Moma Mine Update
25 January 2012 - 6:00PM
UK Regulatory
TIDMKMR
Kenmare Resources plc ("Kenmare" or "the Company")
25 January, 2012
Moma Mine Update
Overview
* Demand for all products robust during 2011 with strong growth in prices
* 192,400 tonnes of finished products shipped in Q4 2011, up from 188,200
tonnes in Q3
* 83% increase in revenue to US$167.5 million (unaudited) in 2011 from US$91.6
million in 2010
* 225,600 tonnes of heavy mineral concentrate produced in Q4 2011, a 15%
increase on Q3 2011
* Ilmenite and zircon production up 13% and 12% respectively in Q4 from Q3
2011
* Production expansion project progressing with delivery of critical items to
Moma
Operations
Mining operations during the fourth quarter of 2011 produced 225,600 tonnes of
Heavy Mineral Concentrate (HMC), compared with 195,700 tonnes during the third
quarter, a 15% increase. The mineral separation plant produced 166,000 tonnes
of ilmenite and 12,500 tonnes of zircon, 13% and 12% increases respectively on
the third quarter.
Total production of HMC for 2011 was 842,900 tonnes. Final products volumes
were 636,800 tonnes of ilmenite, 43,500 tonnes of zircon (including 6,200 tonnes
of a secondary zircon product produced from a zircon rejects stockpile) and
6,500 tonnes of rutile.
730,400 tonnes of finished products were shipped during 2011, compared with
712,900 during 2010. These shipments generated revenues of US$167.5 million
(unaudited) in 2011, an increase of 83% from US$91.6 million during 2010.
While production for the year was planned to be below nameplate capacity due to
interruptions in mining to facilitate the expansion, a further reduction in
mining rate was experienced due to a band of clay-rich ore in the mine path.
While the clay band was anticipated prior to mining, the characteristics were
different to clays previously mined.
Partly in response to this development, a supplementary dry mining system has
been installed and commissioned. This system can currently feed 500 tonnes of
ore per hour to the Wet Concentrator Plant (WCP) and is being ramped up to
1,000 tonnes of ore per hour. By varying its production rate, this system will
serve to enable the mining operation to keep the WCP fully supplied with a
constant amount of ore over a range of orebody conditions.
The upgraded jetty facility has now been fully commissioned and is operating
successfully, allowing ships to be loaded during a much broader range of weather
conditions.
The pre-feasibility study for a Phase III expansion of the Moma Mine and design
of facilities for the production and export of monazite are progressing and due
for completion later this year.
Phase II Expansion
The new dredge, manufactured and tested in the USA, has arrived at Moma and will
be reassembled in the coming months. All of the pontoons which form the floating
base of the new WCP have also arrived at Moma and are being put into position in
the starter mining pond.
Expansion works at the Mineral Separation Plant (MSP) are continuing, with
substantial progress on civil engineering and steelwork on both the new Wet High
Intensity Magnetic Separation (WHIMS) plant and the auxiliary ilmenite plant.
However, the EPCM contractor, E+PC, part of the Aveng Group, has experienced
delays in issuing some drawings which impacted on the start of fabrication in
some areas. Whilst the project cost has not changed significantly, this delay
has regrettably extended the scheduled completion date of the expansion project
well into the second half of this year. Every effort is being made to minimise
this delay, including the employment of extra resources by E+PC and the
appointment of a new Project Manager to Kenmare's Owner's Team.
In December 2011, Kenmare concluded the documentation and execution of an
agreement with lenders which provided that, in addition to cash already
available in the Group, up to US$65 million of operating cashflow may be applied
to expansion costs.
Marketing
The demand for all our products was robust during 2011 and prices grew strongly.
The market price for ilmenite at the start of 2011 of around US$100 per tonne
increased three to four fold throughout the year, driven by tight market
conditions. Going into 2012, Kenmare has secured pricing for new contracts in
the range of US$300 to US$400 per tonne for the first half of the year.
Zircon prices more than doubled during 2011, with standard grade zircon prices
increasing from around US$1,000 per tonne to US$2,400 per tonne by the end of
2011. Rutile prices increased strongly during 2011 and market prices are now
above US$2,000 per tonne.
As a condition of the debt financing package which was used to fund Phase 1, the
Company entered into several fixed price supply contracts. All but one of these
contracts has now expired and this remaining contract has had the price revised
upwards with the agreement of the customer. New contracts entered into are
generally based on annual quantities with six-monthly review of prices.
In the fourth quarter of 2011, there was a slowdown in Chinese real estate
development resulting from policy instruments introduced by the Chinese
Government in order to prevent the real estate sector from overheating. This
resulted in reduced demand for pigment and zircon products. Commentators
believe that, having achieved their goals, the Government will gradually
withdraw these policy instruments. While the growth of the Chinese economy is
expected to be somewhat lower than that experienced during the last couple of
years, Chinese economic growth is still expected be substantial and sustainable,
leading to a strong pricing environment for ilmenite and rutile, with some
softening in zircon prices over the coming months. The Company is therefore now
in a position to more fully benefit from prevailing market conditions.
Board of Directors
On January 23, Charles Carvill retired from the Board of Kenmare and passed
Chairmanship to Justin Loasby. Mr. Loasby joined Kenmare's Board in August 2011
as a Non-Executive Director. He has extensive experience of African mining from
his former position as Associate Director at the European Investment Bank,
Luxembourg, where he led the EIB's financing of development of the mining sector
in Southern Africa and the Indian Ocean from 1994 to 2007, prior to which he
worked in investment banking in the City of London.
For further information, please contact:
Kenmare Resources plc.
Tony McCluskey, Financial Director
Tel: +353 1 671 0411
Mob: + 353 87 674 0346
Jacob Deysel, Operations Director
Tel: +353 1 671 0411
Mob: +353 87 613 9609
Murray Consultants
Joe Heron
Tel: +353 1 498 0300
Mob: +353 87 690 9735
Tavistock Communication
Paul Youens / Jos Simson
Tel: +44 207 920 3150
Mob: +44 7843 260 623
This announcement is distributed by Thomson Reuters on behalf of
Thomson Reuters clients. The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and
other applicable laws; and
(ii) they are solely responsible for the content, accuracy and
originality of the information contained therein.
Source: Kenmare Resources via Thomson Reuters ONE
[HUG#1579855]
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Jun 2024 to Jul 2024
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Jul 2023 to Jul 2024