to surface and will be assayed for its gold
content.
Since the end of the reporting
period, work has focused on preparing the Llechfraith Target for
blasting, involving:
- 100m of cabling
being installed and a new pump lowered to No.4 Level to enable
completion of the dewatering of No.5 Level;
- Alba's
underground works contractors completing a further round of safety
and access works on No.4 Level and, post dewatering, on No.5 Level,
to install ladderways to enable the team to access No.5 Level for
blasting;
- ventilation, in
the form of fans and vent ducting, being installed on Levels 4 and
5 for the removal of blasting
fumes;
- compressed air
being extended to No.4 Level by the installation of about 40m of
pipes linking to the existing air pipes located on No. 2 Level, and
water pipes being extended down to No.4 Level; and
- a large tonnage
capacity winch being installed at the top of the Llechfraith Shaft
with another one on No.4 Level, together with shaft doors and
signalling devices.
On 28 August 2024, the first blast
at the Llechfraith Target was successfully completed.
1.2 OTHER PROJECTS AND
INVESTMENTS
(a) Greenroc Strategic Materials Plc
("GreenRoc")
As at 31 May 2024, Alba owned 37.49%
of the issued share capital of GreenRoc (formerly called GreenRoc
Mining Plc).
Significant progress has been made
at GreenRoc during the reporting period:
• In April 2024,
GreenRoc's application for an enlargement of the licence MEL
2022-03 was approved by the Government of Greenland. GreenRoc now
holds all of the prospective ground in South Greenland with known
graphite mineralisation - several of which hold exceptionally high
grades similar to those of Amitsoq.
• GreenRoc was
invited to present at the Mineral Security Partnership ("MSP")
meeting on graphite held in Toronto in March 2024, as one out of
only three established global graphite companies and the only
graphite company in the northern hemisphere. The MSP is a
collaboration of 13 countries plus the EU and is designed to
catalyse public and private investment in responsible critical
minerals supply chains globally.
• In April 2024 a
Letter of Interest was issued by US EXIM Bank inviting GreenRoc to
apply for financing of up to US$3.5M towards the company's work
programme.
• Amitsoq uncoated
purified spherical graphite was analysed for its electrochemical
performance in a test battery cell at a specialised battery
research facility in Europe. The Amitsoq graphite anode performed
well against all studied parameters, was very stable and had no
signs of damage or loss of capacity after several cycles of both
short and intensive charging.
• In January 2024,
GreenRoc representatives visited key Chinese manufacturers of
graphite anode material processing equipment as part of the
Pre-Feasibility Study ("PFS") in respect of the Company's planned
graphite active anode material ("AAM") plant project ("AAM
Plant").
• The AAM Plant PFS
has been supported by a £250,000 grant from the UK's Automotive
Transformation Fund. Results of the AAM Plant PFS were published in
May and July 2024 and showed:
o Pre-Tax Net Present Value at 8% discount rate (NPV8) of
US$942M with Internal Rate of Return (IRR) of 35.4%.
o After-tax NPV8 of US$621M with IRR of 26.5%.
o Total gross revenue of US$6.5Bn over the 22-year period, with
total gross profit totalling US$3.1Bn.
o Years of operation set at 22 to match that planned for the
Amitsoq Graphite Mine.
o 4-year payback period on capital from start of
production.
o Initial capital cost (Capex) of US$340M inclusive of a 25%
contingency.
o Average operating cost (Opex) of US$1,872 per tonne of
CSPG.
o Average annual processing of 80,000t of graphite concentrate
at 95% graphitic carbon (C(g)) with production of 39,700t of active
anode material in the form of coated spherical purified graphite
(CSPG).
• Due to a change in
Greenlandic law which now allows for a faster application process
for an exploitation permit, GreenRoc expects to be in a position to
apply for an exploitation permit for licence MEL 2013-06 at Amitsoq
before the end of 2024.
In June 2024, Alba subscribed
for 3,888,890 shares in GreenRoc at 1.8
pence per share for a total subscription of £110,000. Alba's directors also separately subscribed for shares in
GreenRoc at the same price.
In August 2024, GreenRoc announced
that it had signed a Letter of Interest ("LOI") to secure an area
in southern Norway for its planned AAM Plant. It also confirmed
that it had applied for "Strategic Project" status under the EU's
Critical Raw Materials Act ("CRMA") and had submitted the Project
Description for the Amitsoq Graphite Mine to the Government of
Greenland as part of the path to achieving an Exploitation
Licence.
At the date of this RNS, Alba owns
34.72% of the issued share capital of GreenRoc.
(b) Horse Hill Developments
Ltd
Alba owns an 11.765% effective
interest in the Horse Hill Oil Project in the Weald Basin in
southern England ("Horse Hill"). In December 2023, Alba
received £102,000 from Horse Hill Developments Limited as a partial
repayment of shareholder loans.
In June 2024, UK Oil & Gas Plc
("UKOG"), the Operator of Horse Hill, noted the Supreme Court's
decision that in its 2019 grant of planning consent for the oil
production at Horse Hill, Surrey County Council ("SCC") failed to
request and consider in its assessment an estimate of the end-use
carbon combustion emissions of produced hydrocarbons. UKOG further
stated that it planned "to work closely with SCC to promptly
rectify the situation, either via an amendment to the original 2018
planning application's EIA or via a new retrospective planning
submission...". Alba awaits the advice of the Operator as to
the next steps and timetable for rectification of the relevant
planning consents.
(c) Projects under
Review
On 24 April 2024 Alba announced that
it had acquired an option to purchase a 50%
interest in a package of highly prospective lithium exploration
licences in the West Pilbara, Western Australia. In June, it
was announced that the option period had expired without the option
being exercised, but that discussions were ongoing with the
vendors. As at the date of this report, no discussions are
ongoing.
The Company continues to review
potential new projects and investments which it considers may add
significant value to Alba.
2.
CORPORATE
On 28 March 2024, Alba announced a
share placing raising £380,000 before costs.
Post period end, Alba announced a
placing and a Retail Offer, which was over-subscribed. Total funds
raised were £492,000 before costs.
Two directors subscribed for shares
in that placing as follows:
Director
|
Subscription (£)
|
Shares Allotted
|
George Frangeskides
|
£17,000
|
48,571,428
|
Michael Nott
|
£3,000
|
8,571,428
|
In December 2023 Alba announced the
cancellation of a numbers of warrants and options is issue, and the
grant of new options and warrants to directors and
employees.
3.
RESULTS
The Group made a loss of £639,000
after tax (May 2022: profit of £2,102,000 including an accounting
profit in relation to the de-consolidation of GreenRoc of
£2,672,000).
Operating losses were £489,000
compared with £459,000 in the comparative period. These include
£197,000 non-cash costs attributable to the grant of new warrants
and options in December 2023. Note that in the comparative period,
GreenRoc was consolidated for 3 months and therefore Alba reported
both companies' costs in the income statement for that
time.
The grant of new warrants and
options (as noted in 2. above) are valued with a Black-Scholes
calculation. The warrants that were cancelled at the same time led
to a release of historic costs booked when they were granted. This
release occurs in reserves rather than the income statement so does
not offset the non-cash cost in the income statement.
Net assets at 31 May 2024 are in
line with those at year end at £9.7 million. During the period,
£200,000 was spent on exploration activities, increasing the value
capitalised in Intangible Assets. Investments were reduced slightly
due to a repayment from Horse Hill and the allocation of a
proportionate share of the loss of GreenRoc for the
period.
Cash at the period end was £97,000.
As noted above, Alba has raised funding of £492,000, before costs,
since the reporting date.
4. OUTLOOK
I am pleased to be writing just
after our team has completed our first blast underground at the
Clogau Gold Mine. It has taken a huge amount of work, skill
and dedication from all the Alba team, as well as from our
fantastic group of technical consultants and contractors, to have
reached this historic milestone, to our knowledge the first blast
to have taken place at Clogau in around four
decades.
Most importantly, the start of
blasting signifies that we are now very much at the business end of
our operational activities at Clogau. This next phase of work
will go some way to determining the viability of commercial gold
operations based at the Lower Llechfraith workings, our priority
target within the existing envelope of the Mine.
On behalf of the entire Board, I
would like to take this opportunity to thank our shareholders for
all their support.
George Frangeskides
30 August 2024
Executive Chairman
This announcement contains inside
information for the purposes of the UK Market Abuse Regulation and
the Directors of the Company are responsible for the release of
this announcement.
Forward Looking
Statements
This announcement contains
forward-looking statements relating to expected or anticipated
future events and anticipated results that are forward-looking in
nature and, as a result, are subject to certain risks and
uncertainties, such as general economic, market and business
conditions, competition for qualified staff, the regulatory process
and actions, technical issues, new legislation, uncertainties
resulting from potential delays or changes in plans, uncertainties
resulting from working in a new political jurisdiction,
uncertainties regarding the results of exploration, uncertainties
regarding the timing and granting of prospecting rights,
uncertainties regarding the Company's ability to execute and
implement future plans, and the occurrence of unexpected events.
Actual results achieved may vary from the information provided
herein as a result of numerous known and unknown risks and
uncertainties and other factors.
For further information, please
visit www.albamineralresources.com
or contact:
Alba Mineral Resources
plc
George Frangeskides, Executive
Chairman
+44 20 3950 0725
SPARK Advisory Partners Limited
(Nomad)
Andrew
Emmott
+44 20 3368 3555
CMC Markets plc (Broker)
Thomas
Smith /
Douglas
Crippen
+44 20 7392 1494
capx@cmcmarkets.com
Alba's Projects and
Investments
Mining Projects Operated by
Alba
|
Location
|
Ownership
|
Clogau (gold)
|
Wales
|
100%
|
Dolgellau Gold Exploration
(gold)
|
Wales
|
100%
|
Gwynfynydd (gold)
|
Wales
|
100%
|
Investments Held by
Alba
|
Location
|
Ownership
|
GreenRoc Strategic Materials
Plc
(graphite - anode)
|
Greenland
|
34.72%
|
Horse Hill (oil)
|
England
|
11.765%
|
UNAUDITED
CONSOLIDATED INCOME STATEMENT
FOR THE SIX
MONTHS ENDED 31 MAY 2024
|
|
Unaudited
6 months
ended 31 May 2024
|
Unaudited
6 months
ended 31 May 2023
|
Audited
Year ended 30 Nov 2023
|
|
|
£'000
|
£'000
|
£'000
|
|
|
|
|
|
Other
income
|
|
33
|
-
|
55
|
Administrative expenses
|
|
(522)
|
(459)
|
(738)
|
Operating
(loss)/profit
|
|
(489)
|
(459)
|
(683)
|
|
|
|
|
|
Gain on
deemed disposal
|
|
-
|
2,672
|
1,475
|
Loss on
dilution of investment in associate
|
|
-
|
-
|
(325)
|
Share of
loss of associate
|
|
(150)
|
(110)
|
(661)
|
Finance
costs
|
|
-
|
(1)
|
(2)
|
(Loss)/profit before tax
|
|
(639)
|
2,102
|
(196)
|
|
|
|
|
|
Taxation
|
|
-
|
-
|
-
|
(Loss)/profit for the year
|
|
(639)
|
2,102
|
(196)
|
|
|
|
|
|
Attributable to:
|
|
|
|
|
Equity
holders of the parent
|
|
(639)
|
2,182
|
(116)
|
Non-controlling interests
|
|
-
|
(80)
|
(80)
|
|
|
(639)
|
2,102
|
(196)
|
|
|
|
|
|
Profit/(loss) per ordinary share
|
|
|
|
|
Basic
(pence)
Diluted
(pence)
|
|
(0.009)
(0.009)
|
0.030
0.028
|
(0.002)
(0.002)
|
UNAUDITED
CONSOLIDATED STATEMENT OF FINANCIAL POSITION
AS AT 31
MAY 2024
|
|
Unaudited
6 months
ended 31 May 2024
|
Unaudited
6 months
ended 31 May 2023
|
Audited
Year ended 30 Nov 2023
|
|
|
£'000
|
£'000
|
£'000
|
|
|
|
|
|
Non-current
assets
|
|
|
|
|
Property,
plant and equipment
|
|
162
|
144
|
168
|
Intangible
fixed assets
|
|
3,721
|
3,214
|
3,520
|
Investment
in associate
|
|
3,297
|
5,386
|
3,447
|
Investments
- Horse Hill Developments
|
|
2,497
|
2,600
|
2,600
|
Total
non-current assets
|
|
9,677
|
11,344
|
9,735
|
|
|
|
|
|
Current
assets
|
|
|
|
|
Trade and
other receivables
|
|
87
|
117
|
88
|
Cash and
cash equivalents
|
|
97
|
58
|
97
|
Total
current assets
|
|
184
|
175
|
185
|
|
|
|
|
|
Current
liabilities
|
|
|
|
|
Trade and
other payables
|
|
(245)
|
(257)
|
(220)
|
Financial
liabilities
|
|
-
|
-
|
-
|
Total
current liabilities
|
|
(245)
|
(257)
|
(220)
|
|
|
|
|
|
Net current
assets / (liabilities)
|
|
(61)
|
(82)
|
(35)
|
|
|
|
|
|
Net
assets
|
|
9,616
|
11,262
|
9,700
|
|
|
|
|
|
Capital and
reserves
|
|
|
|
|
Called up
share capital
|
|
5,196
|
5,076
|
5,137
|
Share
premium account
|
|
11,418
|
10,461
|
11,119
|
Warrant
reserve
|
|
442
|
782
|
782
|
Retained
losses
|
|
(7,608)
|
(5,226)
|
(7,506)
|
Foreign
currency reserve
|
|
168
|
169
|
168
|
Total
equity
|
|
9,616
|
11,262
|
9,700
|