22 August 2024
Petro Matad Limited
("Petro
Matad" or the "Company")
Operational Update
Petro Matad Limited ("Petro Matad" or
"the Company"), the AIM quoted Mongolian oil company, provides the
following operational update.
Highlights
·
The Heron-1 oil discovery well has been
re-entered, stimulated and completed for production in a trouble
free operation.
· Neighbouring
operator PetroChina has provided oil storage tanks that will
complete the surface configuration for the production well site
facilities.
·
DQE Drilling has been approved as the winning
tenderer for the 2024 drilling programme and the rig to drill
Heron-2 is expected to start mobilisation by the end of August with
spud anticipated in mid-September. The smaller rig for Gobi Bear-1
well is expected to mobilise by mid-September and spud before
month's end.
Heron-1 reservoir stimulation
and down-hole completion
Work on the Heron-1 discovery well
has been completed with the down-hole pump installed ready for
production following a successful reservoir stimulation programme.
The well was found to be in good condition and the perforated zone
from 2834m to 2846m in the Lower Tsagaanstav Formation from which
the well flowed at 821 bopd on test was successfully isolated and
hydraulically stimulated. Pressure responses observed during the
stimulation were consistent with a successful operation and oil was
observed during the subsequent recovery of the stimulation fluid.
All completion equipment has been demobilised and the well site
prepared for the installation of production facilities.
Surface equipment
installation and preparations for production
Already purchased production
facilities are ready to be installed and neighbouring operator
PetroChina has provided spare oil storage tanks at nominal cost
which are now being integrity tested and which will complete the
production site configuration. It is planned to install and
commission the surface facilities during the current operational
window and the approval process for the construction permit
required for installation of the facilities is at an advanced
stage.
Discussions with PetroChina and
industry regulator, the Mineral Resources and Petroleum Authority
of Mongolia (MRPAM), on processing, transport and sales of Block XX
production are continuing. The sharing of facilities is covered
under an MoU signed with PetroChina in 2021 and is fully supported
by MRPAM.
Preparations for the 2024
drilling programme
The contract for the drilling of two
wells in the Block XX Exploitation License area has been agreed
with PetroChina's drilling subsidiary DQE Drilling and approved by
MRPAM. Mobilisation of the rig to drill the Heron-2 well is planned
to begin before the end of August with well spud expected by
mid-September. Heron-2 will be drilled to a total depth of c.2,900m
and the anticipated timing will allow for a full evaluation of the
well results, flow testing and completion within the current
operational window.
A smaller rig for the high impact,
low cost Gobi Bear-1 exploration well is expected to mobilise to
site in the first half of September and to spud before month's end.
The planned total depth of 1,800m should be reached in good time to
allow for logging and, if merited, testing before the normal winter
operational shutdown in late November.
Mike
Buck, CEO of Petro Matad, said:
"With the Heron-1 down-hole
completion now ready for production startup, the well site has been
prepared for the installation of the surface production facilities.
We are pleased to have concluded our negotiations with DQE and look
forward to continuing to work with them on the 2024 drilling
programme.
The team is now working at pace to
spud Heron-2 in mid-September and to secure the required
construction permits for Heron-1."
Further updates will be provided as
the 2024 work programme progresses.
- Ends -
Further
information please contact:
Petro Matad
Limited
|
|
Mike Buck, CEO
|
+976 7014 1099 / +976 7575 1099
|
|
|
Shore Capital
(Nominated Adviser and Broker)
|
Toby Gibbs
Rachel Goldstein
|
+44 (0) 20 7408 4090
|
Zeus (Joint
Broker)
Simon Johnson
Louisa Waddell
|
+44 (0) 20 3829 5000
|
FTI Consulting
(Communications Advisory Firm)
|
|
Ben Brewerton
Christopher Laing
Catrin Trudgill
|
+44 (0) 20 3727 1000
|
Technical information in this news
release has been reviewed by the Company's Technical Manager, Mr.
Jerry Smart. He has over 40 years of industry experience in oil and
gas exploration and production with LASMO, Eni, Salamander Energy
and Ophir Energy. He holds a B.Sc. in Geology from King's College,
London.
About Petro Matad
Petro Matad is the parent company of
a group focused on oil exploration, as well as future development
and production in Mongolia. Currently, Petro Matad holds 100%
working interest and the operatorship of the Matad Block XX
Production Sharing Contract with the government of Mongolia. Block
XX has an area of 214 square kilometres in the far eastern part of
the country.
Petro Matad Limited is incorporated
in the Isle of Man under company number 1483V. Its registered
office is at Victory House, Prospect Hill, Douglas, Isle of Man,
IM1 1EQ.