26 January 2017
KAZ MINERALS GROUP Production Report for 12 months and THE
fourth QUARTER Ended 31 December 2016
l Full year copper guidance met and by-product guidance exceeded
in 2016
l Copper cathode equivalent production(1) of 140 kt (guidance
135-145 kt)
-- Copper output growth of 73% year-on-year (FY 2015: 81 kt)
-- New projects Bozshakol and Aktogay contributed 63 kt of new
copper cathode equivalent production in 2016
-- Q4 copper cathode equivalent production of 43 kt (Q3 2016: 45
kt)
l Bozshakol copper cathode equivalent output of 20 kt in Q4 (Q3
2016: 17 kt)
-- Ramp up on track, ore throughput averaged above 75% in Q4
-- 50 kt of copper in concentrate and 45 kt copper cathode
equivalent output in 2016
l Aktogay oxide Q4 output of 6 kt, full year copper cathode
output of 18 kt
-- 6 kt of copper cathode output in Q4 2016 (Q3 2016: 7 kt),
despite colder weather
-- Testing in progress at main sulphide concentrator, first
copper production expected in Q1 2017
l East Region and Bozymchak Q4 copper cathode equivalent output
of 17 kt (Q3 2016: 21 kt)
-- Q3 output benefited from a release of work in progress
l By-product output exceeds full year guidance ranges
-- Stronger than anticipated by-product grades in the East
Region in Q4 2016
-- Bozymchak operated at design capacity throughout 2016
-- Bozshakol 2016 gold bar equivalent output of 60 koz supported
by elevated gold grades
(1) The Group's finished goods "equivalent" production includes
both finished metals produced and the finished metal equivalent of
concentrate sold in the period.
Oleg Novachuk, Chief Executive, said: "I am pleased that we have
achieved our copper and by-product guidance for 2016, a 73%
increase in copper output on the prior year, as we successfully
ramped up Bozshakol and the Aktogay oxide plant. Operating costs at
Bozshakol have temporarily benefited from lower than anticipated
maintenance requirements during the ramp up period, and full year
gross cash costs are expected to be in the region of 20% below the
bottom of the previously guided range of 140-160 USc/lb. Our growth
will continue in 2017 as Bozshakol reaches capacity and we commence
production from sulphide ore at Aktogay."
For further information please contact:
KAZ Minerals
PLC
==================== ========================== =================
Chris Bucknall Investor Relations, Tel: +44 20 7901
London 7882
Investor Relations, Tel: +44 20 7901
Anna Mallere London 7814
Maksut Zhapabayev Corporate Communications, Tel: +7 727 244
Almaty 03 53
==================== ========================== =================
Instinctif Partners
==================== ========================== =================
Tel: +44 20 7457
David Simonson 2020
==================== ========================== =================
REGISTERED OFFICE
6th Floor, Cardinal Place, 100 Victoria Street, London SW1E 5JL,
United Kingdom.
NOTES TO EDITORS
KAZ Minerals PLC ("KAZ Minerals" or "the Group") is a high
growth copper company focused on large scale, low cost, open pit
mining in Kazakhstan. It operates three mines and three
concentrators in the East Region of Kazakhstan, the Bozymchak
copper-gold mine in Kyrgyzstan, the Bozshakol open pit copper mine
in the Pavlodar region of Kazakhstan and the Aktogay open pit
copper mine in the East Region of Kazakhstan. In 2016, total copper
cathode equivalent output was 140 kt with by-products of 75 kt of
zinc in concentrate, 120 koz of gold bar equivalent and 3,103 koz
of silver bar equivalent.
The Group's major growth projects at Bozshakol and Aktogay are
expected to deliver one of the highest growth rates in the industry
and transform KAZ Minerals into a company dominated by world class,
open pit copper mines.
Bozshakol is a first quartile asset on the global cost curve and
will have an annual ore processing capacity of 30 million tonnes
when fully ramped up, with a mine life of 40 years at a copper
grade of 0.36%. The mine and processing facilities will produce 100
kt of copper cathode equivalent and 120 koz of gold in concentrate
per year over the first 10 years of operations.
Aktogay is a large scale, open pit mine similar to Bozshakol,
with a mine life of more than 50 years and average copper grades of
0.37% (oxide) and 0.33% (sulphide). Aktogay commenced production of
copper cathode from oxide ore in December 2015 and copper in
concentrate production from sulphide ore is expected to begin in
the first quarter of 2017. The sulphide concentrator will have an
annual ore processing capacity of 25 million tonnes when fully
ramped up. Aktogay is competitively positioned on the global cost
curve and will produce an average of 90 kt of copper cathode
equivalent from sulphide ore and 15 kt of copper cathode from oxide
ore per year over the first 10 years of operations.
KAZ Minerals is listed on the London Stock Exchange, the
Kazakhstan Stock Exchange and the Hong Kong Stock Exchange and
employs around 13,000 people, principally in Kazakhstan.
This announcement contains inside information.
GROUP PRODUCTION SUMMARY
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
========================================================= ======= ======= ======= ======= ======
Ore extraction kt 49,022 14,537 13,258 13,665 8,040
============================== ========================== ======= ======= ======= ======= ======
Average copper
grade % 0.66 1.10 0.67 0.67 0.88
================================ ======================== ======= ======= ======= ======= ======
Copper in
ore mined kt 324.2 160.3 88.6 91.0 70.7
================================= ======================= ======= ======= ======= ======= ======
Copper in concentrate kt 131.3 89.4 40.8 37.2 23.0
================================== ====================== ======= ======= ======= ======= ======
Copper cathode
equivalent (1) kt 140.3 81.1 43.2 44.5 22.7
=================================== ===================== ======= ======= ======= ======= ======
Bozshakol kt 44.8 - 20.1 16.9 -
=================================== ===================== ======= ======= ======= ======= ======
Aktogay kt 18.1 0.4 6.1 6.6 0.4
=================================== ===================== ======= ======= ======= ======= ======
East Region & Bozymchak kt 77.4 80.7 17.0 21.0 22.3
=================================== ===================== ======= ======= ======= ======= ======
Zinc in concentrate kt 75.4 94.3 19.2 16.6 21.0
=================================== ===================== ======= ======= ======= ======= ======
Gold bar equivalent
(1) koz 119.7 34.6 39.7 40.9 6.4
=================================== ===================== ======= ======= ======= ======= ======
Silver bar equivalent
(1) koz 3,103 3,135 867 806 686
=================================== ===================== ======= ======= ======= ======= ======
(1) Includes finished metals produced and the finished metal
equivalent of concentrate sold in the period.
Copper cathode equivalent output in the fourth quarter of 43.2
kt resulted in full year production of 140.3 kt, in line with
guidance of 135-145 kt and representing a 73% increase from 2015.
The production growth from 2015 reflects the ramp up of the
sulphide concentrator at Bozshakol which added 44.8 kt of new
copper cathode equivalent in 2016 and the oxide operations at
Aktogay which contributed 18.1 kt of cathode.
Total ore extraction in 2016 grew to 49.0 million tonnes from
14.5 million tonnes in 2015, as mining operations at Aktogay and
Bozshakol stepped up to support processing activities at both
sites. The average copper grade reduced in 2016 compared to 2015,
reflecting the incremental ore extraction from the new lower grade
open pit mines at Bozshakol and Aktogay.
In Q4 2016, copper cathode equivalent production decreased by
1.3 kt or 3% compared to Q3 2016, despite higher underlying copper
in concentrate output, as the East Region's Q3 figures benefited
from a release of work in progress at the Balkhash smelter. Copper
output also decreased by 0.5 kt at the Aktogay oxide operations in
Q4, as expected during the winter period. The combined 4.5 kt
reduction in output from the East Region, Bozymchak and Aktogay
mines was partially offset by continued progress in the ramp up of
Bozshakol, where copper cathode equivalent production increased by
3.2 kt or 19% compared to Q3 2016.
Ore extraction reduced by 407 kt in Q4 versus Q3 2016 due to
planned lower extraction at Aktogay in line with heap leaching
requirements, with the Group copper grade remaining stable at
0.67%.
Following strong by-product output in Q4 2016, in particular as
the Artemyevsky mine reported higher than anticipated by-product
content and Yubileyno-Snegirikhinsky continued mining until the end
of December, the Group's zinc, gold and silver output in 2016 met
or exceeded the top end of the Group's guidance ranges for the
year.
The Yubileyno-Snegirikhinsky mine ceased operations at the end
of 2016, having contributed production of 5.5 kt of copper in
concentrate, 0.8 koz of gold in concentrate, 53.0 koz of silver in
concentrate and 0.5 kt of zinc in concentrate during the year.
BOZSHAKOL
Mining
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
=== ======================================== ======= ====== ====== ====== ======
Ore extraction kt 28,272 7,099 8,790 8,466 6,070
=========================== ================ ======= ====== ====== ====== ======
Average copper
grade % 0.58 0.69 0.58 0.62 0.69
=========================== ================ ======= ====== ====== ====== ======
Copper in
ore mined kt 164.6 48.7 51.0 52.1 41.8
========================= ================== ======= ====== ====== ====== ======
Average gold
grade g/t 0.30 0.31 0.29 0.32 0.32
========================== ================= ======= ====== ====== ====== ======
Gold in ore mined koz 270.1 70.0 81.5 88.1 62.8
========================== ================= ======= ====== ====== ====== ======
Average silver
grade g/t 1.5 2.1 1.4 1.5 2.0
========================== ================= ======= ====== ====== ====== ======
Silver in ore
mined koz 1,361 469 388 405 381
========================== ================= ======= ====== ====== ====== ======
Average molybdenum
grade(1) % 0.005 0.005 0.005 0.005 0.005
========================== ================= ======= ====== ====== ====== ======
Molybdenum in
ore mined(1) t 714 25 246 210 25
========================== ================= ======= ====== ====== ====== ======
(1) Molybdenum mined in sulphide ore. Production of molybdenum
concentrate has not yet commenced.
Ore output continued to increase at Bozshakol during Q4 2016 to
support the ramp up of operations. The average copper grade of
0.58% was below the previous quarter (0.62%) as lower grade clay
areas were mined for processing during the commissioning phase of
the clay plant, which began on 29 September 2016. Total ore mined
in Q4 of 8,790 kt consisted of 4,493 kt of sulphide ore with a
grade of 0.58% and 4,297 kt of clay ore also with a grade of 0.58%.
As at 31 December 2016, a total of 21,266 kt of clay ore was
stockpiled at Bozshakol with an average copper grade of 0.63%.
Ore extraction in 2016 rose to 28.3 million tonnes from 7.1
million tonnes in 2015, and copper in ore mined to 164.6 kt from
48.7 kt, as mining operations commenced at Bozshakol in May 2015
and increased in 2016 to support the ramp up of the sulphide
concentrator. The pace of mining activity is now approaching the
level required to supply the maximum ore processing capacity at
Bozshakol of 30 million tonnes per annum.
The grade of gold remained high at 0.29 g/t in Q4 2016 compared
to the measured and indicated resource grade of 0.14 g/t,
supporting gold production at Bozshakol in 2016.
Processing
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
================================= ====== ====== ====== ====== ======
Copper in concentrate kt 50.3 - 22.2 17.5 -
=========================== ===== ====== ====== ====== ====== ======
Copper cathode
equivalent(1) kt 44.8 - 20.1 16.9 -
=========================== ===== ====== ====== ====== ====== ======
Gold in concentrate koz 68.0 - 28.4 26.6 -
=========================== ===== ====== ====== ====== ====== ======
Gold bar equivalent(1) koz 59.6 - 25.6 24.9 -
=========================== ===== ====== ====== ====== ====== ======
Silver in concentrate koz 338.0 - 162.3 110.8 -
=========================== ===== ====== ====== ====== ====== ======
Silver bar equivalent(1) koz 285.8 - 139.3 102.6 -
=========================== ===== ====== ====== ====== ====== ======
(1) The finished metal equivalent of concentrate sold in the
period.
The Bozshakol sulphide concentrator produced 22.2 kt of copper
in concentrate in Q4, a 27% increase compared to the previous
quarter. Average mill throughput in Q4 was over 75%, with higher
levels achieved in October followed by reduced throughput in
November due to shutdowns for planned commissioning activities.
Total production from the main sulphide concentrator in 2016 was
50.1 kt of copper in concentrate and 44.8 kt of copper cathode
equivalent, in line with the bottom end of the full year guidance
range of 45-55 kt.
Gold in concentrate output increased by 1.8 koz or 7% quarter on
quarter as the higher quantity of ore processed was partially
offset by a slightly lower ore grade feed. Bozshakol produced 59.6
koz of gold bar equivalent in 2016, at the top end of full year
production guidance of 50-60 koz.
Silver in concentrate production increased by 51.5 koz or 46% in
Q4 compared to Q3 2016, with silver bar equivalent output also
increasing by 36.7 koz or 36% to 139.3 koz.
On 29 September 2016 commissioning works commenced at the
Bozshakol clay plant, with 0.2 kt of copper in concentrate produced
during initial testing in Q4. The clay plant will continue its ramp
up in 2017.
Subject to smelting capacity availability at Balkhash in 2017, a
small quantity of concentrate produced at Bozshakol may be sent for
toll processing in Kazakhstan on the same terms as East Region
material, with the Group benefiting from savings on transport and
logistics costs when compared to concentrate sales to China.
As previously announced, the project was declared commercial in
October 2016. In the pre-commercial period from January to October,
Bozshakol produced 31.1 kt of copper cathode equivalent, 42.9 koz
of gold bar equivalent and 188 koz of silver bar equivalent.
AKTOGAY
Mining and processing
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
====================== ======== ======= ====== ====== ====== ======
Ore extraction kt 16,086 3,003 3,344 4,063 878
===================== ========= ======= ====== ====== ====== ======
Copper grade % 0.41 0.37 0.43 0.38 0.36
===================== ========= ======= ====== ====== ====== ======
Copper in ore mined kt 65.7 11.0 14.5 15.5 3.1
======================= ======= ======= ====== ====== ====== ======
Copper cathode kt 18.1 0.4 6.1 6.6 0.4
======================= ======= ======= ====== ====== ====== ======
Aktogay ore output reduced by 719 kt or 18% in Q4 as lower
volumes of ore were required to supply the oxide heap leach pads
and as mining activities were focused on exposing sulphide
material. A small volume of sulphide ore (97 kt) was mined in
December, with significant sulphide material now exposed and ready
to supply the concentrator. 3,247 kt of oxide ore with a copper
grade of 0.43% was mined in Q4 compared to 4,063 kt in Q3 at a
grade of 0.38%.
The quantity of copper in ore mined reduced slightly due to the
lower level of ore extracted in Q4 compared to Q3 2016, falling by
1 kt or 6% to 14.5 kt.
In the prior year, mining activies were focused on preparatory
works and obtaining the initial oxide ore for placement on the
leach pads. Mining activities stepped up in 2016 to support
processing, with 16.1 million tonnes of ore extracted in 2016,
compared to 3.0 million tonnes in 2015.
Copper cathode production from oxide ore in Q4 reduced compared
to Q3 due to seasonally lower temperatures, falling by 0.5 kt or 8%
to 6.1 kt. The successful ramp up of the leaching and SX/EW
operations during 2016 resulted in full year output of 18.1 kt for
2016.
The Aktogay sulphide concentrator commenced commissioning on 6
December 2016 and is currently undergoing testing. The first
production of saleable copper concentrate is expected in Q1
2017.
EAST REGION & BOZYMCHAK
Copper mining
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
=============================== ====== ====== ====== ====== ======
Ore extraction kt 4,664 4,435 1,124 1,136 1,092
========================== ==== ====== ====== ====== ====== ======
Orlovsky kt 1,260 1,417 287 294 355
========================== ==== ====== ====== ====== ====== ======
% 3.67 3.69 3.89 3.87 4.20
=============================== ====== ====== ====== ====== ======
Artemyevsky kt 1,309 1,289 323 340 316
========================== ==== ====== ====== ====== ====== ======
% 1.48 1.62 1.34 1.47 1.43
=============================== ====== ====== ====== ====== ======
Irtyshsky kt 632 655 159 157 166
========================== ==== ====== ====== ====== ====== ======
% 1.54 1.67 1.52 1.59 1.64
=============================== ====== ====== ====== ====== ======
Yubileyno-Snegirikhinsky kt 528 625 136 129 142
========================== ==== ====== ====== ====== ====== ======
% 1.98 1.94 2.44 2.05 1.83
=============================== ====== ====== ====== ====== ======
Bozymchak kt 935 449 219 216 113
========================== ==== ====== ====== ====== ====== ======
% 0.86 0.97 0.86 0.87 0.98
=============================== ====== ====== ====== ====== ======
Average grade % 2.01 2.27 2.06 2.06 2.36
Copper in ore
mined kt 93.9 100.6 23.1 23.4 25.8
========================== ==== ====== ====== ====== ====== ======
Ore extraction in the East Region and Bozymchak in Q4 2016 was
in line with the previous quarter. In 2016 ore output increased
compared to 2015 as Bozymchak operated at full capacity throughout
the year, more than offsetting lower output from the East Region
mines.
Copper in ore mined in Q4 was stable compared to Q3 2016, with
the lower grade at Artemyevsky offset by an increase in copper
content at Yubileyno-Snegirikhinsky. Copper in ore mined decreased
in 2016 by 6.7 kt or 7% compared to the prior year, due to lower
copper grades at all mines other than Yubileyno-Snegirikhinsky and
reduced ore output from Orlovsky.
At the Orlovksy mine the introduction of a six day week in the
second half of the year to allow for essential maintenance work to
a ventilation shaft resulted in a 157 kt or 11% decrease in ore
extraction to 1,260 kt for the full year. The works will continue
in 2017 and into 2018.
The Yubileyno-Snegirikhinsky mine was expected to cease
operations in the second half of 2016 and mining activities ended
in December 2016 with all mineral reserves fully exploited after 15
years. Ore stockpiled at the site will be processed in the first
half of 2017. 118 employees have either been redeployed within the
Group or accepted redundancy, whilst 40 employees will remain on
site to supervise the process of decommissioning and
rehabilitation.
Copper processing
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
=== ============================================= ====== ====== ====== ====== ======
Copper in concentrate kt 81.0 89.4 18.6 19.7 23.0
=================================== ============= ====== ====== ====== ====== ======
Orlovsky concentrator kt 41.7 47.2 10.4 9.9 13.5
=================================== ============= ====== ====== ====== ====== ======
Nikolayevsky concentrator kt 22.5 29.0 4.2 5.6 5.9
=================================== ============= ====== ====== ====== ====== ======
Belousovsky concentrator kt 8.6 10.1 2.1 2.1 2.6
=================================== ============= ====== ====== ====== ====== ======
Bozymchak concentrator kt 8.2 3.1 1.9 2.1 1.0
=================================== ============= ====== ====== ====== ====== ======
Copper cathode equivalent(1) kt 77.4 80.7 17.0 21.0 22.3
==================================== ============ ====== ====== ====== ====== ======
(1) Includes finished metal produced and the finished metal
equivalent of concentrate sold in the period.
Copper in concentrate output reduced in Q4 2016 by 1.1 kt or 6%
compared to Q3 due to lower grades and restricted ore deliveries to
the Nikolayevsky concentrator due to poor weather conditions and
road repairs, partially offset by higher production from
Orlovsky.
In 2016 copper in concentrate declined by 8.4 kt or 9% compared
to the prior year as reduced output from the two largest
concentrators, Orlovsky and Nikolayevsky, more than offset higher
production from the optimised Bozymchak. Orlovsky processed a lower
quantity of ore as the mine moved to a six day week in the second
half of the year, whilst a lower copper grade from Artemyevsky
reduced the feed grade at the Nikolayevsky concentrator.
Copper cathode equivalent output in Q4 decreased by 4 kt or 19%
compared to Q3 2016 as the previous quarter benefited from a large
release of work in progress at the Balkhash smelter and due to 1.1
kt lower copper in concentrate production.
2016 copper cathode equivalent production reduced by 3.3 kt or
4% year on year, mainly due to the lower copper in concentrate
output. Maintenance work at the Balkhash smelter in Q4 2016
resulted in some work in progress being carried forward into
2017.
Full year copper cathode equivalent production of 77.4 kt
includes 0.9 kt recognised following the sale of copper concentrate
produced at Bozymchak in 2015 to a third party processor in Q1 2016
and 1.7 kt of material that was sold as copper concentrate from the
East Region to a third party processor in China in the second half
of 2016. Limited volumes of East Region concentrate may continue to
be sold to China in 2017.
Zinc
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
======================= ==== ====== ====== ====== ====== ======
Zinc bearing
ore mined kt 3,729 3,986 905 920 979
====================== ===== ====== ====== ====== ====== ======
Grade % 2.98 3.23 3.38 2.75 3.09
====================== ===== ====== ====== ====== ====== ======
Zinc in ore mined kt 111.3 128.9 30.6 25.3 30.2
====================== ===== ====== ====== ====== ====== ======
Zinc in concentrate kt 75.4 94.3 19.2 16.6 21.0
===================== ====== ====== ====== ====== ====== ======
Zinc in ore mined increased by 5.3 kt or 21% in Q4 compared to
Q3 2016 due to higher zinc grades across all East Region mines
(3.38% from 2.75% in Q3). The zinc grade at the
Yubileyno-Snegirikhinsky mine was 3.93% in its last quarter of
operations, compared to 1.22% in the previous quarter.
Zinc in concentrate output increased by 2.6 kt or 16% in Q4 2016
versus the previous quarter, driven by the higher grades, but fell
by 18.9 kt or 20% in 2016 compared to the prior year as the volume
of ore mined and grade in the East Region reduced in line with
expectations.
Full year zinc in ore mined reduced by 17.6 kt or 14% as both
ore output and grade were lower year on year. The largest zinc
producing mine, Orlovsky, moved to a six day week in the second
half of the year for maintenance works and the zinc grade in the
second largest mine, Artemyevsky, reduced to 2.10% from 2.96% in
2015.
Gold
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
========================= ===== ====== ====== ====== ====== ======
Gold bearing
ore mined kt 4,664 4,435 1,124 1,136 1,092
======================== ====== ====== ====== ====== ====== ======
Grade g/t 0.74 0.75 0.72 0.68 0.73
======================== ====== ====== ====== ====== ====== ======
Gold in ore mined koz 111.2 106.6 26.1 25.0 25.7
======================== ====== ====== ====== ====== ====== ======
Gold in concentrate koz 67.6 42.1 16.5 16.3 11.5
======================== ====== ====== ====== ====== ====== ======
Gold bar equivalent(1) koz 60.1 34.6 14.1 16.0 6.4
======================== ====== ====== ====== ====== ====== ======
(1) Includes finished metal produced and the finished metal
equivalent of concentrate sold in the period.
Gold bearing ore output in Q4 2016 of 1,124 kt was stable
compared to the previous quarter. However, the average gold grade
increased from 0.68 g/t in Q3 to 0.72 g/t in Q4 due to an almost
doubling of gold content at Artemyevsky, from 0.27 g/t to 0.50 g/t,
as mining moved through a by-product rich area. Gold in concentrate
output was stable from Q3 into Q4 2016, increasing by 1% to 16.5
koz.
Gold bar equivalent output in Q4 of 14.1 koz represented a
decrease of 1.9 koz or 12% compared to Q3, due to a small build up
of work in progress at the Balkhash smelter whereas Q3 2016 had
benefited from a release of work in progress.
In 2016 gold bearing ore output increased by 229 kt or 5%
compared to 2015, to 4,664 kt. The ramp up of mining at Bozymchak
added 486 kt of additional gold bearing ore, more than offsetting
the reduction in output in the East Region. The gold grade in 2016
was stable compared to 2015, but gold in concentrate output
increased significantly, by 25.5 koz or 61%, reflecting the
operation of the Bozymchak concentrator at its design capacity
throughout 2016. Gold bar equivalent output for the full year
consequently increased by 25.5 kt or 74% to 60.1 koz, ahead of full
year guidance of 45-55 koz.
Silver
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
============================ ===== ====== ====== ====== ====== ======
Silver bearing
ore mined kt 4,664 4,435 1,124 1,136 1,092
=========================== ====== ====== ====== ====== ====== ======
Grade g/t 37.8 43.3 41.0 34.2 41.6
=========================== ====== ====== ====== ====== ====== ======
Silver in ore
mined koz 5,660 6,168 1,483 1,248 1,460
=========================== ====== ====== ====== ====== ====== ======
Silver in concentrate koz 3,224 3,229 922 680 801
========================== ======= ====== ====== ====== ====== ======
Silver bar equivalent(1) koz 2,817 3,135 728 703 686
=========================== ====== ====== ====== ====== ====== ======
(1) Includes finished metal produced and the finished metal
equivalent of concentrate sold in the period.
Silver grades increased in Q4 2016 to 41.0 g/t from 34.2 g/t in
Q3 as Artemyevsky benefited from the mining of a by-product rich
area, with silver content rising from 24.6 g/t in Q3 to 56.1 g/t in
Q4 2016. Higher grades drove growth in silver in ore mined of 235
koz, a 19% increase on Q3 2016. Silver in concentrate production
benefited from the increase in silver in ore mined, but silver bar
equivalent output only increased by 4% to 728 koz in Q4 due to a
build up of work in progress at the Balkhash precious metal
smelter, compared to a release of work in progress in Q3 2016.
Silver in ore mined reduced by 8% in 2016 compared to 2015, but
silver in concentrate production remained stable as concentrator
recovery rates improved. Silver bar equivalent output in 2016 of
2,817 koz represents a decrease of 10% compared to the prior year,
but exceeded guidance for the East Region and Bozymchak of
2,250-2,500 koz. Silver grades were expected to fall in the East
Region mines in 2016, but were stronger than anticipated at
Artemyevsky and Irtyshsky (which also assisted concentrator
recovery rates) and the Yubileyno-Snegirikhinsky mine was able to
sustain operations until December 2016, when mining operations
ceased.
APPIX - GROUP PRODUCTION SUMMARY
Copper processing
12m 12m Q4 Q3 Q4
East Region 2016 2015 2016 2016 2015
=================================== ======= ====== ====== ====== ======
Copper concentrate kt 366.4 441.4 86.3 84.5 117.3
============================= ==== ======= ====== ====== ====== ======
Copper in concentrate kt 72.8 86.3 16.7 17.6 22.0
============================= ==== ======= ====== ====== ====== ======
Bozymchak
=================================== ======= ====== ====== ====== ======
Copper concentrate kt 33.9 13.2 8.2 9.0 3.9
============================= ==== ======= ====== ====== ====== ======
Copper in concentrate kt 8.2 3.1 1.9 2.1 1.0
============================= ==== ======= ====== ====== ====== ======
Bozshakol
=================================== ======= ====== ====== ====== ======
Copper concentrate kt 214.4 - 97.1 72.1 -
============================= ==== ======= ====== ====== ====== ======
Copper in concentrate kt 50.3 - 22.2 17.5 -
============================= ==== ======= ====== ====== ====== ======
Total copper concentrate kt 614.7 454.6 191.6 165.6 121.2
============================= ==== ======= ====== ====== ====== ======
Total copper in concentrate kt 131.3 89.4 40.8 37.2 23.0
============================= ==== ======= ====== ====== ====== ======
Aktogay oxide
=================================== ======= ====== ====== ====== ======
Ore to leach pads kt 15,989 3,003 3,247 4,063 878
============================= ==== ======= ====== ====== ====== ======
Grade % 0.41 0.37 0.43 0.38 0.36
============================= ==== ======= ====== ====== ====== ======
Copper cathode kt 92.9 81.1 22.9 26.1 22.7
============================= ==== ======= ====== ====== ====== ======
Copper cathode equivalent kt 140.3 81.1 43.2 44.5 22.7
============================= ==== ======= ====== ====== ====== ======
East Region(1) kt 70.2 78.5 15.7 18.9 21.8
============================= ==== ======= ====== ====== ====== ======
Bozymchak(1) kt 7.2 2.2 1.3 2.1 0.5
============================= ==== ======= ====== ====== ====== ======
Aktogay oxide kt 18.1 0.4 6.1 6.6 0.4
============================= ==== ======= ====== ====== ====== ======
Bozshakol(1) kt 44.8 - 20.1 16.9 -
============================= ==== ======= ====== ====== ====== ======
(1) Includes finished metal produced and the finished metal
equivalent of concentrate sold in the period.
Zinc
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
================================== ====== ====== ====== ====== ======
Zinc bearing ore
mined kt 3,729 3,986 905 920 979
========================== ======= ====== ====== ====== ====== ======
grade
Orlovsky (%) 4.38 4.52 4.39 4.18 5.03
========================== ======= ====== ====== ====== ====== ======
grade
Artemyevsky (%) 2.10 2.96 2.25 1.84 2.11
========================== ======= ====== ====== ====== ====== ======
grade
Irtyshsky (%) 3.12 3.13 3.39 3.33 3.06
========================== ======= ====== ====== ====== ====== ======
grade
Yubileyno-Snegirikhinsky (%) 1.68 0.98 3.93 1.22 0.43
========================== ======= ====== ====== ====== ====== ======
grade
Average (%) 2.98 3.23 3.38 2.75 3.09
========================== ======= ====== ====== ====== ====== ======
Zinc in ore mined kt 111.3 128.9 30.6 25.3 30.2
========================== ======= ====== ====== ====== ====== ======
Zinc in concentrate kt 75.4 94.3 19.2 16.6 21.0
========================== ======= ====== ====== ====== ====== ======
Gold
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
=============================== =============== ======= ======= ====== ====== ======
Gold bearing ore
mined kt 32,936 11,534 9,914 9,602 7,162
============================== ================ ======= ======= ====== ====== ======
Orlovsky grade (g/t) 1.02 1.18 0.88 1.05 1.14
========================== ==================== ======= ======= ====== ====== ======
Artemyevsky grade (g/t) 0.37 0.38 0.50 0.27 0.37
========================== ==================== ======= ======= ====== ====== ======
Irtyshsky grade (g/t) 0.29 0.28 0.32 0.29 0.29
========================== ==================== ======= ======= ====== ====== ======
grade
Yubileyno-Snegirikhinsky (g/t) 0.27 0.28 0.32 0.25 0.19
============================ ================== ======= ======= ====== ====== ======
grade
Bozymchak (g/t) 1.46 1.77 1.39 1.37 1.82
============================ ================== ======= ======= ====== ====== ======
grade
Bozshakol (g/t) 0.30 0.31 0.29 0.32 0.32
============================ ================== ======= ======= ====== ====== ======
grade
Average (g/t) 0.36 0.48 0.34 0.37 0.38
============================ ================== ======= ======= ====== ====== ======
Gold metal in
ore mined koz 381.3 176.6 107.6 113.1 88.5
============================ ================== ======= ======= ====== ====== ======
East Region koz 67.3 81.1 16.3 15.4 19.1
=========================== =================== ======= ======= ====== ====== ======
Bozymchak koz 43.9 25.5 9.8 9.6 6.6
=========================== =================== ======= ======= ====== ====== ======
Bozshakol koz 270.1 70.0 81.5 88.1 62.8
=========================== =================== ======= ======= ====== ====== ======
Gold in concentrate koz 135.6 42.1 44.9 42.9 11.5
================================ ============== ======= ======= ====== ====== ======
East Region koz 21.8 24.3 5.9 4.4 5.9
================================ ============== ======= ======= ====== ====== ======
Bozymchak koz 45.8 17.8 10.6 11.9 5.6
================================ ============== ======= ======= ====== ====== ======
Bozshakol koz 68.0 - 28.4 26.6 -
================================ ============== ======= ======= ====== ====== ======
Gold bar equivalent koz 119.7 34.6 39.7 40.9 6.4
================================= ============= ======= ======= ====== ====== ======
East Region(1) koz 21.8 22.1 4.7 5.0 3.3
============================= ================= ======= ======= ====== ====== ======
Bozymchak(1) koz 38.3 12.5 9.4 11.0 3.1
============================= ================= ======= ======= ====== ====== ======
Bozshakol(1) koz 59.6 - 25.6 24.9 -
============================= ================= ======= ======= ====== ====== ======
(1) Includes finished metal produced and the finished metal
equivalent of concentrate sold in the period.
Silver
12m 12m Q4 Q3 Q4
2016 2015 2016 2016 2015
=============================== =============== ======= ======= ====== ====== ======
Silver bearing
ore mined kt 32,936 11,534 9,914 9,602 7,162
================================ ============== ======= ======= ====== ====== ======
Orlovsky grade (g/t) 58.0 64.4 45.9 61.9 62.3
========================== ==================== ======= ======= ====== ====== ======
Artemyevsky grade (g/t) 38.9 35.1 56.1 24.6 33.5
========================== ==================== ======= ======= ====== ====== ======
grade
Irtyshsky (g/t) 53.6 62.2 59.7 52.4 59.6
============================= ================= ======= ======= ====== ====== ======
grade
Yubileyno-Snegirikhinsky (g/t) 17.5 16.4 25.3 16.5 12.3
============================= ================= ======= ======= ====== ====== ======
grade
Bozymchak (g/t) 9.5 10.0 8.8 8.8 9.2
=============================== =============== ======= ======= ====== ====== ======
grade
Bozshakol (g/t) 1.5 2.1 1.4 1.5 2.0
=============================== =============== ======= ======= ====== ====== ======
grade
Average (g/t) 6.6 17.9 5.9 5.4 8.0
=============================== =============== ======= ======= ====== ====== ======
Silver in ore
mined koz 7,021 6,637 1,871 1,653 1,841
=============================== =============== ======= ======= ====== ====== ======
East Region koz 5,376 6,024 1,421 1,187 1,427
=========================== =================== ======= ======= ====== ====== ======
Bozymchak koz 284 144 62 61 33
============================== ================ ======= ======= ====== ====== ======
Bozshakol koz 1,361 469 388 405 381
============================== ================ ======= ======= ====== ====== ======
Silver in concentrate koz 3,562 3,229 1,084 791 801
============================== ================ ======= ======= ====== ====== ======
East Region koz 2,928 3,110 862 607 765
============================== ================ ======= ======= ====== ====== ======
Bozymchak koz 296 119 60 73 36
============================== ================ ======= ======= ====== ====== ======
Bozshakol koz 338 - 162 111 -
============================== ================ ======= ======= ====== ====== ======
Silver bar equivalent koz 3,103 3,135 867 806 686
================================= ============= ======= ======= ====== ====== ======
East Region(1) koz 2,565 3,052 668 629 665
============================ ================== ======= ======= ====== ====== ======
Bozymchak(1) koz 252 83 60 74 21
============================ ================== ======= ======= ====== ====== ======
Bozshakol(1) koz 286 - 139 103 -
============================ ================== ======= ======= ====== ====== ======
(1) Includes finished metal produced and the finished metal
equivalent of concentrate sold in the period.
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCVELFLDFFBBBL
(END) Dow Jones Newswires