Q3 2024 Production Report
Kenmare Resources plc
(“Kenmare” or “the Company” or “the Group”)
17 October 2024
Q3 2024 Production Report
Kenmare Resources plc (LSE:KMR, ISE:KMR), one of
the leading global producers of titanium minerals and zircon, which
operates the Moma Titanium Minerals Mine (the "Mine" or "Moma") in
northern Mozambique, is pleased to provide a trading update for the
quarter ending 30 September 2024 (“Q3 2024”).
Statement from Tom Hickey, Managing
Director:
“I am delighted to report my first quarterly
production update as Managing Director. I visited Moma in September
for the first time since taking on the role and it was encouraging
to see the significant progress being made on the Wet Concentrator
Plant A upgrade. It was also exciting to discuss the near-term
commissioning of a small-scale dredge-mining and concentrating
operation to support production in 2025 and beyond. Additionally,
we made the first trial shipment of a new concentrates product
during the quarter.
Production strengthened in Q3 compared to
Q2, as expected, due to higher excavated ore volumes, and Kenmare
is on track to achieve its 2024 guidance on all metrics. Shipments
also improved significantly, with over 300,000 tonnes of products
shipped, and this is expected to drive stronger financial
performance in H2 versus H1.
Market conditions for all of our products
continue to be robust, with the healthy demand we experienced in Q3
extending into Q4. Our order book is largely committed for the
remainder of the year.”
Q3 2024 overview
- Lost Time Injury Frequency Rate
(“LTIFR”) of 0.06 per 200,000 hours worked for the 12 months to 30
September 2024 (30 September 2023: 0.21)
-
Kenmare is on track to achieve 2024 guidance across all stated
metrics
- Heavy Mineral Concentrate (“HMC”)
production of 355,400 tonnes in Q3 2024, down 14% year-on-year
(“YoY”), primarily due to lower ore grades, in line with
expectations
- Ilmenite production of 257,400
tonnes in Q3 2024, down 12% YoY, due to reduced HMC processed
- Primary zircon production of 14,600
tonnes, up 4% YoY, due to improved recoveries and the processing of
intermediate stocks
- Total shipments of finished
products of 302,700 tonnes, up 85% YoY due to the timing of
shipments in Q3 2023, and up 29% on Q2 2024 due to improved weather
conditions
-
The project to upgrade Wet Concentrator Plant (“WCP”) A in
preparation for Nataka mining remains on budget. Twenty pontoons
have arrived at site, allowing the commencement of the construction
phase of the project
-
Commissioning of a new small-scale dredge-mining and concentrating
operation expected to commence in late Q4 2024, with a capital cost
of less than $6 million
- Strong global pigment production
supporting demand for Kenmare’s products
- Kenmare has continued to engage
constructively with the Government of Mozambique regarding the
Implementation Agreement renewal in December 2024
- As previously announced, Tom Hickey
was appointed as Managing Director on 15 August 2024, succeeding
Michael Carvill
- A process is underway to identify
Tom’s successor as Chief Financial Officer and an update is
expected to be provided during Q4 2024
Operations update
Production from the Moma Mine in Q3 2024 was as
follows:
|
Q3 2024 |
Q3 2023 |
Q3 2023 |
Q2 2024 |
Q2 2024 |
tonnes |
tonnes |
% variance |
tonnes |
% variance |
Excavated ore1 |
11,089,000 |
10,822,000 |
2% |
10,386,000 |
7% |
Grade1 |
3.80% |
4.32% |
-12% |
3.84% |
-1% |
Production |
|
|
|
|
|
HMC production |
355,400 |
414,600 |
-14% |
342,600 |
4% |
HMC processed |
356,000 |
412,900 |
-14% |
343,200 |
4% |
Ilmenite |
257,400 |
291,200 |
-12% |
238,600 |
8% |
Primary zircon |
14,600 |
14,100 |
4% |
13,000 |
12% |
Rutile |
2,900 |
2,700 |
7% |
2,500 |
16% |
Concentrates2 |
13,500 |
14,700 |
-8% |
11,700 |
15% |
Shipments |
302,700 |
163,400 |
85% |
234,700 |
29% |
1. Excavated ore tonnage and grade prior to any
floor losses.
2. Concentrates include secondary zircon, mineral sands concentrate
and a new trial concentrates product.
Kenmare’s rolling 12-month LTIFR to 30 September
2024 was 0.06 per 200,000 hours worked (30 September 2023: 0.21)
and one Lost Time Injury was recorded during Q3 2024.
HMC production was 355,400 tonnes in Q3 2024, a
14% decrease YoY, due primarily to a 12% decrease in ore grades.
Slower mining rates from the WCP A dredges, due to higher slimes
and a descending mine floor, were partially offset by increased dry
mining. However, the slower dredging advance delayed higher grades,
which are now being mined in early Q4.
Ilmenite production was 257,400 tonnes, down 12%
YoY due to reduced HMC processed, partially offset by improved
recoveries in the Mineral Separation Plant and processing of
intermediate stocks. Primary zircon production was up 4% YoY to
14,600 tonnes, also benefitting from higher recoveries and drawdown
of intermediate stocks. Rutile production was up 7% YoY to 2,900
tonnes, supported by improved recoveries, delivering record
quarterly rutile production. Concentrates production was 13,500
tonnes, down 8% YoY, offset by the production of a new concentrates
product on a trial basis in Q3 2024.
Total shipments in Q3 2024 were 302,700 tonnes,
including two zircon shipments that were delayed from Q2 and
shipped in early Q3. Shipments were up 85% YoY, due to the timing
of shipments in Q3 2023, when two large ilmenite shipments were
completed after period end and attributed to Q4 2023. Shipments
increased by 29% on Q2 2024 due to improved weather conditions.
Shipments in Q3 2024 comprised 269,200 tonnes of ilmenite, 12,500
tonnes of primary zircon, 3,700 tonnes of rutile and 17,300 tonnes
of concentrates.
Shipments of concentrates included 3,100 tonnes
of a new concentrate product that was sold on a trial basis to
customers in Q3. Kenmare expects to ship this product on a
commercial basis and incorporate in annual guidance from January
2025.
Closing stock of HMC at the end of Q3 2024 was
24,000 tonnes, compared to 24,600 tonnes at the end of Q2 2024.
Closing stock of finished products at the end of Q3 2024 was
259,200 tonnes, compared to 273,000 tonnes at the end of Q2 2024,
reflecting improved shipments exceeding production in Q3. Kenmare
continues to expect stock levels to remain higher than usual in Q4,
due to strong production and high levels of finished product stock
at the end of H1, before normalising during H1 2025.
Capital projects update
WCP A upgrade
The project remains on budget, with upgrade
works continuing to advance, thereby progressively derisking the
project. At the end of Q3, 68% of the project budget has been
committed and approximately 75% is expected by year-end.
The fabrication of the two new dredges continues
to progress with the project contractor in the Netherlands. Twenty
out of 42 of the pontoons for the new WCP module, incorporating the
upfront desliming circuit, screens and surge bin, have arrived at
Moma and construction has commenced. The detailed design of the
Tailings Storage Facility (“TSF”) was completed in Q3 2024, with
construction incorporating Global Industry Standard on Tailings
Management (GISTM) standards expected to begin in Q4 2024.
Construction of the infrastructure in Nataka to support the TSF is
underway.
Selective Mining Operation (“SMO”)
The introduction of a new small-scale
dredge-mining and concentrating operation, or SMO, will enable
mining in peripheral areas of Mineral Resources in the Pilivili
high dunes and Namalope Flats at the Mine. These areas are low in
slimes, high in grade and not accessible by the larger WCPs or
existing dry mining operations that are limited by groundwater
levels, which prevent the extraction of ore below the water
table.
The SMO will consist of two small cutter-suction
dredges, a slurry bin unit, screening equipment, and a 300 tonnes
per hour concentrator spiral plant. This represents 60% of the
capacity of WCP C, which is currently the smallest of Kenmare’s
three mining operations. The first SMO module is en-route to Moma
by sea and is expected to arrive in Q4 2024. The first dredge and
half of the spiral circuit capacity are expected to be commissioned
by year-end and the remainder in early 2025.
Due to the free-flowing nature of the ore to be
mined and the simple, modular design of the operation, the capital
expenditure for both units is anticipated to be less than $6
million in total. This is a small investment that is expected to
add HMC production with a very low capital intensity. It is a new
approach to mining at Moma and may present further opportunities,
depending on the success of the first module.
The introduction of the SMO supports Kenmare’s
ability to deliver ilmenite production in 2025 that is broadly in
line with 2023 and 2024 levels, despite the planned downtime for
WCP A required to facilitate the replacement of the dredges and the
upgrade of the plant. The SMO is expected to produce approximately
50,000 tonnes of HMC per annum, enabling exploitation of resources
that would otherwise not be mined.
Corporate update
As previously announced, Tom Hickey was
appointed as Managing Director on 15 August 2024. Tom succeeds
Michael Carvill, who stepped down from the Board and his executive
role after 38 years.
A process is underway to appoint Tom’s successor
as Chief Financial Officer. The Company expects to provide an
update on the results of the process during Q4 2024.
During the period, Kenmare has continued to
engage constructively with Government of Mozambique representatives
in relation to the renewal of Moma’s Implementation Agreement
(“IA”). The IA governs fiscal and other terms of the Industrial
Free Zone, under which Kenmare conducts its mining, beneficiating
and export activities and does not govern or impact day-to-day
mining operations. On 9 October 2024 Mozambique held elections and
electoral authorities have until 24 October to announce the final
results. Kenmare believes that Government representatives share its
objective of concluding the renewal process before the 21 December
renewal date, without the need for recourse to the dispute
resolution procedures provided for in the agreement.
Market update
Kenmare continued to experience encouraging
demand for all products in Q3 2024. While ilmenite prices were
stable during Q3, the Company's average price received increased on
the prior quarter, as expected. The product mix benefitted from two
high-value zircon shipments which left Moma in July 2024, having
been delayed from Q2. Strong demand for Kenmare’s products has
extended into Q4, with the Company’s order book largely committed
into 2025
In Q3 demand for Kenmare’s ilmenite benefitted
from both strong Chinese pigment production and increased
production rates in other regions. Pigment production in China
remained resilient in Q3, despite soft domestic demand and the
impact of the anti-dumping regulations from the European Union
(“EU”) and the Commonwealth of Independent States. Although exports
to the EU from China have decreased, there has been an uptick in
exports to some Asian markets. Western producers reported increased
pigment sales in Q2, viewing the regulatory constraints on Chinese
exports as an opportunity.
Strengthening global demand for titanium
feedstocks in Q3 was matched by increased supply, enabling the
market to remain balanced. The main contributor to this supply
growth was from Mozambique, with a new project ramping up
production and shipments this year while increased HMC production
from new projects in Australia also contributed.
Kenmare received a marginally higher average
price for its zircon products in Q3 compared to Q2, supported by
the constrained supply of high-quality zircon products. Demand from
the ceramics sector weakened during the quarter due to the downturn
in China’s real estate market and this is expected to impact zircon
prices in Q4, however the Company believes that due to supply
constraints in the medium and long-term, the fundamentals for its
zircon products remain strong.
For further information, please contact:
Kenmare Resources plc
Jeremy Dibb / Katharine Sutton
Investor Relations
ir@kenmareresources.com
Tel: +353 1 671 0411
Mob: + 353 87 943 0367 / + 353 87 663 0875
Murray (PR advisor)
Paul O’Kane
pokane@murraygroup.ie
Tel: +353 1 498 0300
Mob: +353 86 609 0221
About Kenmare Resources
Kenmare Resources plc is one of the world's
largest producers of mineral sands products. Listed on the London
Stock Exchange and the Euronext Dublin, Kenmare operates the Moma
Titanium Minerals Mine in Mozambique. Moma's production accounts
for approximately 7% of global titanium feedstocks and the Company
supplies to customers operating in more than 15 countries. Kenmare
produces raw materials that are ultimately consumed in everyday
quality-of life items such as paints, plastics and ceramic
tiles.
All monetary amounts refer to United States dollars unless
otherwise indicated.
Forward Looking Statements
This announcement contains some forward-looking
statements that represent Kenmare's expectations for its business,
based on current expectations about future events, which by their
nature involve risks and uncertainties. Kenmare believes that its
expectations and assumptions with respect to these forward-looking
statements are reasonable. However, because they involve risk and
uncertainty, which are in some cases beyond Kenmare's control,
actual results or performance may differ materially from those
expressed or implied by such forward-looking information.
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Nov 2024 to Dec 2024
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Dec 2023 to Dec 2024