Continental Nickel Limited (TSX VENTURE:CNI) ("CNI" or the
"Company") is pleased to announce that it has received a positive
Preliminary Economic Assessment ("PEA") for the development of its
Ntaka Hill Nickel Project ("Ntaka Hill" or the "Project"). Ntaka
Hill is part of the 75:25 Nachingwea exploration joint venture
property in southern Tanzania with IMX Resources Limited of
Australia.
Highlights
-- Total after tax NPV for the Base Case of US$207M.
-- Total life of mine forecast production for the Base Case of 376 million
lbs of nickel contained in high grade concentrate, based on Mineral
Resources announced 15 April 2011.
-- Low capital cost for the project reflecting the low infrastructure
requirements and staged development.
-- Initial scale of the project sized to suit extraction of high grade near
surface Measured and Indicated Resources in the first four years
followed by an expansion, which will of a scale to suit the resources in
the Sleeping Giant zone, which are still the subject of step-out
drilling.
-- Overall mine life in excess of 12 years.
-- Cash costs (C1) and total production costs (C2) per pound of contained
nickel in the second quartile on industry cost curves.
-- Excellent metallurgical performance (previously announced in detail 15
September 2011) delivers the possibility to attract a premium for the
concentrate off take.
Immediate Upside
-- Previous drilling of the Sleeping Giant zone showed the presence of low
grade mineralisation that is not included in the current resource
estimate.
-- Results of the PEA indicate that a lower cut-off grade can be used than
in the preparation of the current Mineral Resource.
-- A Sensitivity Case based on an allowance for potential tonnage and grade
of this low grade mineralisation in the Base Case pit indicated the
possibility of increasing contained nickel production by 20% and greatly
improving project value.
-- The current extension drilling program continues to provide positive
results on the Sleeping Giant zone which also includes wide
intersections of disseminated mineralisation within the Base Case pit
shell. These results, along with full analysis of the low grade
mineralisation, will be used to update Mineral Resources and the
economic assessment at the beginning of the second quarter of 2012.
The study considered two development scenarios and the upside
sensitivity case which are outlined further below. As shown in
Table 1 below, the Project provides a positive economic outcome
from the mining and treatment of the resources at Ntaka Hill.
Table 1 - Highlights of Project and Economic Outcomes
----------------------------------------------------------------------------
Parameter Base Case
----------------------------------------------------------------------------
Mining
Years 1 to 4 processing rate, Mtpa 1.0
Years 5 onwards processing rate, Mtpa 2.5
Total mill feed, Mt 23.8
Total material mined, Mt 432.8
Strip ratio 17.2
----------------------------------------------------------------------------
Production
Average Feed Grade, %Ni 0.82
Average Ni Recovery, % 87.3
Average Concentrate Grade, %Ni 15.2
Concentrate Contained Ni, lbs'000 377,000
----------------------------------------------------------------------------
Capital Costs
Initial Capital Cost, US$M 216.7
Total Capital Cost, US$M 559.0
----------------------------------------------------------------------------
Unit Production Costs, US$/lb. Ni
Operating 4.24
Capital 1.48
Total 5.72
----------------------------------------------------------------------------
Economic Outcomes, US$M
Net after-tax cash flow 539
After-tax internal rate of return, % 21.6
After-tax NPV @ 8% discount rate 207.4
----------------------------------------------------------------------------
Note: All cases in this Preliminary Economic Assessment are preliminary in
nature and include both Indicated and Inferred Mineral Resources. Inferred
Mineral Resources are considered too speculative geologically to have the
economic considerations applied to them that would enable them to be
categorized as Mineral Reserves. There is no certainty that the Preliminary
Economic Assessment will be realized.
Mr. David Massola, President and CEO, commented "The positive
results of the technical study are an important milestone in the
advancement of the Ntaka Hill Project. The Company will move into
the next stage of evaluating the project by updating the resources
and project economics to include the analysis of already identified
low grade mineralisation and incorporate the results of this
season's step-out drilling on Sleeping Giant."
"We will progress options studies looking at various project
parameters and other technical studies in 2012 with the goal of
preparing a feasibility study by the end of the year. In parallel
with this, we will move forward with detailed metallurgical test
work and the environment studies and permitting as these represent
the critical path in bringing the project into production."
"We are also confident that the Company's current and future
exploration programs will continue to add resources that will
enhance the project going forward."
The preliminary economic assessment was compiled by Roscoe
Postle Associates Inc. ("RPA"), Mineralurgy Pty Ltd ("Mineralurgy")
and Lycopodium Minerals Pty Limited ("Lycopodium"). The key
consultants involved in the studies are described at the end of
this press release, in the "Qualified Persons" section. The
preparation of the study was managed by Stewart Watkins, CNI's
Study Manager.
Next Steps
Based on the results of this PEA, CNI's management and board are
committed to continuing the evaluation of the Project. Activities
that are currently underway, which include drilling to secure
additional metallurgical samples, metallurgical test work,
environmental baseline studies and the preparation of the
environmental scoping study will position the project for fast
track development.
Following the completion of the step-out drilling, the extents
of the Sleeping Giant mineralisation will be redefined using an
updated nickel cut-off grade to accommodate the economics outlined
in this study. This will result in an update of the Mineral
Resource, which will include detailed analysis of the low grade
mineralisation that has been included in the Upside Sensitivity
Case. This updated Mineral Resource will then be used as a basis to
update the project economics. The company is targeting the start of
the second quarter 2012 to release the results of an updated
Preliminary Economic Analysis.
A detailed outline of the project evaluation and development
timeline with key milestone dates is outlined below.
Options Considered
The PEA considered two development scenarios, Open Pit Only or
"Base Case", Open Pit Plus Underground. Along with traditional
sensitivity analysis, an Upside Sensitivity Case was also
investigated to understand the impact of low grade mineralisation
that is believed to be contained in the Base Case Sleeping Giant
pit.
All of these scenarios commence operation at 1 Mtpa of mill feed
for four years followed by an expansion of the mining and
processing rate. This upgrade development philosophy is aimed at
providing a project scenario that delivers early production from
current Measured and Indicated Resources, maintains modest capital
requirements and is fundable for CNI.
The key aspects include:
Open Pit Only (Base Case)
-- Open pit mining of all zones with resources based on current Mineral
Resources announced April 2011.
-- First four years of ore production and processing at a rate of 1 Mtpa
from the higher grade near surface L, H, J, M and NAD013 zones which are
predominately contained in the current Measured and Indicated Resources
categories.
-- Expansion of ore production and processing rate in year five to 2.5 Mtpa
coinciding with the commencement of mining from the Sleeping Giant zone.
-- G zone, possessing lower grade and less favorable metallurgy, mined at
the end of the mine life.
-- Total mine life of approximately 12 years.
Open Pit Plus Underground
-- Resources based on current Mineral Resources announced April 2011.
-- First four years of ore production and processing at a rate of 1 Mtpa
from open pit mining of J, L, M, G and the upper portion of H zones.
-- Expansion of ore production and processing rate in year five to 2.5 Mtpa
coinciding with the commencement of underground mining from the Sleeping
Giant, NAD013 and the lower portion of H zones.
-- Total mine life of just over 12 years.
Upside Sensitivity Case
-- Open pit mining of all zones with resources based on current Mineral
Resources and the addition of an allowance for potential tonnage and
grade of the low grade mineralisation contained in the upper parts of
the Sleeping Giant pit shell. The understanding of the value of any low
grade mineralisation contained in the pit shells has been a recent
occurrence and, as such, there has been insufficient time to complete a
rigorous geological interpretation of this low grade mineralisation.
-- First four years of operations identical to the Base Case.
-- Expansion of ore production and processing rate in year five to 4 Mtpa
coinciding with the commencement of mining from the Sleeping Giant zone.
-- G zone mined at the end of the mine life.
-- Total mine life of just over 12 years.
-- It should be noted that the Upside Sensitivity Case includes an
allowance for material identified as an "exploration target" (as defined
by NI43-101). The allowance for the quantity and grade of this
"exploration target" is conceptual in nature and there has been
insufficient analysis completed to define a Mineral Resource. It is
uncertain if further exploration will result in the definition of a
Mineral Resource in this area.
The economic analysis of the options demonstrated that the Open
Pit Only (Base Case) scenario provided a far superior return than
the Open Pit Plus Underground scenario (which achieved an after-Tax
NPV @8% of US$117M) and as such further discussion of this scenario
is not included in this release.
Mineral Resources
Ntaka Hill resources, as disclosed on 15 April, 2011, are
outlined below in Table 2.
Table 2 -Summary of Ntaka Hill Mineral Resources
----------------------------------------------------------------------------
Resource Category Tonnes % Ni % Cu Contained Ni
(000's) (tonnes)
----------------------------------------------------------------------------
Measured 1,871 1.74 0.30 32,500
Indicated 3,110 0.91 0.20 28,400
----------------------------------------------------------------------------
Total Measured + Indicated 4,981 1.22 0.24 60,900
----------------------------------------------------------------------------
Inferred 17,260 0.76 0.17 131,000
----------------------------------------------------------------------------
Notes:
1. CIM definitions were followed for Mineral Resources.
2. Mineral Resources were estimated at a NSR cut-off value of $17/t for
open pit mining; this corresponds to an approximate grade of 0.14% Ni.
3. Mineral Resources were estimated using an average long-term nickel,
copper, and cobalt prices of $10.00/lb, $3.50/lb, and $20.00/lb,
respectively.
4. Preliminary metal recoveries were estimated at 87% for nickel, 81% for
copper, and 80% for cobalt.
5. No minimum width was used.
6. Ntaka Hill Mineral Resources collectively include J, G, M, L, NAD013, H
and Sleeping Giant zones.
The current and previous drilling programs have also intersected
multiple zones of disseminated sulphide mineralization located
above the Sleeping Giant zone which have not yet been included in
the Mineral Resource estimate. An allowance of between 12 Mt and 14
Mt, at grades ranging from 0.25% Ni to 0.40% Ni has been made for
this low grade "exploration target" (as defined in Ni 43-101) based
on conceptual interpretation of low grade mineralisation
intersections contained within the bounds of the Sleeping Giant pit
shell.
Mining
Open Pit Mining is based on conceptual pit shells. Mining is
planned to be carried out by contract mining for the first four
years of production by conventional means with a conversion to
owner mining thereafter. Key mining parameters used and calculated
in the PEA are summarised in Table 3.
Table 3 - Key Mining Parameters
----------------------------------------------------------------------------
Parameter Base Case
----------------------------------------------------------------------------
Pre-Production
Tonnes Moved, Mt 8.0
Years 1 to 4
Mill Feed Production, Mtpa 1.0
Mill Feed Produced, Mt 3.9
Waste Moved, Mt 78.1
Total Moved, Mt 82.0
Total Moved per Day, t 66,000
Strip Ratio 20.0
Years 5 to LOM
Mill Feed Production, Mtpa 2.5
Mill Feed Produced, Mt 19.9
Waste Moved, Mt 322.9
Total Moved, Mt 342.7
Total Moved per Day, t 137,000
Strip Ratio 16.2
Life of Mine
Mill Feed Produced, Mt 23.8
Waste Moved, Mt 409.0
Total Moved, Mt 432.8
Strip Ratio 17.2
----------------------------------------------------------------------------
The Upside Sensitivity Case assumes that some material
classified as waste within the Sleeping Giant pit in the Base Case
will be processed as mill feed. Consequently the mining operation
for the first four years would remain unchanged however the ratio
between waste and mill feed would be reduced thereafter. It is
estimated that the change in stripping ratio would be to lower it
from the Base Case of 17.2 to between 10 and 12.
Processing, Metallurgy and Production
Preliminary metallurgical test work results have indicated that
the Project can use a conventional approach to the recovery of
nickel from sulphide ore and produce a high grade nickel plus
copper bulk concentrate with very low levels of MgO and clean of
other contaminants. These results have previously been announced
(15 September 2011) in detail. Using these initial flotation test
work results and previous mineralogical studies, an estimate was
made of the concentrate grade and recovery from each mineralised
zone and this was applied to the production schedule.
Based on typical industry practice, the mineralogical
information available and the initial flotation test work, a
flowsheet design and basic design criteria were developed for use
in this study. Key aspects of this design and criteria include:
-- Two stage crushing followed by ball milling to a product size of 80%
passing 75 micron.
-- Rougher flotation, followed by three stages of cleaning to produce a
combined nickel and copper bulk concentrate.
-- Thickening and filtration of the concentrate prior to loading into
containers for transport to smelters.
-- Typical reagent additions.
A summary of key production parameters are given in Table 4.
Table 4 - Key Processing and Production Parameters
----------------------------------------------------------------------------
Parameter Base Case
----------------------------------------------------------------------------
Years 1 to 4
Mill Throughput, Mtpa 1.0
Total Milled, Mt 3.9
Average Feed Grade, %Ni 1.41
Average Ni Recovery, % 84.4
Average Concentrate Grade, %Ni 16.9
Concentrate Contained Ni, lbs'000 102,000
Years 5 to LOM
Mill Throughput, Mtpa 2.5
Total Milled, Mt 19.9
Average Feed Grade, %Ni 0.71
Average Ni Recovery, % 88.1
Average Concentrate Grade, %Ni 14.6
Concentrate Contained Ni, lbs'000 275,000
Life of Mine
Total Milled, Mt 23.8
Average Feed Grade, %Ni 0.82
Average Ni Recovery, % 87.3
Average Concentrate Grade, %Ni 15.2
Concentrate Contained Ni, lbs'000 377,000
----------------------------------------------------------------------------
The inclusion of the allowance for low grade mineralisation in
the Upside Sensitivity Case reduces the average feed grade
following the commencement of expanded mining in the Sleeping Giant
zone to between 0.55% and 0.6% Ni however recovery to concentrate
would not be expected to vary greatly due to the excellent
metallurgical performance of the Sleeping Giant style
mineralisation.
Operating Costs
Operating costs for the mining, processing and general and
administration were developed for the Project by the various
consultants. Key input parameters for the operating costs
included:
-- Contractor mining for the initial four year of operations with a
conversion to owner mining thereafter.
-- Typical consumables, labour and other requirements.
-- Power sourced from the Mtwara distribution grid which is separate from
other parts of Tanzania and fed from a privately operated natural gas
fired power station. Connection to this grid is from existing lines near
Nachingwea (approximately 45km from site).
A summary of the operating costs is given in Table 5.
Table 5 -Operating Costs Summary (+/-30%)
----------------------------------------------------------------------------
Parameter Open Pit Only
US$'000 US$/t
----------------------------------------------------------------------------
Years 1 to 4
Mining 258,426
per tonne moved 3.15
per tonne milled 66.27
Processing 70,285 18.02
G&A 49,418 12.67
----------------------------------------------------------------------------
TOTAL 378,129 96.96
----------------------------------------------------------------------------
Years 5 to LOM
Mining 651,187
per tonne moved 1.90
per tonne milled 32.77
Processing 271,558 13.67
G&A 108,720 5.47
----------------------------------------------------------------------------
TOTAL 1,031,464 51.91
----------------------------------------------------------------------------
Life of Mine
Mining 909,613
per tonne moved 2.10
per tonne milled 38.27
Processing 341,843 14.38
G&A 158,138 6.65
----------------------------------------------------------------------------
TOTAL 1,409,594 59.30
----------------------------------------------------------------------------
Unit Operating Costs (US$/lb Ni) (net
of by-product revenue) 3.43
----------------------------------------------------------------------------
For the Upside Sensitivity Case for year five onwards (since
years 1 to 4 are identical to the Base Case) it would be expected
that the total mining costs would not change since the total
material mined would not vary, which would lead to a significant
reduction in the unit mining cost per tonne milled. Processing
costs would vary on the breakdown between fixed and variable costs
and G&A costs would be largely fixed. Based on this conceptual
style of analysis the Upside Sensitivity case would be expected to
return overall operating costs of between US$40 and US$45 per tonne
milled.
Capital Costs
A breakdown of the estimated capital costs for the Base Case is
presented in Table 6.
Table 6 - Breakdown of Capital Cost Estimate (+/-30%)
----------------------------------------------------------------------------
Cost Area Initial Upgrade Sustaining
(million US$) (million US$) (million US$)
----------------------------------------------------------------------------
Mining 31.2 148.0 46.9
Process Plant 64.5 50.2 6.0
Infrastructure 38.8 19.8 3.6
Tailings Dam 5.1 0.0 7.5
Environmental 0.0 0.0 21.0
Owners Costs 12.8 14.8 0.0
Working capital 16.1 8.5 0.0
EPCM 18.8 23.1 0.0
Contingency 29.4 32.8 0.0
----------------------------------------------------------------------------
TOTAL 216.7 297.2 85.0
----------------------------------------------------------------------------
Note: Working Capital recovery at the end of the LOM is US$39.9M giving a
total capital cost of US$559.0M
For the Upside Sensitivity Case, the up-front capital cost would
remain unchanged from the above, however, the plant upgrade costs
would increase with the increased throughput. These costs were
estimated from scaling to give a total upgrade capital cost of
around US$385M (comparable to US$297.2M for the Base Case) with
only minor increases in sustaining and working capital over the
Base Case.
Concentrate Marketing and Revenue
CNI engaged Mineral Commerce Services Pty Ltd ("MCS") to conduct
a concentrate marketing study to provide metal price assumptions,
concentrate terms and freight costs for use in the this study. MCS
developed base case metal price assumptions based on published
forecasts. A range of prices was forecast and median levels of
US$22,500 per tonne of nickel and US$7,500 per tonne of copper were
used.
MCS concluded that there would be significant demand for a
sulphide concentrate from the project with its high predicted
nickel grade and low contaminants. Based on typical off-take
contracts for high grade nickel concentrates MCS estimated that the
project should achieve 77% payable for nickel (inclusive of
smelting and refining charges and at forecast prices) with an
average of US$90 per dry metric tonne of concentrate for other
metal credits.
Concentrate from the project will be containerised at the mine
site and trucked approximately 300km to the port of Mtwara in
southern Tanzania. Containerised concentrate will be stored near
the port and then loaded using ships gear on an approximately
monthly basis. Concentrate transport costs were estimated based on
typical trucking and shipping charges with Tanzanian specific port
charges estimated. These costs are summarised in Table 7.
Table 7 - Concentrate Transport Estimates
----------------------------------------------------------------------------
Parameter Cost
US$/dry t
----------------------------------------------------------------------------
Road transport to port 57.00
Port Handling 26.00
Port ad valorem (Tanzanian Port Authority Charge) 0.5% of CIF Value
Weighing, sampling and assaying at destination 4.00
Insurance 3.00
Sea Freight
China 32.00
Europe 98.00
North America 84.00
South America 79.00
----------------------------------------------------------------------------
The concentrate marketing and freight terms were reviewed by RPA
for use in the PEA.
Economic Assessment
RPA developed a financial model for the Project using the
production parameters, capital and operating costs and revenue
information presented above. Assumptions on taxation and other
financial parameters were provided by CNI. The net present value
(NPV) and Internal Rate of Return (IRR) discounted to the
commencement of project delivery are presented on an after-tax
basis (only Tanzanian taxes included). Table 8 below presents the
financial highlights associated with the Project.
Table 8 - Financial and Investment Analysis Highlights
----------------------------------------------------------------------------
Parameter Base Case
----------------------------------------------------------------------------
Financials, US$M
Revenues (mine gate basis) 2,721
Operating income (EBIT) 1,242
Net earnings 1,028
Cash flow from operations 1,433
Free cash flow to equity 539.0
Investment Analysis, US$M
Initial Capital Cost 216.7
Expansion Capital Cost 297.2
Total Sustaining Capital 85.0
Total Capital (after working capital recovery) 559.0
After-tax internal rate of return, % 21.6
Payback, years 5.3
After-tax NPV @ 8% discount rate 207.4
----------------------------------------------------------------------------
Note: All scenarios in this Preliminary Economic Assessment are preliminary
in nature and include both Indicated and Inferred Mineral Resources.
Inferred Mineral Resources are considered too speculative geologically to
have the economic considerations applied to them that would enable them to
be categorized as Mineral Reserves. There is no certainty that the
Preliminary Economic Assessment will be realized.
The cash costs (C1) and the total production costs (C2) per
pound of nickel net of by-product credits for the Base Case are
calculated to be US$4.24 and US$5.72 respectively. Both of these
measures place the project in the second quartile of global nickel
producers on published industry cost curves.
As previously stated, the inclusion of an allowance for low
grade mineralisation in the Base Case pit in the Upside Sensitivity
Case would be expected to provide a large benefit to the underlying
value of the project. The detailed sensitivity analysis carried out
for this case included incorporating the complex impacts of mill
feed tonnage, feed grade, operating costs and capital cost on the
return from the project. This sensitivity analysis indicated that
the project NPV could be expected to increase by approximately
US$100M should this sensitivity case be realised.
Project Development Timeline
Along with the previously outlined re-estimation of the mineral
resources and update of the project economics, the development
timeline for the project includes a number of key milestones. These
milestones are outlined in Table 9.
Table 9 - Project Development Timeline Milestones
----------------------------------------------------------------------------
Project Milestone Timing
----------------------------------------------------------------------------
Submit Environmental Scoping Study and Terms of
Reference for Approval December 2011
Update Mineral Resources and PEA Beginning 2Q12
Definitive metallurgical test work complete End 2Q12
Various options studies completed End 2Q12
Complete environmental baseline studies Mid 2012
Complete in-fill drilling on Sleeping Giant zone 4Q12
Submit EIS and EMP for Approval 4Q12
Conditional Off-Take in Place 4Q12
Complete Feasibility Study End 2012
Update Mineral Resource, Prepare Mining Reserve and
Technical Report 1Q13
Project Commitment by CNI 1Q13
Front End Engineering Design 2Q13
Mining Licence and Mine Development Agreement 3Q13
Financing and Production Commitment 3Q13
Commence Construction on Site (end of Wet Season) 2Q14
Commence Commissioning 2Q15
First Production and Shipment 3Q15
----------------------------------------------------------------------------
It is worth noting that the critical path on the current
construction schedule is the wet season in 2013/14 and as such
there exists a certain degree of latitude in the development
program and the timeline for permitting, design and procurement
activities.
Qualified Persons
The PEA summarized here for the Ntaka Hill Nickel project will
be incorporated into an NI 43-101 compliant Technical Report to be
available on SEDAR and CNI's website within 45 days of the date of
this news release.
The Company is not aware of any environmental, permitting,
legal, title, taxation, socio-political, marketing or other issue
that might materially affect this estimate of Mineral Resources.
The projections, forecasts and estimates presented in the PEA
constitute forward-looking statements, and readers are urged not to
place undue reliance on such statements. Additional cautionary and
forward-looking statement information is provided at the end of
this press release.
The Qualified Persons for the purpose of National Instrument
43-101 "Standards of Disclosure for Mineral Projects" for the PEA
are shown in Table 10.
Table 10 - Qualified Persons
----------------------------------------------------------------------------
Section Company Qualified Person
----------------------------------------------------------------------------
Mineral Resources RPA Chester Moore, P. Geo.
Mining and Mine Capital and
Operating Costs RPA Marc Lavigne, Ing.
Metallurgy, flowsheet design,
performance predictions Mineralurgy Peter Munro, FAusIMM
Process plant and infrastructure Christopher Waller,
operating/capital costs Lycopodium MAusIMM(CP)
Concentrate marketing and freight RPA Jason Cox, P.Eng
Financial modelling and general
aspects RPA Jason Cox, P.Eng
----------------------------------------------------------------------------
All qualified persons have reviewed this press release and
consented to the inclusion of the data in the form and context in
which it appears.
About Continental Nickel Limited
Continental is focused on the exploration, discovery and
development of nickel sulphide deposits in geologically
prospective, but under-explored regions globally. The Company's key
asset is its 75% interest in its Nachingwea property in Tanzania,
where Mineral Resources (Measured and Indicated) have been
estimated at 60,900 tonnes of contained nickel, and an additional
131,000 tonnes of contained nickel in Inferred Mineral Resources
(CNI press release April 15, 2011). The project is a 75:25
exploration joint venture between the Company and IMX Resources
Limited.
The Company also has an option to joint venture on the St.
Stephen project in New Brunswick, Canada where the 2010 diamond
drill program discovered new Ni-Cu sulphide zones.
As at the date of this release, the Company has 42,713,508
common shares issued and outstanding (51,031,914 on a fully-diluted
basis) and trades on the TSX Venture Exchange under the symbol CNI.
The Company remains well funded with over C$13.6 million in the
treasury as at June 30, 2011.
On behalf of Continental Nickel Limited
Dave Massola, President and Chief Executive Officer
CAUTIONARY STATEMENT: This News Release includes certain
"forward-looking statements". All statements other than statements
of historical fact included in this release including, without
limitation, statements regarding potential mineralization,
potential or estimated metal recoveries, resources and reserves,
exploration results, future plans and objectives of Continental
Nickel Limited, is forward-looking information that involves
various risks and uncertainties. There can be no assurance that
such information will prove to be accurate and actual results and
future events could differ materially from those anticipated in
such information. Important factors that could cause actual results
to differ materially from Continental Nickel Limited's expectations
are the risks detailed herein and from time to time in the filings
made by Continental Nickel Limited with securities regulators.
The TSX Venture Exchange does not accept responsibility for the
adequacy or accuracy of this release. No stock exchange, securities
commission or other regulatory authority has approved or
disapproved the information contained herein.
Contacts: Continental Nickel Limited Dave Massola President and
Chief Executive Officer (905) 815-0533 (905) 815-0532
(FAX)info@continentalnickel.comwww.continentalnickel.com
Continental Nickel Limited Stewart Watkins Study Manager - Ntaka
Hill Nickel Project +61 403 242 954
Continental Nickel Limited (TSXV:CNI)
Historical Stock Chart
From Jun 2024 to Jul 2024
Continental Nickel Limited (TSXV:CNI)
Historical Stock Chart
From Jul 2023 to Jul 2024