31
July 2024
Sylvania Platinum
Limited
("Sylvania", the
"Company" or the "Group")
Fourth Quarter Report to 30
June 2024
Sylvania (AIM: SLP), the platinum
group metals ("PGM") producer and developer with assets in South
Africa, announces its results for the three months ended 30 June
2024 (the "Quarter" or the "Period"). Unless otherwise stated, the
consolidated financial information contained in this report is
presented in United States Dollars ("USD" or "$").
Highlights
· Sylvania Dump Operations ("SDO") produced 17,067 4E (21,896
6E) PGM ounces in Q4 FY2024 (Q3 FY2024: 17,232 4E (21,857 6E)
PGM ounces);
· SDO
produced 72,704 4E (92,4276E) PGM ounces for FY2024 (FY2023 75,469
4E PGM ounces; 95,965 6E PGM ounces);
· SDO
recorded $20.6 million net revenue for the Quarter (Q3 FY2024:
$20.3 million);
· Group
EBITDA of $2.8 million (Q3 FY2024: $3.2 million);
· Cash
balance as at 30 June 2024 of $97.8 million (31 March 2024: $101.3
million);
· Doornbosch operation achieved 12 years
Lost-Time Injury ("LTI")-free days as well
as achieving three years total injury free days during the Quarter;
· Thaba
Joint Venture ("Thaba JV") project is on schedule with all phases
of construction of the chrome and PGM beneficiation plants
progressing well;
· An
interim cash dividend for HY1 FY2024 of 1 pence per Ordinary Share,
amounting to $3.3 million, was paid in April 2024;
· The
Company received early settlement of the loan and proceeds for the
sale of Grasvally Chrome Mine (Pty) Ltd ("Grasvally") amounting to
an equivalent of $6.2 million; and
· A
special dividend of 1 pence per Ordinary Share, amounting to $3.3
million, was paid on 7 June 2024 from the Grasvally settlement
proceeds.
Outlook
· The
Mooinooi and Millsell operations on the West have now stabilised
and are expected to perform at steady-state capacity, while
optimisation efforts continue to address lower PGM feed grades and
recoveries associated with the blend of feed sources at selected
operations;
· Progress on the final design aspects, bulk power supply,
environmental approvals, procurement and construction elements of
the Thaba JV project continue with the aim to commence
commissioning during March 2025;
· The
Scoping Study for the Volspruit project is currently being
finalised for the combined project (North and South ore bodies)
with results expected to be released during August 2024;
· The
Group maintains strong cash reserves enabling funding of expansion,
diversification and joint venture ("JV") initiatives, process
optimisation capital and upgrading of the Group's exploration
assets, and
· Performance enhancement initiative commenced at
Lesedi.
Commenting on the results,
Sylvania's CEO, Jaco Prinsloo, said:
"Doornbosch recorded an extraordinary health and safety
milestone of 12 years LTI-free days during the Quarter
and has achieved three years total
injury-free days. We are extremely proud of
Management and all personnel, who have set an example of exemplary
high safety standards for the Company and the industry as a
whole.
"The SDO experienced a slower than expected ramp-up of
operations after members of the National Union of Mineworkers South
Africa ("NUMSA") embarked on a strike during February 2024 at our
Western operations that impacted production at Mooinooi and
Millsell in particular, but operations have since normalised and
are running at planned capacity. This, together with lower PGM feed
grades and a decrease in associated metal recoveries related to the
ore mix at some of our Eastern operations, resulted in a lower than
anticipated quarterly production and ultimate annual production of
72,704 4E PGM ounces for FY2024, marginally below our target of
between 74,000 to 75,000 4E PGM ounces for the year.
"Direct operating costs increased by 3% in rand terms with the
main contributor being the purchase cost for external feed material
which commenced during December 2023 and ramped up over HY2 FY2024.
This is an interim arrangement that is anticipated to last until
June/July 2025.
"Net profit increased 9% from Q3 FY2024, due to
the lower tax in
Q4 FY2024 as compared to Q3 FY2024. Net revenue for Q4 FY2024
increased by 2% mainly due to the slightly improved
gross basket price, off-set marginally by the 1% decrease in
production. Group EBITDA decreased by
10% owing to the increase in direct costs during the
Quarter.
"I
am very pleased with the excellent progress on the Thaba JV with
the design, procurement and construction elements of the project
all on schedule during the Period and throughout
FY2024. The Thaba JV project remains
exciting as it is the first stage of our strategy to diversify our
production and income streams and will transform us into a
significant chrome producer as we continue our examination of other
opportunities for diversification."
Operational and Financial
Summary
Production
|
|
|
|
|
Unit
|
Q3 FY2024
|
Q4 FY2024
|
% Change
|
Plant Feed
|
T
|
580,572
|
600,058
|
3%
|
Feed Head Grade
|
g/t
|
2.07
|
1.98
|
-4%
|
PGM Plant Feed Tons
|
T
|
330,379
|
336,029
|
2%
|
PGM Plant Feed Grade
|
g/t
|
3.06
|
3.03
|
-1%
|
PGM Plant
Recovery1
|
%
|
53.03%
|
52.10%
|
-2%
|
Total 4E PGMs
|
Oz
|
17,232
|
17,067
|
-1%
|
Total 6E PGMs
|
Oz
|
21,857
|
21,896
|
0%
|
Unaudited
|
|
USD
|
|
ZAR
|
|
Unit
|
Q3 FY2024
|
Q4 FY2024
|
% Change
|
Unit
|
Q3 FY2024
|
Q4 FY2024
|
% Change
|
Financials
3
|
Average
4E Gross Basket Price2
|
$/oz
|
1,303
|
1,383
|
6%
|
R/oz
|
24,624
|
25,683
|
4%
|
Revenue
(4E)
|
$'000
|
16,086
|
16,967
|
5%
|
R'000
|
304,017
|
314,903
|
4%
|
Revenue
(by-products including base metals)
|
$'000
|
3,121
|
2,827
|
-9%
|
R'000
|
58,992
|
52,472
|
-11%
|
Sales
adjustments
|
$'000
|
1,115
|
833
|
-25%
|
R'000
|
21,081
|
15,457
|
-27%
|
Net
revenue
|
$'000
|
20,322
|
20,627
|
2%
|
R'000
|
384,090
|
382,832
|
0%
|
|
|
|
|
|
|
|
|
|
Direct
Operating costs
|
$'000
|
14,233
|
14,931
|
5%
|
R'000
|
269,011
|
277,112
|
3%
|
Indirect
Operating costs
|
$'000
|
2,354
|
2,220
|
-6%
|
R'000
|
44,484
|
41,197
|
-7%
|
General
and Administrative costs
|
$'000
|
653
|
721
|
10%
|
R'000
|
12,342
|
13,382
|
8%
|
Group
EBITDA5
|
$'000
|
3,164
|
2,845
|
-10%
|
R'000
|
59,800
|
52,803
|
-12%
|
Net
Profit5
|
$'000
|
2,530
|
2,752
|
9%
|
R'000
|
47,817
|
51,077
|
7%
|
|
|
|
|
|
|
|
|
|
Capital
Expenditure
|
$'000
|
3,514
|
5,292
|
51%
|
R'000
|
66,410
|
98,221
|
48%
|
|
|
|
|
|
|
|
|
|
Cash
Balance4
|
$'000
|
101,342
|
97,845
|
-3%
|
R'000
|
1,916,377
|
1,779,801
|
-7%
|
|
|
|
|
|
|
|
|
|
Ave R/$
rate
|
|
|
|
|
R/$
|
18.90
|
18.56
|
-2%
|
Spot R/$
rate
|
|
|
|
|
R/$
|
18.91
|
18.19
|
-4%
|
|
|
|
|
|
|
|
|
|
Unit
Cost/Efficiencies
|
SDO Cash
Cost per 4E PGM oz6
|
$/oz
|
826
|
875
|
6%
|
R/oz
|
15,611
|
16,237
|
4%
|
SDO Cash
Cost per 6E PGM oz6
|
$/oz
|
651
|
682
|
5%
|
R/oz
|
12,308
|
12,656
|
3%
|
Group
Cash Cost Per 4E PGM oz6
|
$/oz
|
980
|
1,027
|
5%
|
R/oz
|
18,522
|
19,061
|
3%
|
Group
Cash Cost Per 6E PGM oz6
|
$/oz
|
772
|
801
|
4%
|
R/oz
|
14,591
|
14,867
|
2%
|
All-in
Sustaining Cost (4E)
|
$/oz
|
1,008
|
1,077
|
7%
|
R/oz
|
19,046
|
19,986
|
5%
|
All-in
Cost (4E)
|
$/oz
|
1,145
|
1,161
|
1%
|
R/oz
|
21,643
|
21,555
|
0%
|
The Sylvania cash generating
subsidiaries are incorporated in South Africa with the functional
currency of these operations being ZAR. Revenues from the
sale of PGMs are received in USD and then converted into ZAR.
The Group's reporting currency is USD as the parent company is
incorporated in Bermuda. Corporate and general and
administration costs are incurred in USD, GBP and ZAR.
1 PGM plant recovery is
calculated on the production ounces that include the
work-in-progress ounces when applicable.
2 The gross basket price in
the table is the June 2024 gross 4E basket used for revenue
recognition of ounces delivered in Q4 FY2024, before
penalties/smelting costs and applying the contractual
payability.
3 Revenue (6E) for Q4 FY2024, before adjustments is $19.7
million (6E prill split is Pt 52%, Pd 18%, Rh 9%, Au 0%, Ru 16%, Ir
5%). Revenue excludes profit/loss on foreign exchange.
4 The cash balance excludes
restricted cash held as guarantees. An additional $0.4 million was
issued as a cash guarantee to Eskom during the Quarter for the
Thaba JV.
5 Group
EBITDA and Net Profit exclude $1.2 million accrued interest written
off with regards to the Grasvally Chrome Mine (Pty) Ltd transaction
which was concluded at the end of Q3 FY2024.
6
The cash costs include operating costs and exclude
indirect costs for example mineral royalty tax and Employee
Dividend Entitlement Plan ("EDEP") payments.
A. OPERATIONAL OVERVIEW
Safety, health and environment
Doornbosch continued its stellar
safety record by achieving twelve years LTI-free days on 26 June
2024 as well as achieving three years total injury-free days, while
Mooinooi, Millsell and Lannex also achieved Zero Harm during the
Period.
During the Period under review,
Tweefontein experienced an LTI when a tipper truck overturned and
resulted in the operator injuring his shoulder.
Management's commitment to safety is
not just a policy, but a fundamental value that seeks to ensure
everyone working at Sylvania's operations can go home to their
families at the end of each day healthy and unharmed. The Company
is committed to achieving the aim of ensuring Zero Harm for both
employees and contractors, which remains a top priority.
Operational performance
The SDO delivered 17,067 4E PGM
ounces for the Quarter. This equates to a decrease of 1% on Q3
FY2024 and lower than planned, largely due to the slower than
expected ramp-up of operations after the strike action in February
2024 at our Western operations that impacted production at the
Mooinooi and Millsell operations in particular. The
slower-than-expected ramp-up was a result
of a backlog of maintenance during the strike period due to limited
resources at the time, which ultimately resulted in lower plant
availabilities and runtime and process stability on the
run of mine ("ROM")
section. Additionally, lower PGM feed
grades as well as a decrease in associated metal recoveries related
to the ore mix treated at Lannex during the period were also a
factor.
The Western operations have since
improved with better maintenance and runtime, while measures are
being implemented to address the lower grade feed material and
related recoveries at affected operations.
Direct operating costs have
increased by 3% in rand terms with the main contributor being the
purchase and treatment of external feed material which commenced
during December 2023 and has ramped up over the last six
months. This is a temporary initiative that will continue
until June 2025, where the company sourced external feed material
to supplement lower grade feed sources at Doornbosch and also to
secure material that became available to extend the life of
selected Eastern operations.
SDO operating cash costs per 4E PGM
ounce increased 4% in rand terms to ZAR16,237/ounce and 6% in
dollar terms, to $875/ounce (Q3 FY2024: ZAR15,611/ounce and
$826/ounce) due to the 1% reduction in production, the purchase of
increased tonnages of external material for the Eastern operations,
and increased electricity costs associated with higher rates during
the winter months.
The Group incurred capital
expenditure of ZAR98.2 million ($5.3 million), in line with planned
capital project schedules.
Operational opportunities and outlook
Optimisation of ore blending remains
a priority with continuing focus on improving equipment runtime,
which has resulted in an increase of 2% in flotation plant
throughput. This is being further optimised and should yield
positive results going forward. The "On
Key" Enterprise Asset Management System is
currently being rolled-out at the Mooinooi operation, which aims to
optimise maintenance management planning
and scheduling tasks.
No Eskom load curtailment has been
experienced at any of the operations during the Quarter. The
installation of the Millsell standby generator has been completed
and commissioning commenced post year-end during July
2024.
A feasibility study for a potential
new treatment facility for chrome tailings and ROM ore sources at
the Eastern operations is in progress.
In view of the performance of Lesedi
over the past 12 months, which has been impacted by a combination
of low feed grades from current feed sources and continued subdued
PGM prices, the Company has commenced consultation with
stakeholders under Section 189A ("S189A") of the Labour Relations
Act, 66 of 1995 (LRA) on the possible restructuring of the
operation. The aim of this process is to improve the overall
profitability of the SDO and further updates will be provided in
due course.
B. FINANCIAL OVERVIEW
Financial performance
Revenue (4E) for the Quarter
increased by 5% to $17.0 million (Q3 FY2024: $16.1 million) as a
result of the average 4E gross basket price for the Quarter
increasing 6% to $1,383/ounce against $1,303/ounce in Q3
FY2024.
Net revenue, which includes revenue
from by-products, base metals and the quarter-on-quarter sales
adjustment, was $20.6 million (Q3 FY2024: $20.3 million). Net
revenue includes attributable revenue received for ounces produced
from material purchased from third parties.
Group cash costs per 4E PGM
ounce increased by 3% in rand terms from
ZAR18,522/ounce to ZAR19,061/ounce and 5%
in dollar terms from $980/ounce to $1,027/ounce mainly
as a result of the 1% decrease in ounce production
quarter-on-quarter and the increase in Eskom tariffs by 13.3% from
April 2024.
General and administrative costs
increased to $0.72 million from $0.65 million in Q3 FY2024. These
costs are incurred in USD, Pounds Sterling ("GBP") and
ZAR.
Group EBITDA for the Quarter was
$2.8 million (Q3 FY2024: $3.2 million) impacted mainly by the
increased direct cost as a result of the purchase of external feed
sources. Net profit was $2.8 million (Q3
FY2024: $2.5 million). Net profit increased 9% from Q3 FY2024, due
to the lower tax in Q4 FY2024 compared to
Q3 FY2024. The lower tax is mainly due to the write-off of the
accrued interest on the loan relating to the Grasvally sale. Due to
the early settlement of the loan and sale price, it was agreed to
write off the accrued interest on the loan and sale
price.
The Group cash balance decreased 3%
to $97.8 million compared to $101.3 million in the previous
quarter. Provisional income tax of $1.4 million and mineral royalty
tax of $0.8 million were paid to the South African Revenue Services
during Q4 FY2024. The Company paid a special dividend of 1 pence
per Ordinary Share amounting to $3.3 million on 7 June 2024 to all
shareholders on the register at the close of business on 10 May
2024, following the early settlement of the Grasvally sale proceeds
and loan of $6.2 million. An amount of $0.1 million was paid under
the share buyback programme during the Quarter and a cash guarantee
of $0.4 million was issued to Eskom in relation to the Thaba
JV.
The Group spent $5.3 million on
capital during Q4 FY2024 (Q3 FY2024: $3.5 million), comprising of
$3.1 million attributable capital on the Thaba JV, $1.9 million on
improvement and stay-in business capital and $0.3 million on
exploration projects, and. Surplus cash invested earned $1.5
million interest income for the Quarter.
Cash generated from operations
before working capital movement was $2.8 million. Net changes in
working capital amounted to $2.6 million, which is mainly due to
the movement in trade debtors and trade creditors. The impact of
exchange rate fluctuations on cash held at the end of Q4 FY2024 was
a $2.5 million gain due to the appreciation in the spot ZAR to USD
exchange rate at 30 June 2024.
C.
THABA JV
The unincorporated JV Agreement
between the Company's wholly owned South African subsidiary,
Sylvania Metals (Pty) Ltd ("Sylvania Metals") and Limberg Mining
Company (Pty) Ltd ("LMC"), a subsidiary of ChromTech Mining Company
(Pty) Ltd ("ChromTech"), the Thaba JV, is advancing well and as
expected. The project execution phase is approximately 18-24 months
which commenced in August 2023, with the first production expected
in HY2 FY2025.
Safety
At the end of the June 2024
reporting Period, more than 124,000 manhours had been worked
without any serious injuries being recorded. Manhours will escalate
significantly from Q1 FY2025 when the structural, mechanical and
platework ("SMP") contractors arrive on site and will continue to
ramp up during Q2 FY2025 when electrical
control and instrumentation ("EC&I") and piping contractors
arrive on site.
Environmental Approvals
Environmental Impact Assessment
("EIA") Reports, required for tailings
deposition and new water storage dams, were delivered to the
Department of Mineral Resources and Energy
("DMRE") during March 2024 and a timely decision
is expected on the EIA based on the legislated timeframe for
issuance of decisions by the DMRE.
Primary Chrome Plant
The primary (ROM) chrome recovery
plant is an existing plant, but several improvements will be
implemented to increase availability, throughput, and chrome
recoveries. Modelling of the plant modifications, including
mechanical equipment changes, has been completed.
Secondary Chrome Plant
The secondary chrome recovery plant
is a new plant, which incorporates circuits for recovery of coarse
and fine chrome from Primary Chrome Plant tailings and dump feed.
Civil works for this plant were completed during Q4 FY2024 and
steel deliveries have started. The contractor is on site and steel
and plate erection commenced in July 2024.
PGM
Plant
Civil works for the PGM plant is
complete and steel erection commenced in June 2024. The first batch
of float tanks were delivered and installed during June 2024.
Structural design of reagent plant and ancillary equipment and
infrastructure was finalised and issued for fabrication in July
2024.
Infrastructure
Orders for all long lead items and
for the installation contract were placed during Q3 FY2024 and Q4
FY2024. Most of the EC&I design work has been completed, with
small power, lighting and the last of the non-critical instrument
datasheets being undertaken presently.
Long lead items that are ready for
delivery, but not yet required (including more than 80% of cabling)
are warehoused by the suppliers to minimise risk of theft and
vandalism while secure off-loading areas are being prepared on
site.
The EIA report was submitted in
March 2024 and followed by the Water Use Licence ("WUL") report in
April 2024. Feedback from the DMRE is expected soon.
Preparation works have started for
the equipping of strategic boreholes and open cast pit dewatering /
recovery to supply clean water to the plant. The stormwater
management design was completed and simplified. Enquiries were
issued for the construction of the tailings
storage facility ("TSF") for in-pit
deposition.
Construction of the new in-plant
road for PGM and chrome concentrate truck dispatches is in progress
and the weighbridge will be relocated during a short duration
shutdown - to avoid impact on existing mining operations - as soon
as civil works are completed.
D. MINERAL ASSET DEVELOPMENT AND JOINT
VENTURES
The Group holds approved mining
rights for three PGM-base metal projects on the Northern Limb of
the Bushveld Igneous Complex in South Africa. Following on from the
Exploration Results and Resource Statement that was released in
FY2023, the Company continues to develop these projects through
additional technical studies and re-interpretation of historical
information. A Scoping Study is being finalised for Volspruit and
an updated exploration programme is being developed for the Aurora
project. This additional information will assist the Company in
ascertaining how best to develop these projects.
Volspruit Project
SRK Consulting is finalising the
Scoping Study for Volspruit with the final report expected to be
released during August 2024. The study was undertaken to
assess the economic viability of the Project based on the updated
mineral resource statement that was published during February 2024.
Contributions from rhodium and the additional resources from the
South ore body are now included as well as updated input
costs.
Additional metallurgical test work
has also been completed at Mintek South Africa on samples obtained
during an FY2023 drilling campaign with the final report expected
during Q1 FY2025. The updated results from the Scoping Study and
metallurgical test work will be utilised to guide the next steps
for this project.
On the regulator front, steady
progress is being made in the permitting process necessary for the
existing mining right. Local Economic Development projects are
gaining traction and the Water Use License application for mining
and on-site processing operations, as well as the updated EIA
submissions, are expected to be made in the first quarter of
FY2025, allowing for a comprehensive public engagement process to
be completed.
Far
Northern Limb Projects
An exploration programme for Aurora
has been compiled based on the reinterpretation of historic
drilling. A geophysical survey has been proposed to cover the
entire strike length of the project to assess both the continuity
of the mineralisation as well as to gain a greater understanding of
the structural setting of the area. The Hacra project area will be
included in the geophysical survey ensuring that knowledge gained
from the work covers the entire project area.
Processing test work has been
proposed for a set of samples from the most recent drilling
campaign at Aurora to understand the metallurgical characteristics
of the mineralised zone.
Borehole drilling programmes will be
designed based on the outcomes of the geophysical and metallurgical
test work.
A Technical Report received in Q3
FY2024 on the Hacra North Underground Target from the independent
consultant Earthlab Technical Division is under review and will
form part of an exploration update announcement during August
2024.
Grasvally
As reported previously, the Company
agreed to an early settlement, in the amount of ZAR115.0 million
($6.2 million on date of payment), of the loan and sale price
related to the sale of Grasvally Chrome Mine (Pty) Ltd to Forward
Africa Mining (Pty) Ltd.
During the previous quarter, the
parties negotiated an early settlement date for payment of the
capital amount outstanding at 31 March 2024 and the full ZAR115.0
million ($6.2 million on date of payment) was received in April
2024. The original contractual repayment terms of the capital and
interest was 15 equal quarterly instalments, commencing at the end
of the quarter following the first anniversary of the Effective
Date. As a result of the early settlement, the Company agreed to
write off the interest accrued.
Following receipt of the early
settlement proceeds, the Company declared and paid a Special
Dividend of 1 pence per Ordinary Share, amounting to $3.3 million
in aggregate.
E.
CORPORATE ACTIVITIES
Share Buyback and Cancellation of Ordinary
Shares
During the Period, the Company
conducted a Share Buyback from the market and bought back 130,000
Ordinary Shares of $0.01 each in the Company ("Ordinary Shares") at
an average price of 59.78 pence per Ordinary Share. A total of
1,843,000 Ordinary Shares have to date been bought back during the
Buyback programme at an average price of 57.21 pence per share,
equating to $1.3 million in aggregate. The purpose of the Share
Buyback was to reduce the share capital of the Company and enhance
the value attributable to the remaining shareholders of the
Company. During the Period, 2,009,000 Ordinary Shares held in
Treasury were cancelled. Following the above cancellation,
the Company's issued share capital is 273,366,725 Ordinary Shares,
of which a total of 11,765,211 Ordinary Shares are held in
Treasury. Therefore, the total number of Ordinary Shares with
voting rights in Sylvania is 261,601,514 Ordinary
Shares.
Notice of Annual Results Investor
Presentation
The Company confirms it will
announce its Final Results for the year ended 30 June 2024 on
Tuesday, 10 September 2024.
Sylvania's CEO, Jaco Prinsloo, and
CFO, Lewanne Carminati, will host a live investor presentation, via
the Investor Meet Company platform, on 10 September 2024 at 16:00
BST.
The presentation is open to all
existing and potential shareholders. Questions can be submitted
pre-event via your Investor Meet Company dashboard up until 9.00am
the day before the meeting or at any time during the live
presentation.
Investors can sign up to Investor
Meet Company for free and add to meet Sylvania via:
https://www.investormeetcompany.com/sylvania-platinum-limited/register-investor
Investors who already follow
Sylvania on the Investor Meet Company platform will automatically
be invited.
CONTACT DETAILS
For
further information, please contact:
|
|
Jaco Prinsloo CEO
Lewanne Carminati CFO
|
+27 11 673 1171
|
|
|
Nominated Adviser and Broker
|
|
Panmure Liberum Limited
|
+44 (0) 20 3100 2000
|
Scott Mathieson / John More / Joshua
Borlant
|
|
|
|
Communications
|
|
BlytheRay
|
+44 (0) 20 7138 3205
|
Tim Blythe / Megan Ray
|
sylvania@BlytheRay.com
|
CORPORATE INFORMATION
Registered and postal address:
|
Sylvania Platinum Limited
|
|
Clarendon House
|
|
2 Church Street
|
|
Hamilton HM 11
|
|
Bermuda
|
|
|
SA
Operations postal address:
|
PO Box 976
|
|
Florida Hills, 1716
|
|
South Africa
|
|
|
Sylvania Website:
www.sylvaniaplatinum.com
About Sylvania Platinum Limited
Sylvania Platinum is a lower-cost
producer of platinum group metals (PGM) (platinum, palladium and rhodium) with
operations located in South Africa. The Sylvania Dump Operations
(SDO) comprises six chrome beneficiation and PGM processing plants
focusing on the retreatment of PGM-rich chrome tailings materials
from mines in the Bushveld Igneous Complex. The SDO is the largest
PGM producer from chrome tailings re-treatment in the industry.
Additionally, the Thaba JV comprises chrome beneficiation and PGM
processing plants, which will treat a combination of run of mine
(ROM) and historical chrome tailings from the JV partner, adding a
full margin chromite concentrate revenue stream. The Group also
holds mining rights for PGM projects in the Northern Limb of the
Bushveld Complex.
For more information visit
https://www.sylvaniaplatinum.com/
ANNEXURE
GLOSSARY OF TERMS FY2024
|
The
following definitions apply throughout the
period:
|
3E PGMs
|
3E ounces include the precious metal
elements platinum, palladium and gold
|
4E PGMs
|
4E ounces include the precious metal
elements platinum, palladium, rhodium and gold
|
6E PGMs
|
6E ounces include the 4E elements
plus additional Iridium and Ruthenium
|
AGM
|
Annual General Meeting
|
AIM
|
Alternative Investment Market of the
London Stock Exchange
|
All-in costs
|
All-in sustaining cost plus
non-sustaining and expansion capital expenditure
|
All-in sustaining cost
|
Production costs
plus all costs relating to sustaining current production
and sustaining capital expenditure
|
CLOs
|
Community Liaison
Officers
|
Current arisings
|
Fresh chrome tails from current
operating host mines processing operations
|
DFFE
|
Department of Forestry, Fisheries
and the Environment
|
DMRE
|
Department of Mineral Resources and
Energy
|
EBITDA
|
Earnings before interest, tax,
depreciation and amortisation
|
EA
|
Environmental
Authorisation
|
EAP
|
Employee Assistance
Program
|
EC&I
|
Electrical Control and
Instrumentation
|
EEFs
|
Employment Engagement
Forums
|
EDEP
|
Employee Dividend Entitlement
Programme
|
ESG
|
Environment, social and
governance
|
EIA
|
Environmental Impact
Assessment
|
EIR
|
Effective interest rate
|
EMPR
|
Environmental Management Programme
Report
|
ESG
|
Environment, Social and
Governance
|
GBP
|
Pounds Sterling
|
GBV
|
Gender based violence
|
GHG
|
Greenhouse gases
|
GISTM
|
Global Industry Standard on Tailings
Management
|
GRI
|
Global Reporting
Initiative
|
HWS
|
Harriets Wish Succession
|
JORC
|
Joint Ore Reserves
Committee
|
IASB
|
International Accounting Standards
Board
|
ICE
|
Internal combustion
engine
|
IFRIC
|
International Financial Reporting
Interpretation Committee
|
IFRS
|
International Financial Reporting
Standards
|
Lesedi
|
Phoenix Platinum Mining Proprietary
Limited, renamed Sylvania Lesedi
|
LSE
|
London Stock Exchange
|
LTI
|
Lost-time injury
|
LTIFR
|
Lost-time injury frequency
rate
|
MF2
|
Milling and flotation
technology
|
MPRDA
|
Mineral and Petroleum Resources
Development Act
|
MRA
|
Mining Right Application
|
MRE
|
Mineral Resource Estimate
|
Mt
|
Million Tons
|
NWA
|
National Water Act 36 of
1998
|
PGM
|
Platinum group metals comprising
mainly platinum, palladium, rhodium and gold
|
PAR
|
Pan African Resources Plc
|
PDMR
|
Person displaying management
responsibility
|
PEA
|
Preliminary Economic
Assessment
|
PFS
|
Preliminary Feasibility
Study
|
Pipeline ounces
|
6E ounces delivered but not
invoiced
|
Pipeline revenue
|
Revenue recognised for ounces
delivered, but not yet invoiced based on contractual
timelines
|
Pipeline sales adjustment
|
Adjustments to pipeline revenues
based on the basket price for the period between delivery and
invoicing
|
PTM
|
Platinum Group Metal's Joint
Venture
|
Project Echo
|
Secondary PGM Milling and Flotation
(MF2) program announced in FY2017 to design and install additional
new fine grinding mills and flotation circuits at Millsell,
Doornbosch, Tweefontein, Mooinooi and Lesedi
|
RPEEE
|
Reasonable Prospects for Eventual
Economic Extraction
|
Revenue (by products)
|
Revenue earned on Ruthenium,
Iridium, Nickel and Copper
|
ROM
|
Run of mine
|
S189A
|
A formal consultation process with
relevant stakeholders on potential restructuring
|
SDO
|
Sylvania dump operations
|
SHE
|
Safety, health and
environmental
|
SLP
|
Social and Labour Plan
|
Sylvania
|
Sylvania Platinum Limited, a company
incorporated in Bermuda
|
Sylvania Metals
|
Sylvania Metals (Pty)
Limited
|
tCO2e
|
Tons of carbon dioxide
equivalent
|
Thaba JV
|
Thaba Joint Venture
|
TRIFR
|
Total recordable injury frequency
rate
|
TSF
|
Tailings storage facility
|
UNSDGs
|
United Nations Sustainability
Development Goals
|
USD
|
United States Dollar
|
WUL
|
Water Use Licence
|
UK
|
United Kingdom of Great Britain and
Northern Ireland
|
ZAR
|
South African Rand
|
Zero Harm
|
The South African mining industry is
committed to the shared aspiration of achieving the goal of Zero
Harm, which aims to ensure that mineworkers return home from work
healthy and unharmed every day
|