Kodal
Minerals Plc / Index: AIM / Epic: KOD / Sector: Mining
31 July 2024
Kodal Minerals
plc
("Kodal
Minerals", "Kodal" or the "Company")
Bougouni Lithium Project
Update - Construction Progress on Track
The Board of Kodal Minerals, the
mineral exploration and development company, is pleased to provide an update on project development
activities at its fully funded Bougouni
Lithium Project in Southern Mali ("Bougouni" or the "Project"). The Project is fully
funded through the Hainan funding transaction as previously
announced by the Company on 15 November 2023 that completed a
US$100m investment into Kodal Mining UK Limited ("KMUK") a company
owned 51% by the Hainan group and 49% Kodal that is the developer
of the Project.
Highlights:
·
Shipping of the dense media separation
("DMS") processing plant and crushing circuit modules is progressing with minor
delays for reasons outside KMUK's control, namely, the diversion of
the vessel to Freetown, Sierra Leone to offload other humanitarian
cargo deemed urgent by the operator. The vessel has since departed
Freetown and is enroute to the scheduled Abidjan port in Cote
d'Ivoire.
·
Structural steelwork fabrication was completed in
June and is also on the above-mentioned vessel.
·
The second shipment is also currently enroute to
Abidjan port, passing Walvis Bay port in Namibia. This shipment
contains the remainder of the processing plant equipment, the
initial consumables for the DMS plant, spare parts, chemical
laboratory and site equipment.
·
The mining contractors consortium
comprising Auxin Mining Services Mali
SARL ("Auxin") and Enterprise Générale
Traoré et Fréres SARL ("EGTF") (the "Mining Contractors") is
progressing well with mining at the Ngoualana pit.
·
The civil construction contractor, Bambara
Resources SARL ("Bambara"), together with its key subcontractor,
GZB Mali, part of the Gezhouba Group (GZB) from China, has
completed all major footings for the DMS plant in readiness to
receive steelwork for erection.
·
Overall, the Project remains on budget and on
target for production by the end of 2024.
Bernard Aylward, CEO of Kodal Minerals,
remarked: "The construction of the
Bougouni Project continues to progress satisfactorily with the
targeted first production before the end of 2024 remaining on
schedule. The shipment of the DMS plant, key equipment and plant
steelwork has experienced some minor shipping delays which were
outside of our control. However, this will not impact our overall
production commencement target and work onsite is continuing in
preparation of the arrival of the processing
plant."
"The civil contractor has completed the installation of all
major DMS plant footings, clearing the way for unfettered access
for installation works to complete steelwork and platework erection
activities."
"The Mining Contractors commenced the mining of overburden
materials at the Ngoualana pit at the beginning of July with this
material predominantly "free dig" oxide waste. Hard rock will be
reached next month, after which it is anticipated that our first
blast will be conducted in early September 2024. The mining team is
on target to have a stockpile of ore on the ROM pad for
commissioning and commencement of processing."
"We remain on track to achieve first production by year end,
and within the projected capital expenditure ("Capex") guidance of
US$65m."
FURTHER
INFORMATION
Shipping of equipment and
steelwork
Critical long lead equipment,
steelwork and platework items for the DMS processing plant are
enroute to West Africa. KMUK has experienced minor delays with the
shipment of the aforementioned items due to reasons outside of its
control, namely the diversion of the vessel to Freetown in Sierra
Leone to offload other humanitarian cargo that was deemed urgent by
the operator.
As a result, KMUK has conducted a
critical review of the overall construction schedule and sequencing
to assess the potential impacts of the delayed shipment and remains
confident that the shipping delay experienced will not impact the
overall production milestone target of the end of 2024. The freight
forwarding agent is making all the necessary preparations for
prompt clearance and transport of cargo in priority order to site.
The site construction of the DMS and steelwork design will be
supervised by experts from Haiwang Technology Group ("Haiwang") as
part of the agreed purchase of the equipment from Haiwang. This
assistance will provide the installation team with immediate access
to technical experts from Haiwang who were involved in the design
and fabrication tasks and have supervised previous installations at
various sites.
The final remaining major shipment
is currently enroute from China, carrying the power plant, as well
as other minor outstanding sub-critical piping and electrical
items.
Civil construction - concrete
contract
The civil construction works have
continued to progress satisfactorily, and all major concrete
footings required for the assembly and erection of the DMS plant
steelwork have been completed. The delay of the shipment will give
the civil contractor additional time to fully prepare the access
avenues to the DMS area, and to ensure hardstands for crane
operations are established and solid.
Mining
contract
Mining activities are progressing
very well on site. The Mining Contractors' mobilisation activities
are advancing with the establishment of the explosives storage and
mixing yards, and the general mine services facilities. The final
location of the explosives storage and mixing yards was agreed with
the community representatives, mindful of limiting impacts to
existing agricultural areas. In addition, construction and secure
fencing of the explosive storage area is now near completion. Land
acquisition compensation arrangements have also been agreed in
accordance with statutory obligations.
Removal of "free dig" overburden at
the main Ngoualana pit is proceeding to plan in order to remove the
softer oxide waste and expose the hard rock beneath. The Mining
Contractors are on schedule to complete the free dig works in
advance of the first blast at the pit which is scheduled for early
September 2024.
Environmental and social
updates
As part of the community
consultation process and our commitment to improving the livelihood
of the adjacent communities, KMUK donated two tractors to the
Kola-Sokoura and Ngoualana villages back in March 2024. It is
pleasing to see the village farmers making constructive shared use
of the two tractors and we've received much praise and appreciation
for this initiative which has enabled the communities to improve
their farming productivities.
On 28 June 2024, KMUK'S ESR Manager,
Operations Director and our entire community relations team
attended the school ceremonies on the final day before the start of
school holidays for the Kola-Sokoura School. In addition, KMUK
awarded gifts of encouragement to the best performing students in
the class and to the teacher in the presence of the parents of
students, the chief of the village and his administration notables,
and an educational advisor from the Centre for Pedagogical
Animation (CAP) of Bougouni.
**ENDS**
For further information, please
visit www.kodalminerals.com or contact the following:
Kodal Minerals plc
Bernard Aylward, CEO
|
Tel: +61 418 943 345
|
Allenby Capital Limited, Nominated
Adviser
Jeremy Porter/Vivek Bhardwaj/Nick
Harriss
|
Tel: 020 3328 5656
|
SP Angel Corporate Finance LLP,
Financial Adviser & Joint Broker
John Mackay/Adam Cowl
|
Tel: 020 3470 0470
|
Canaccord Genuity Limited, Joint
Broker
James Asensio/Gordon
Hamilton
|
Tel: 0207 523 4680
|
Burson Buchanan, Financial
PR
Bobby Morse/Oonagh Reidy
|
Tel: +44 (0)20 7466 5000
kodal@buchanancomms.co.uk
|