TIDMS32
RNS Number : 4846D
South32 Limited
27 April 2017
South32 Limited
(Incorporated in Australia under the Corporations Act 2001
(Cth))
(ACN 093 732 597)
ASX, LSE, JSE Share Code: S32 ADR: SOUHY
ISIN: AU000000S320
27 April 2017
South32 Limited
QUARTERLY OPERATIONAL REPORT MARCH 2017
Graham Kerr, South32 CEO said:
"Despite several operational challenges during the quarter, we
increased our net cash balance by US$645M to US$1.5B.
"Having achieved the right balance of strength and flexibility,
we announced a US$500M capital management program and subsequently
commenced an on-market share buy-back in April.
"Consistent with our strategy to identify new opportunities
through the drill bit, we entered into a strategic alliance with
AusQuest. Under this agreement, we will pursue five early stage
base metal opportunities in Australia and Peru. We have also
entered into an option agreement with Trilogy covering the more
advanced Upper Kobuk Mineral projects in Alaska and will initially
test the extent of their high grade Bornite copper resource."
-- Increased net cash by US$645M to US$1.5B at 31 March 2017.
-- Announced a US$500M capital management program in line with
our commitment to return excess cash to shareholders.
-- Maintained strong performance at our aluminium smelters and
achieved an alumina hydrate production rate in excess of 4.6Mtpa
(100% basis) at Worsley Alumina.
-- Increased ore production at South Africa Manganese to an
annualised rate of 3.8Mwmt pa (100% basis) in response to
favourable market conditions.
-- Delivered first ore from the higher grade La Esmeralda deposit at Cerro Matoso.
-- Maintained FY17 production guidance at Illawarra
Metallurgical Coal following the completion of an extended longwall
move at Dendrobium.
-- Revised FY17 production guidance at Cannington to 16.5Moz of
silver, 135kt of lead and 70kt of zinc following an underground
fire, with unit costs now expected to approximate US$155/t.
-- Revised FY17 and FY18 production guidance at South Africa
Energy Coal following heavy rainfall and an associated delay in the
development of new mining areas at the Wolvekrans-Middelburg
Complex (WMC).
-- Entered into an option agreement with Trilogy Metals Inc. in
respect of their Upper Kobuk Mineral projects in the Ambler Mining
District, Alaska.
Production summary
------------------------- ------ ------ ----- ----- ----- ----- -----
9M 9M
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 QoQ
------------------------- ------ ------ ----- ----- ----- ----- -----
Alumina production
(kt) 4,000 3,901 (2%) 1,334 1,320 1,288 (2%)
------------------------- ------ ------ ----- ----- ----- ----- -----
Aluminium production
(kt) 725 737 2% 240 249 245 (2%)
------------------------- ------ ------ ----- ----- ----- ----- -----
Energy coal production
(kt) 24,967 22,567 (10%) 7,930 7,518 6,858 (9%)
------------------------- ------ ------ ----- ----- ----- ----- -----
Metallurgical coal
production (kt) 4,940 4,260 (14%) 1,642 1,392 1,431 3%
------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese ore production
(kwmt) 3,551 3,718 5% 1,205 1,253 1,285 3%
------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese alloy
production (kt) 179 162 (9%) 48 56 47 (16%)
------------------------- ------ ------ ----- ----- ----- ----- -----
Payable nickel
production (kt) 27.2 26.8 (1%) 9.7 9.0 9.1 1%
------------------------- ------ ------ ----- ----- ----- ----- -----
Payable silver
production (koz) 16,356 12,277 (25%) 4,478 4,035 3,548 (12%)
------------------------- ------ ------ ----- ----- ----- ----- -----
Payable lead production
(kt) 134.4 105.2 (22%) 36.9 35.5 31.3 (12%)
------------------------- ------ ------ ----- ----- ----- ----- -----
Payable zinc production
(kt) 60.3 57.2 (5%) 18.5 24.4 15.1 (38%)
------------------------- ------ ------ ----- ----- ----- ----- -----
Unless otherwise noted: percentage variance relates
to performance during the nine months ended March
2017 compared with the nine months ended March
2016 (YoY) or the March 2017 quarter compared with
the December 2016 quarter (QoQ); production and
sales volumes are reported on an attributable basis.
----------------------------------------------------------------------------
CORPORATE UPDATE
* Our net cash(1) balance increased by US$645M to
US$1.5B in the quarter as working capital unwound and
we received US$108M (South32 share) in distributions
from our equity accounted investments. On 27 March
2017, we announced a US$500M capital management
program and subsequently commenced an on-market share
buy-back on 19 April 2017.
* Following an underground fire and subsequent
downgrade to FY17 production guidance, Cannington's
Operating unit cost(2) , including Sustaining capital
expenditure, is now expected to increase to US$155/t
(previously US$141/t). Unit cost guidance for all
other operations in FY17 remains unchanged and will
require strong performance in the June 2017 quarter.
* Capital expenditure of approximately US$420M
(previously US$450M) is now expected in FY17,
although the rate of spend is expected to increase in
the June 2017 quarter as land is purchased in
preparation for the Klipspruit Life Extension
project.
* We invested US$13.0M in exploration in the nine
months ended March 2017 (US$2.1M capitalised). This
includes US$1.7M at our equity accounted investments
(US$1.0M capitalised). We explored for metallurgical
coal, manganese and silver in Australia and nickel in
Colombia.
* Beyond our current portfolio, we are pursuing base
metals opportunities in four countries, having
entered into new agreements with AusQuest Limited and
Trilogy Metals Inc. in March and April, respectively.
Under the terms of the latter agreement, we will
provide US$30M over three years to test the extent of
the high-grade copper resource at Trilogy's Bornite
deposit in the Ambler Mining District, Alaska. This
funding will be paid in tranches of US$10M per annum,
with the decision to proceed to year two and three
subject to exploration results. Our exploration spend
is now expected to be approximately US$30M in FY17.
Upstream production FY16 9M FY17e
guidance YTD17
(South32's share)
----------------------------- ------- ------- -----------
Worsley Alumina
----------------------------- ------- ------- -----------
Alumina production
(kt) 3,961 2,904 3,965
----------------------------- ------- ------- -----------
Brazil Alumina
----------------------------- ------- ------- -----------
Alumina production
(kt) 1,335 997 1,320
----------------------------- ------- ------- -----------
South Africa Energy
Coal(3)
----------------------------- ------- ------- -----------
Energy coal production Revised
(kt) 31,681 21,500 30,000
----------------------------- ------- ------- -----------
Domestic coal production Revised
(kt) 16,825 12,744 17,500
----------------------------- ------- ------- -----------
Export coal production Revised
(kt) 14,856 8,756 12,500
----------------------------- ------- ------- -----------
Illawarra Metallurgical
Coal
----------------------------- ------- ------- -----------
Total coal production
(kt) 8,366 5,327 7,900
----------------------------- ------- ------- -----------
Metallurgical coal
production (kt) 7,059 4,260 6,360
----------------------------- ------- ------- -----------
Energy coal production
(kt) 1,307 1,067 1,540
----------------------------- ------- ------- -----------
Australia Manganese
----------------------------- ------- ------- -----------
Manganese ore production
(kwmt) 3,071 2,218 3,120
----------------------------- ------- ------- -----------
South Africa Manganese
----------------------------- ------- ------- -----------
Manganese ore production(4) Subject
(kwmt) 1,711 1,500 to demand
----------------------------- ------- ------- -----------
Cerro Matoso
----------------------------- ------- ------- -----------
Payable nickel production
(kt) 36.8 26.8 36.0
----------------------------- ------- ------- -----------
Cannington
----------------------------- ------- ------- -----------
Payable silver production Revised
(koz) 21,393 12,277 16,500
----------------------------- ------- ------- -----------
Payable lead production Revised
(kt) 173 105 135
----------------------------- ------- ------- -----------
Payable zinc production Revised
(kt) 79 57 70
----------------------------- ------- ------- -----------
WORSLEY ALUMINA
(86% share)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
------------------- ------ ------ ---- ----- ---- ----- ----- -----
Alumina production
(kt) 3,001 2,904 (3%) 1,008 973 964 (4%) (1%)
------------------- ------ ------ ---- ----- ---- ----- ----- -----
Alumina sales (kt) 2,915 2,927 0% 1,017 949 1,018 0% 7%
------------------- ------ ------ ---- ----- ---- ----- ----- -----
Worsley Alumina saleable production decreased by 3% (or 97kt) to
2.9Mt in the nine months ended March 2017. While the alumina
hydrate input circuit achieved an annualised production rate in
excess of 4.6Mtpa (100% basis) in the March 2017 quarter, saleable
alumina production was impacted by unplanned calciner maintenance.
FY17 saleable alumina production guidance remains unchanged at
approximately 4.0Mt.
SOUTH AFRICA ALUMINIUM
(100%)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
--------------------- ------ ------ ---- ---- ---- ---- ----- -----
Aluminium production
(kt) 525 534 2% 173 181 178 3% (2%)
--------------------- ------ ------ ---- ---- ---- ---- ----- -----
Aluminium sales
(kt) 525 510 (3%) 162 169 163 1% (4%)
--------------------- ------ ------ ---- ---- ---- ---- ----- -----
South Africa Aluminium saleable production increased by 2% (or
9kt) to 534kt in the nine months ended March 2017 as benchmark
levels of current efficiency continued to be achieved, the smelter
benefitted from fewer load-shedding events and 22 pots were brought
back online in the December 2016 quarter.
MOZAL ALUMINIUm
(47.1% share)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
--------------------- ------ ------ --- ---- ---- ---- ----- -----
Aluminium production
(kt) 200 203 2% 67 68 67 0% (1%)
--------------------- ------ ------ --- ---- ---- ---- ----- -----
Aluminium sales
(kt) 185 200 8% 64 70 66 3% (6%)
--------------------- ------ ------ --- ---- ---- ---- ----- -----
Mozal Aluminium saleable production increased by 2% (or 3kt) to
203kt in the nine months ended March 2017 as benchmark levels of
current efficiency continued to be achieved and the smelter
benefitted from fewer load-shedding events.
Brazil Alumina
(36% share)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
------------------- ------ ------ ---- ---- ---- ---- ----- -----
Alumina production
(kt) 999 997 (0%) 326 347 324 (1%) (7%)
------------------- ------ ------ ---- ---- ---- ---- ----- -----
Alumina sales (kt) 1,021 994 (3%) 360 339 356 (1%) 5%
------------------- ------ ------ ---- ---- ---- ---- ----- -----
Brazil Alumina saleable production remained largely unchanged in
the nine months ended March 2017. Heavy rainfall in the March 2017
quarter resulted in a 7% (or 23kt) decrease in production relative
to the record December 2016 quarter. FY17 saleable alumina
production guidance remains unchanged at 1.3Mt.
South Africa Energy Coal
(100%)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Energy coal production
(kt) 24,071 21,500 (11%) 7,692 7,081 6,675 (13%) (6%)
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Domestic sales
(kt) 13,080 12,974 (1%) 4,000 4,472 4,056 1% (9%)
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Export sales (kt) 11,596 8,729 (25%) 3,575 2,952 2,873 (20%) (3%)
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
South Africa Energy Coal saleable production decreased by 11%
(or 2.6Mt) to 21.5Mt in the nine months ended March 2017. Export
sales and pit development at the WMC were impacted by heavy
rainfall in the March 2017 quarter and FY17 production guidance has
been revised accordingly to 30.0Mt (domestic coal 17.5Mt, export
coal 12.5Mt). The depletion of existing pits and the delayed
development of new mining areas at the WMC is expected to result in
a further 2.5Mt reduction in production in FY18 to approximately
27.5Mt (domestic coal 16.0Mt, export coal 11.5Mt). While our
budgeting process for FY18 is currently underway, we do anticipate
a significant increase in Operating unit cost, including Sustaining
capital expenditure, as a result of the temporary reduction in
production and rise in sustaining capital expenditure at the
WMC.
illawarra metallurgical coal
(100%)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Total coal production
(kt) 5,836 5,327 (9%) 1,880 1,829 1,614 (14%) (12%)
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Total coal sales
(kt) 5,700 5,585 (2%) 1,959 1,412 1,980 1% 40%
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Metallurgical coal
production (kt) 4,940 4,260 (14%) 1,642 1,392 1,431 (13%) 3%
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Metallurgical coal
sales (kt) 4,727 4,482 (5%) 1,595 1,065 1,694 6% 59%
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Energy coal production
(kt) 896 1,067 19% 238 437 183 (23%) (58%)
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Energy coal sales
(kt) 973 1,103 13% 364 347 286 (21%) (18%)
----------------------- ------ ------ ----- ----- ----- ----- ----- -----
Illawarra Metallurgical Coal total saleable production decreased
by 9% (or 509kt) to 5.3Mt in the nine months ended March 2017 as
challenging ground conditions were encountered at Appin Area 9 and
mining rates were moderated at Appin Area 7 to ensure gas
concentrations were maintained at safe levels. Production in the
March 2017 quarter was impacted by a longwall move at Dendrobium
that was extended by four days and was slow to ramp-up as a result
of challenging roof conditions. FY17 production guidance remains
unchanged at 7.9Mt and requires a strong finish to the year. A
longwall move at Appin Area 9 is scheduled for June.
A drawdown of inventory ensured sales in the nine months ended
March 2017 exceeded production by 258kt. Sales in the March 2017
quarter also included a carry-over shipment from the December 2016
half year, as anticipated.
australia manganese
(60% share)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
------------------------- ------ ------ ---- ---- ---- ---- ----- -----
Manganese ore production
(kwmt) 2,332 2,218 (5%) 743 736 719 (3%) (2%)
------------------------- ------ ------ ---- ---- ---- ---- ----- -----
Manganese ore sales
(kwmt) 2,309 2,249 (3%) 852 743 749 (12%) 1%
------------------------- ------ ------ ---- ---- ---- ---- ----- -----
Manganese alloy
production (kt) 111 106 (5%) 26 40 28 8% (30%)
------------------------- ------ ------ ---- ---- ---- ---- ----- -----
Manganese alloy
sales (kt) 120 119 (1%) 44 28 37 (16%) 32%
------------------------- ------ ------ ---- ---- ---- ---- ----- -----
Australia Manganese saleable ore production decreased by 5% (or
114kwmt) to 2.2Mwmt in the nine months ended March 2017. Heavy
rainfall and Tropical Cyclone Alfred led to lower production in the
primary high grade circuit in the March 2017 quarter, although this
was partially offset by strong performance within the Premium
Concentrate ore (PC02) circuit which continued to operate at its
annualised capacity of 500kwmt (100% basis). Our low cost PC02
fines product has a manganese content of approximately 40% which
leads to both grade and product-type discounts when referenced to
the high grade 44% manganese lump ore index. FY17 production
guidance of 3.1Mwmt remains unchanged.
Saleable manganese alloy production decreased by 5% (or 5kt) to
106kt in the nine months ended March 2017 as an electrode upgrade
was undertaken in January. The impact of the shutdown was offset by
a drawdown of inventory, resulting in an increase of alloy sales in
the March 2017 quarter. All four furnaces are expected to ramp-up
to full capacity in the June 2017 quarter.
SOUTH AFRICA manganese
(60% share)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
------------------------- ------ ------ ----- ---- ---- ---- ----- -----
Manganese ore production
(kwmt) 1,219 1,500 23% 462 517 566 23% 9%
------------------------- ------ ------ ----- ---- ---- ---- ----- -----
Manganese ore sales
(kwmt) 1,345 1,482 10% 466 511 554 19% 8%
------------------------- ------ ------ ----- ---- ---- ---- ----- -----
Manganese alloy
production (kt) 68 56 (18%) 22 16 19 (14%) 19%
------------------------- ------ ------ ----- ---- ---- ---- ----- -----
Manganese alloy
sales (kt) 70 54 (23%) 20 20 14 (30%) (30%)
------------------------- ------ ------ ----- ---- ---- ---- ----- -----
South Africa Manganese saleable ore production increased by 23%
(or 281kwmt) to 1.5Mwmt in the nine months ended March 2017 as we
responded to favourable market conditions by opportunistically
increasing ore production. This included an annualised production
rate of 3.8Mwmt pa (100% basis) in the March 2017 quarter as we
continued to sell Wessels concentrate and use higher cost trucking
to access export opportunities. We ceased trucking activity at the
end of the March 2017 quarter as we responded to a change in market
conditions.
The Wessels Central Block project was commissioned in the March
2017 quarter, as planned. The project will enable mining to
relocate closer to critical infrastructure and lower production
costs in the underground mine.
Manganese alloy saleable production decreased by 18% (or 12kt)
to 56kt in the nine months ended March 2017 despite an improvement
in furnace stability in the quarter. Metalloys continues to operate
one of its four furnaces. Alloy sales in the March 2017 quarter
were affected by the timing of shipments.
cerro matoso
(99.9% share)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
----------------- ------ ------ ---- ---- ---- ---- ----- -----
Payable nickel
production (kt) 27.2 26.8 (1%) 9.7 9.0 9.1 (6%) 1%
----------------- ------ ------ ---- ---- ---- ---- ----- -----
Payable nickel
sales (kt) 26.8 26.8 0% 9.3 9.4 9.2 (1%) (2%)
----------------- ------ ------ ---- ---- ---- ---- ----- -----
Cerro Matoso payable nickel production decreased by 1% to 26.8kt
in the nine months ended March 2017. A reduction in furnace
availability in the March 2017 quarter was offset by the
availability of previously stockpiled, higher grade fines.
The accelerated development of the higher grade La Esmeralda
deposit allowed first ore to be delivered to the plant in the March
2017 quarter. Payable nickel production guidance remains unchanged
at 36kt in FY17 but will rise to approximately 41.6kt in FY18 as La
Esmeralda ramps up to full capacity.
cannington
(100%)
3Q16 2Q17
9M 9M vs vs
South32's share YTD16 YTD17 YoY 3Q16 2Q17 3Q17 3Q17 3Q17
------------------------ ------ ------ ----- ----- ----- ----- ----- -----
Payable silver
production (koz) 16,356 12,277 (25%) 4,478 4,035 3,548 (21%) (12%)
------------------------ ------ ------ ----- ----- ----- ----- ----- -----
Payable silver
sales (koz) 16,262 12,404 (24%) 4,364 3,797 3,544 (19%) (7%)
------------------------ ------ ------ ----- ----- ----- ----- ----- -----
Payable lead production
(kt) 134.4 105.2 (22%) 36.9 35.5 31.3 (15%) (12%)
------------------------ ------ ------ ----- ----- ----- ----- ----- -----
Payable lead sales
(kt) 132.5 105.8 (20%) 37.0 33.2 32.5 (12%) (2%)
------------------------ ------ ------ ----- ----- ----- ----- ----- -----
Payable zinc production
(kt) 60.3 57.2 (5%) 18.5 24.4 15.1 (18%) (38%)
------------------------ ------ ------ ----- ----- ----- ----- ----- -----
Payable zinc sales
(kt) 59.8 57.6 (4%) 18.6 22.3 16.8 (10%) (25%)
------------------------ ------ ------ ----- ----- ----- ----- ----- -----
Cannington silver, lead and zinc saleable production decreased
by 25%, 22% and 5%, respectively, in the nine months ended March
2017 due to lower feed grades, consistent with the mine plan.
Remediation work to repair load-out and shaft haulage
infrastructure damaged by an underground fire in April is
continuing. FY17 production guidance was previously revised to
16.5Moz of silver, 135kt of lead and 70kt of zinc as mill
throughput will remain constrained while this work is undertaken
and the extraction of the higher grade (silver/lead) 60L stope is
delayed. An Operating unit cost, including Sustaining capital
expenditure, of US$155/t (previously US$141/t) is now expected in
FY17 given the operation's high fixed cost base.
The development of the replacement underground crusher remains
on schedule for commissioning in the March 2018 quarter. As
previously indicated, the rate of deformation in the existing
crusher chamber has increased and it may become inoperable earlier
than planned. As such, the rate of ore extraction and metal
production may become temporarily constrained by trucking capacity
within the decline. We continue to monitor the rate of deformation
and will provide updated production guidance when we report our
FY17 financial results.
Notes:
1. Provisional unaudited net cash balance as at 31 March 2017.
2. FY17 Operating unit cost guidance, including Sustaining
capital expenditure, and Sustaining capital expenditure guidance,
include royalties (where appropriate) and the influence of exchange
rates, and are predicated on various assumptions for H2 FY17,
including: an alumina price of US$316/t; an average blended coal
price of US$146/t for Illawarra Metallurgical Coal; a manganese ore
price of US$6.79/dmtu for 44% manganese product; a nickel price of
US$4.65/lb; a thermal coal price of US$84/t (API4) for South Africa
Energy Coal; a silver price of US$17.04/troy oz; a lead price of
US$2,267/t; a zinc price of US$2,746/t; an AUD:USD exchange rate of
0.75; a USD:ZAR exchange rate of 14.20; and a USD:COP exchange rate
of 2,943; all of which reflected forward markets as at January 2017
or our internal expectations.
3. 8% of South Africa Energy Coal is owned by a Broad-Based
Black Economic Empowerment (B-BBEE) consortium. The interests owned
by the
B-BBEE consortium were acquired using vendor finance, with the
loans repayable to South32 via distributions attributable to these
parties, pro rata to their share in South Africa Energy Coal. Until
these loans are repaid, South32's interest in South Africa Energy
Coal is accounted at 100%.
4. Consistent with the presentation of South32's segment
information, South Africa Manganese ore production and sales have
been reported at 60%. The Group's financial statement will continue
to reflect a 54.6% interest in South Africa Manganese ore.
5. Figures in Italics indicate that an adjustment has been made
since the figures were previously reported.
6. The following abbreviations have been used throughout this
report: grams per tonne (g/t); tonnes (t); thousand tonnes (kt);
thousand tonnes per annum (ktpa); million tonnes (Mt); million
tonnes per annum (Mtpa); thousand ounces (koz); million ounces
(Moz); thousand wet metric tonnes (kwmt); million wet metric tonnes
(Mwmt); million wet metric tonnes per annum (Mwmt pa); thousand dry
metric tonnes (kdmt); Australian Securities Exchange (ASX); London
Stock Exchange (LSE); Johannesburg Stock Exchange (JSE); and
American Depositary Receipts (ADR).
operating performance
9M 9M
South32's share YTD16 YTD17 3Q16 4Q16 1Q17 2Q17 3Q17
--------------------------- ------ ------ ----- ----- ----- ----- -----
Worsley Alumina
(86% share)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Alumina hydrate production
(kt) 2,959 2,939 989 946 980 966 993
--------------------------- ------ ------ ----- ----- ----- ----- -----
Alumina production
(kt) 3,001 2,904 1,008 960 967 973 964
--------------------------- ------ ------ ----- ----- ----- ----- -----
Alumina sales (kt) 2,915 2,927 1,017 959 960 949 1,018
--------------------------- ------ ------ ----- ----- ----- ----- -----
South Africa Aluminium
(100%)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Aluminium production
(kt) 525 534 173 172 175 181 178
--------------------------- ------ ------ ----- ----- ----- ----- -----
Aluminium sales (kt) 525 510 162 184 178 169 163
--------------------------- ------ ------ ----- ----- ----- ----- -----
Mozal Aluminium
(47.1% share)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Aluminium production
(kt) 200 203 67 66 68 68 67
--------------------------- ------ ------ ----- ----- ----- ----- -----
Aluminium sales (kt) 185 200 64 69 64 70 66
--------------------------- ------ ------ ----- ----- ----- ----- -----
Brazil Alumina
(alumina 36% share,
aluminium 40% share)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Alumina production
(kt) 999 997 326 336 326 347 324
--------------------------- ------ ------ ----- ----- ----- ----- -----
Alumina sales (kt) 1,021 994 360 338 299 339 356
--------------------------- ------ ------ ----- ----- ----- ----- -----
South Africa Energy
Coal
(100%)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Energy coal production
(kt) 24,071 21,500 7,692 7,610 7,744 7,081 6,675
--------------------------- ------ ------ ----- ----- ----- ----- -----
Domestic sales (kt) 13,080 12,974 4,000 4,089 4,446 4,472 4,056
--------------------------- ------ ------ ----- ----- ----- ----- -----
Export sales (kt) 11,596 8,729 3,575 3,561 2,904 2,952 2,873
--------------------------- ------ ------ ----- ----- ----- ----- -----
Illawarra Metallurgical
Coal
(100%)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Total coal production
(kt) 5,836 5,327 1,880 2,530 1,884 1,829 1,614
--------------------------- ------ ------ ----- ----- ----- ----- -----
Total coal sales (kt) 5,700 5,585 1,959 2,617 2,193 1,412 1,980
--------------------------- ------ ------ ----- ----- ----- ----- -----
Metallurgical coal
production (kt) 4,940 4,260 1,642 2,119 1,437 1,392 1,431
--------------------------- ------ ------ ----- ----- ----- ----- -----
Metallurgical coal
sales (kt) 4,727 4,482 1,595 2,257 1,723 1,065 1,694
--------------------------- ------ ------ ----- ----- ----- ----- -----
Energy coal production
(kt) 896 1,067 238 411 447 437 183
--------------------------- ------ ------ ----- ----- ----- ----- -----
Energy coal sales (kt) 973 1,103 364 360 470 347 286
--------------------------- ------ ------ ----- ----- ----- ----- -----
Australia Manganese
(60% share)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese ore production
(kwmt) 2,332 2,218 743 739 763 736 719
--------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese ore sales
(kwmt) 2,309 2,249 852 775 757 743 749
--------------------------- ------ ------ ----- ----- ----- ----- -----
Ore grade sold (%,
Mn) 47.4 46.3 47.1 47.0 46.7 46.1 46.0
--------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese alloy production
(kt) 111 106 26 22 38 40 28
--------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese alloy sales
(kt) 120 119 44 30 54 28 37
--------------------------- ------ ------ ----- ----- ----- ----- -----
South Africa Manganese
(60% share)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese ore production
(kwmt) 1,219 1,500 462 492 417 517 566
--------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese ore sales
(kwmt) 1,345 1,482 466 489 417 511 554
--------------------------- ------ ------ ----- ----- ----- ----- -----
Ore grade sold (%,
Mn) 40.2 40.2 40.4 39.2 39.7 40.8 40.1
--------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese alloy production
(kt) 68 56 22 23 21 16 19
--------------------------- ------ ------ ----- ----- ----- ----- -----
Manganese alloy sales
(kt) 70 54 20 40 20 20 14
--------------------------- ------ ------ ----- ----- ----- ----- -----
9M 9M
South32's share YTD16 YTD17 3Q16 4Q16 1Q17 2Q17 3Q17
--------------------------- ------ ------ ----- ----- ----- ----- -----
Cerro Matoso
(99.9% share)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Ore mined (kwmt) 4,529 3,391 1,512 1,480 1,238 1,109 1,044
--------------------------- ------ ------ ----- ----- ----- ----- -----
Ore processed (kdmt) 2,016 1,937 704 683 645 644 648
--------------------------- ------ ------ ----- ----- ----- ----- -----
Ore grade processed
(%, Ni) 1.53 1.56 1.53 1.55 1.52 1.55 1.60
--------------------------- ------ ------ ----- ----- ----- ----- -----
Payable nickel production
(kt) 27.2 26.8 9.7 9.6 8.7 9.0 9.1
--------------------------- ------ ------ ----- ----- ----- ----- -----
Payable nickel sales
(kt) 26.8 26.8 9.3 10.0 8.2 9.4 9.2
--------------------------- ------ ------ ----- ----- ----- ----- -----
Cannington
(100%)
--------------------------- ------ ------ ----- ----- ----- ----- -----
Ore mined (kt) 2,470 2,314 727 819 780 859 675
--------------------------- ------ ------ ----- ----- ----- ----- -----
Ore processed (kt) 2,330 2,408 673 819 828 841 739
--------------------------- ------ ------ ----- ----- ----- ----- -----
Silver ore grade processed
(g/t, Ag) 264 194 258 230 216 182 183
--------------------------- ------ ------ ----- ----- ----- ----- -----
Lead ore grade processed
(%, Pb) 6.9 5.4 6.7 5.9 5.7 5.2 5.3
--------------------------- ------ ------ ----- ----- ----- ----- -----
Zinc ore grade processed
(%, Zn) 3.8 3.5 4.1 3.6 3.2 4.2 3.0
--------------------------- ------ ------ ----- ----- ----- ----- -----
Payable silver production
(koz) 16,356 12,277 4,478 5,037 4,694 4,035 3,548
--------------------------- ------ ------ ----- ----- ----- ----- -----
Payable silver sales
(koz) 16,262 12,404 4,364 4,590 5,063 3,797 3,544
--------------------------- ------ ------ ----- ----- ----- ----- -----
Payable lead production
(kt) 134.4 105.2 36.9 38.8 38.4 35.5 31.3
--------------------------- ------ ------ ----- ----- ----- ----- -----
Payable lead sales
(kt) 132.5 105.8 37.0 37.2 40.1 33.2 32.5
--------------------------- ------ ------ ----- ----- ----- ----- -----
Payable zinc production
(kt) 60.3 57.2 18.5 18.7 17.7 24.4 15.1
--------------------------- ------ ------ ----- ----- ----- ----- -----
Payable zinc sales
(kt) 59.8 57.6 18.6 22.8 18.5 22.3 16.8
--------------------------- ------ ------ ----- ----- ----- ----- -----
Forward-looking statements
This release contains forward-looking statements, including
statements about currency exchange rates, commodity prices,
production forecasts, plans, development decisions, exploration and
capital expenditure. These forward-looking statements reflect
expectations at the date of this release; however, they are not
guarantees or predictions of future performance. They involve known
and unknown risks, uncertainties and other factors, many of which
are beyond our control, and which may cause actual results to
differ materially from those expressed in the statements contained
in this release. Readers are cautioned not to put undue reliance on
forward-looking statements. Except as required by applicable laws
or regulations, South32 Limited does not undertake to publicly
update or review any forward looking statements, whether as a
result of new information or future events. Past performance cannot
be relied on as a guide to future performance.
Further information
INVESTOR RELATIONS
Alex Volante Rob Ward
T +61 8 9324 9029 T +61 8 9324 9340
M +61 403 328 M +61 431 596
408 831
E Alex.Volante@south32.net E Robert.Ward@south32.net
MEDIA RELATIONS
Hayley Cardy James Clothier
T +61 8 9324 9008 T +61 8 9324 9697
M +61 409 448 M +61 413 319
288 031
E Hayley.Cardy@south32.net E James.Clothier@south32.net
27 April 2017
JSE Sponsor: UBS South Africa (Pty) Ltd
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCLIFIESVIDFID
(END) Dow Jones Newswires
April 27, 2017 02:02 ET (06:02 GMT)
South32 (LSE:S32)
Historical Stock Chart
From Apr 2024 to May 2024
South32 (LSE:S32)
Historical Stock Chart
From May 2023 to May 2024