Alba
Mineral Resources Plc / EPIC: ALBA / Market: AIM / Sector:
Mining
29 October 2024
Alba Mineral Resources
Plc
("Alba"
or the "Company")
Clogau Operational
Update
Alba Mineral Resources Plc (AIM:
ALBA) is pleased to report on the progress of ongoing works at the
Company's 100% owned Clogau-St David's Gold Mine in north Wales
("Clogau" or the "Mine").
Key
Points
- Underground
operations are ongoing at the Llechfraith Target, Alba's priority
target at Clogau, with blasting having taken place at Levels 4.5
and 5. Newly blasted ore currently remains underground but
will be removed to surface for sample processing and
assaying.
- The volume of
ore found in situ at Levels 4 and 5 from historic mining operations
has greatly exceeded what was anticipated, leading to a significant
ore extraction exercise being completed prior to blasting,
involving some 25 tonnes. Although this has added to the Company's
development timeline, it is considered overall positive as this
additional ore will be processed for its gold content.
- Site visits
completed by HM Inspectorate of Mines, part of the Health and
Safety Executive ("HSE"), and Natural Resources Wales ("NRW"), with
some further remedial works requested by HSE having since been
completed.
- While these
developments have pushed out the Company's timelines for the
completion of bulk sampling at the Llechfraith Target, Alba now
expects the next sequence of blasting to commence on Level 5 later
this week. Following the completion of the next sequence, the
Company expects to be able to provide an update on overall
timings.
- Blasts undertaken to
date have been successful and confirmed that the rocks at Clogau
are amenable to blasting by low-impact deflagrating explosives,
which is a major positive as the Company moves forward with the
development of the Project.
- From the test gold
production to date, the Company intends to auction a limited run of
commemorative coins in the coming weeks. Further details will be
announced in due course.
George Frangeskides, Executive Chairman,
commented:
"Since our last update, we have completed a substantial amount
of work underground. The need to clear out a large volume of
residual ore, combined with additional remedial measures requested
by the Mines Inspector, has pushed out our planned blasting
timeline, however our mining team anticipate being able to
recommence blasting on No.5 Level later this
week.
"The blasting we have undertaken to date, both on 4.5 and 5
Levels, has been successful and confirmed the suitability of the
deflagrating explosives we are currently using. This also gives us
confidence that the blasting programme should be able to proceed
efficiently from here.
"In related news, we have been working hard also on our plans
for the commercialisation of gold produced from Clogau. We intend
to release soon the details of a limited run of commemorative coins
which are being produced from our test gold production to
date."
Works Completed Since Last RNS
Since the last operational update
RNS on 30 August 2024, the Company has completed the following
works, among others:
Underground Works
Adit Level
- Concrete bed laid and winch installed at the Main
Shaft.
- Main Shaft sheave wheel rehabilitated.
No.4 Level
- Sampling completed on No.4 Level.
- Old ladders stripped out of Sub Shaft and new ladderways
installed from No.4 to 4.5 Level.
- Vent ducting installed from Drainage Level to No.4 Level
fan.
- Electrical reticulation extended to No.4 Level for connection
of fan and winch.
- Old pipes cut and removed on No.4 Level.
- Concrete laid for No.4 Level Sub Shaft winch bed and winch
installed.
- Concrete laid for Sub Shaft station
area.
- Roof bolts installed for sheave wheel at Sub Shaft.
- Pressure washing of walls.
- New Kubota KC70VHD-4 tracked loader delivered to No.4 Level in
preparation for transport to No.5 Level.
No.4.5 Level
- Pressure washing of walls.
- Ladderway installed from 4.5 to 5 Level.
No.5 Level
- Back up pump installed on No.5 Level.
- Air line installed from Mine Yard compressor to No.5
Level.
- 25 tonnes of rock from previous periods of mining dug out from
No. 5 Level and extracted to Llechfraith Mine Yard.
- Sump dug out on No.5 Level for siting of pump below floor
level.
- Water supply fitted for drilling of blast holes.
- Pressure washing of
walls.
- Drilling of blast
holes and blasting on No.5 Level.
Pilot Processing
Plant
- New sump installed in plant to create a closed water
system.
- Tailing pipes and water supply
reconfigured.
- New hammers fitted to the mill.
- Pump motor changed and extraction fan repaired on the primary
crusher.
- On-going test processing of various
ores.
Surface Works
- Cleared land access across the bridge from the Llechfraith
Mine Yard to gain access to the historic explosives storage
magazine.
- Bridge integrity inspection carried out by engineering
consultant.
- Historic mine material cleaned from between the rails on
surface for possible gold content.
- Fitted additional pipework on outflow side of the settlement
tank.
- Fitted out a dry room in the Llechfraith Mine Shed for the use
of personnel.
- PAT electrical testing completed, as well as upgrade of
electricity supply from hydro plant.
- Removal of tailings to temporary storage
zone.
- Reclaiming of rails for use on shaft doors.
Safety
-
Additional anchor points fitted. All anchor points
pull tested and registered.
-
Fall arrests installed at all
ladderways.
-
Safety gates fitted at Main Shaft (Adit Level and
No.4
Level).
-
Pneumatic shaft doors installed on Main
Shaft.
-
Shaft doors and gates installed at Sub Shaft (No.4
Level).
-
Underground signalling and telephone systems
installed for Main
Shaft.
Regulatory
- NRW and HSE site visits
completed.
- Extension of European Protected Species Licence ("EPSL")
applied for and granted, now valid for continuous underground
operations until 30 September 2025.
Forward Looking
Statements
This announcement contains
forward-looking statements relating to expected or anticipated
future events and anticipated results that are forward-looking in
nature and, as a result, are subject to certain risks and
uncertainties, such as general economic, market, financial and
business conditions, competition for and availability of qualified
staff and contractors, regulatory processes and actions, technical
issues, new legislation, uncertainties resulting from potential
delays or changes in plans, uncertainties resulting from working in
a new political jurisdiction, uncertainties regarding the results
of exploration, uncertainties regarding the timing and granting of
prospecting rights, uncertainties regarding the timing and granting
of regulatory and other third party consents and approvals,
uncertainties regarding the Company's or any third party's ability
to finance, execute and implement future plans and programmes, and
the occurrence of unexpected events. Actual results achieved may
vary from the information provided herein as a result of numerous
known and unknown risks and uncertainties and other
factors.
**ENDS**
For further information, please
visit www.albamineralresources.com or
contact:
Alba Mineral Resources
plc
George Frangeskides, Executive
Chairman
|
+44 20
3950 0725
|
SPARK Advisory Partners Limited
(Nomad)
Andrew Emmott
|
+44 20
3368 3555
|
CMC Markets plc (Broker)
Thomas Smith / Douglas
Crippen
|
+44 20
3003 8632
|
Alba's
Projects & Investments
|
Projects Operated by Alba
|
Location
|
Ownership
|
Clogau (gold)
|
Wales
|
100%
|
Dolgellau Gold Exploration
(gold)
|
Wales
|
100%
|
Gwynfynydd (gold)
|
Wales
|
100%
|
Investments Held by Alba
|
Location
|
Ownership
|
GreenRoc Strategic Materials Plc
(graphite - anode)
|
Greenland
|
34.34%
|
Horse Hill (oil)
|
England
|
11.765%
|