TIDMHUM
RNS Number : 9360O
Hummingbird Resources PLC
06 February 2023
Hummingbird Resources plc / Ticker: HUM / Index: AIM / Sector:
Mining
6 February 2023
Hummingbird Resources plc
("Hummingbird" or the "Company")
Q4 2022 and 2023 Outlook
Closing out the 2022 year with strong production of +28koz,
meeting revised full year guidance and on track at Kouroussa,
Guinea for first gold pour at the end of Q2 2023
Hummingbird Resources plc (AIM: HUM) provides an operational
update for the fourth quarter of 2022 ("Q4 2022") and its outlook
for FY2023.
Operational update
Yanfolila, Mali
-- Production: Strong Q4 2022 gold production of 28,264 ounces
("oz"), +67% from Q3 2022
o Full year 2022 production of 80,635 oz, meeting revised
guidance
-- All-in Sustaining Cost ("AISC"): Materially improved
quarterly AISC of US$1,248 per oz for Q4 2022 (Q3 2022 US$2,161 per
oz)
o Full year 2022 AISC of US$1,782 pe--r oz, meeting revised
guidance
-- Gold sold: 27,860 oz of gold sold in Q4 2022 at an average
realised price of US$1,726 per oz (Q3 2022: 16,917 oz of gold sold
at an average realised price of US$1,713 per oz). The Company held
2,057 oz of gold inventory on 31 December 2022, valued at c.US$3.7
million
Kouroussa, Guinea
-- Kouroussa remains on track for first gold pour at the end of
Q2 2023
-- Critical path construction and operational readiness items
are nearing completion
-- 2 million lost time injury ("LTI") free hours achieved, a key
safety achievement for the Kouroussa construction team, with this
positive safety trend continuing
Dugbe, Liberia
-- As reported in the Q3 2022 operational update, the Company is
currently conducting a strategic review of its options to best
realise the maximum value of the Dugbe project for all
stakeholders. This process is ongoing with our joint venture
partner, Pasofino Gold Limited ("Pasofino")
Corporate
-- Improved Group EBITDA of c.US$11 million for Q4 2022
-- ESG : The Company achieved full World Gold Council ("WGC")
Responsible Gold Mining Principles ("RGMP") compliance during the
quarter as detailed in 15 November 2022 RNS
2023 Outlook
-- The Company provides a 2023 guidance update for Yanfolila,
Mali and, once Kouroussa, Guinea is in production and ramping up,
the Company will provide a more detailed Group wide guidance update
for the full year
o Expectations are that once Kouroussa is fully operational, the
mine will add a material uplift to the Group's production profile
for FY2023 and beyond
-- FY2023 production guidance for Yanfolila, Mali of 80,000 -
90,000 oz, with full year AISC of under US$1,500 per oz
Dan Betts, CEO of Hummingbird, commented:
"Following the initiation of restructuring the Company's
contract mining operations as detailed last quarter, Hummingbird
finished the year in a substantially stronger position, with
Yanfolila producing its best quarterly production for several
years, of over 28koz, an improved AISC profile generating positive
cashflows, with similar trends continuing for this current
quarter.
Kouroussa's construction continued to make material advances and
remains on target for first gold pour at the end of Q2 2023,
despite a challenging macro environment. Kouroussa is a high-grade
mine, with LOM upside through further drilling which we are
reviewing for 2H 2023, that will provide strong cash flow
generation, taking the Company to be a +200,000 oz gold producer,
which we will give more detailed guidance on once in production and
ramping up.
Further, during the quarter we achieved full WGC RGMP
compliance, a key milestone in terms of the Company's
implementation of leading industry standard ESG policies and
procedures.
For 2023 we will achieve our strategic goal of being a
multi-asset, multi-jurisdiction gold producer. With Yanfolila
operational performance improving, and Kouroussa set to come online
the end of Q2 2023, the Company is at a pivotal juncture for
exponential growth, with expectations for improved cash flow
generation and a stronger balance sheet this year."
Operational Update
Further operational and post period updates on:
Yanfolila, Mali
-- Q4 2022 production of 28,264 oz was a +67% improvement from
the 16,827 oz in Q3 2022, and 80,653 oz for FY 2022, meeting
revised guidance
o As noted in our Q3 2022 release, to stabilise production, the
Company intervened with our contract miner in securing additional
key equipment to site, including grade control and production rigs,
coupled with onsite leadership changes
o These measures have been broadly successful, with the Company
being able to better achieve its mine plan schedule, move into the
higher-grade Komana East ("KE") deposit, resulting in a strong
production quarter, with a similar quarter-on quarter production
profile expected for this quarter, Q1 2023
-- Mill feed grade for Q4 2022 averaged 2.45 grammes per tonne
("g/t"), a material improvement from the previous quarters, with a
FY 2022 average mill feed grade of 2.00 g/t
o With operational and production improvements as highlighted
above, better access to the higher-grade ore deposit at KE was
achieved, leading to the improved grade profile
-- Ore processed totalled 382,683 tonnes ("t"), a +30%
improvement from Q3 2022 levels, as the key target deposit for the
quarter, being KE, was mined, leading to higher-grade and more
tonnage ore feed processed at the mill
-- Mined bank cubic meters ("BCM") totalled 1,303,770 in Q4 2022
and 7,734,175 for FY 2022
o The BCM movement in Q4 2022 was lower than Q3 2022, as the key
target mine area for the quarter, being KE, required less overall
BCM movement and more drill rig exposure to access the higher-grade
ore feed to the mill. This resulted in an improvement in ore
processed at the mill as noted above compared to Q3 2022 levels
-- Processing plant recovery rates for Q4 2022 were 94.28%,
returning to the average 1H 2022 rates
-- As noted in our Q3 2022 update, the Komana East underground
("KEUG") deposit is in our 2023 Yanfolila mine plan with first
underground gold production expected by the end of Q4 2023, for a
full year of production scheduled for FY 2024. With a + 278,000 oz
Reserve, at 3.94 g/t , and increased mine life potential with
further drilling, the KEUG will be a key deposit to underpin
Yanfolila's future production profile
-- The Company has initiated a detailed cost control and
reduction programme at Yanfolila, Mali with a focus to reduce AISC
for FY2023 and beyond versus FY2022 levels
-- Per the highlights above, FY2023 production guidance for
Yanfolila, Mali of 80,000 - 90,000 oz, with a full year AISC of
under US$1,500 per oz
Kouroussa, Guinea:
Kouroussa is a high-grade, low-cost mine, which has a current
Reserve of 647,000 oz at 4.15 g/t with upside potential to extend
life of mine ("LOM") with further drilling, which is being reviewed
for 2H 2023. As previously announced, the mine is estimated to
produce an average of between 120,000 oz and 140,000 oz for the
first three years of production and average 100,000 oz over the
initial LOM.
As noted in the highlights above, Kouroussa remains on track for
first gold pour at end of Q2 2023, with a more detailed Group wide
production guidance update to be released once the mine is in
production and ramping up.
Key operational and construction updates that occurred for the
quarter include:
-- All process plant earthworks completed
-- Civil works for the Oxide ore crushing ROM wall, SAG mill,
and Reclaim Tunnel have been completed, Carbon Plant civil works
near completion and Gold Room civil works have commenced
-- All Pre-Leach, CIL and Detoxification tanks constructed,
reagents make-up building erected
-- Plant store and Workshop infrastructure buildings completed
and mine administration building roofing installation in
progress
-- All mine camp accommodation units near completion, camp
messing and entertainment building under construction
-- TSF construction progress aligned with the planned process
plant commissioning date
Installation and delivery of key items
-- Mechanical installation commenced for Mineral Sizer and SAG
mill, all SAG mill base plates are installed and signed off. SAG
mill fixed and floating bearing installation commenced
-- CIL and Detox Agitator shafts and blades, delivered to site
and installed
-- Air services building, compressors and air receivers
installed
-- All crushing circuit mechanicals delivered to site - Apron
Feeder, Vibrating Grizzly Feeder, Jaw Crusher and Mineral Sizer.
Conveyor mechanical equipment delivered to site
-- SAG mill base plates, fasteners, bearings, trommel screen,
feed chute, shell cans and liners delivered to site
-- Carbon safety screen installed
Operational Readiness update
-- A General Manager with significant operational experience
joined during Q4 2022 and is implementing detailed operational
readiness programs towards first gold pour
-- Long lead items for the project have been ordered, with the
last remaining key equipment delivery items due early this quarter,
Q1 2023
-- Operation readiness programmes are being finalised and
implemented in preparation for first gold pour end of Q2 2023
including: mine plan; grade control drilling; overall mining and
power infrastructure implementation; and active recruitment for
final key operational positions
-- Mobilisation of mining personnel and equipment took place
during the quarter, with mining ramping up in 1H 2023
-- Power plant scheduled to be operational in Q1 2023, with the
addition of a +7-megawatt hour ("Mwh") solar farm to be constructed
and operational by year end. Once installed it is anticipated that
in excess of 30% of the power will be generated through solar, with
discussions ongoing to increase this to 40% in 2024, being a key
part of the Company's greenhouse gas ("GHG") emission reduction
strategy
-- As noted on our Q3 2022 release, community engagement remains
a key feature of all workstreams, with the community projects and
livelihood initiatives underway, which the Company expects to
expand upon in 2023 including: water supply infrastructure; local
community hospital infrastructure improvements and medical
supplies; market gardens; and commercial product manufacturing
training such as Shea butter and honey cultivation
Dugbe, Liberia:
As noted above, the Company is currently conducting a strategic
review of its options to best realise the maximum value of the
Dugbe project for all stakeholders with our joint venture partner,
Pasofino. The Company will provide more details once more material
progress is made.
Financial Summary:
-- Q4 2022 AISC improved materially from Q3 2022 levels at
US$1,248 per oz, versus US$2,161 per oz, primarily due to the
improved quarterly production
o FY 2022 AISC of US$1,782 oz, meeting revised guidance
-- Improved Group EBITDA of c.US$11 million for Q4 2022
-- Net debt position c.US$114 million end of Q4 2022 (c.US$110
million including gold inventory value). As detailed in the Q3 2022
release, an additional c.US$35 million debt facility was agreed
with Coris Bank International ("Coris Bank"), to secure funding
requirements and ensure Kouroussa moves into production, with
c.US$15 million of the US$35 million remaining available and
expected to be drawn 1H 2023
-- Of the budgeted c.US$115 million capex for the construction
of Kouroussa, c.US$65 million has been paid as at the end of Q4
2022, with the balance to be paid over the coming quarters from
Yanfolila cash flows (which have improved) and existing debt
facilities, including c.US$20 million contractor deferrals,
retention incentives and working capital not expected to be paid
until Kouroussa is into full production
ESG Q4 2022 updates include:
-- The Company achieved full WGC RGMP compliance during the
quarter as detailed on 15 November 2022. Adopting the WGC RGMPs is
a key part of the Company's strategy for building a long term,
sustainable mining Company and a key ESG result and highlight for
2022
-- The Company continued to have strong community engagement
both at Yanfolila and Kouroussa, including the development and
enhancement of community projects at both sites including: water
supply infrastructure; malaria prevention spraying; market gardens;
training initiatives; and community healthcare support. FY 2023 ESG
budgets have been finalised and the Company expects to enhance our
community project works, especially at Kouroussa
-- As noted above, at Kouroussa, planning and budgeting was
finalised during Q4 2024 to have installed a +7Mwh solar farm to
provide energy efficiencies and reduce the Company's GHG emissions
at the mine. Once installed it is anticipated that in excess of 30%
of the power will be generated through solar, with discussions
ongoing to increase this to 40% in 2024
Notes to Editors:
Hummingbird Resources plc (AIM: HUM) is a leading multi-asset,
multi-jurisdiction gold production, development and exploration
Company, member of the World Gold Council and founding member of
Single Mine Origin ( www.singlemineorigin.com ). The Company
currently has two core gold projects, the operational Yanfolila
Gold Mine in Mali, and the Kouroussa Gold Mine in Guinea, which
will more than double current gold production when in full
production, scheduled for first gold pour the end of Q2 2023.
Further, the Company has a controlling interest in the Dugbe Gold
Project in Liberia that is being developed by Pasofino Gold Limited
through an earn-in agreement. The final feasibility results on
Dugbe showcase 2.76Moz in Reserves and strong economics such as a
3.5-year capex payback period once in production, 14-year life of
mine at a low AISC profile. Our vision is to continue to grow our
asset base, producing profitable ounces, while central to all we do
being our Environmental, Social & Governance ("ESG") policies
and practices.
F or further information, please visit
hummingbirdresources.co.uk or subscribe to our investor releases
via investor email alerts
Daniel Betts, Hummingbird Resources Tel: +44 (0) 20 7409
CEO plc 6660
Thomas Hill,
FD
Edward Montgomery,
CSO & ESG
James Spinney Strand Hanson Limited Tel: +44 (0) 20 7409
Ritchie Balmer Nominated Adviser 3494
-------------------------- ----------------------------
James Asensio Canaccord Genuity Limited Tel: +44 (0) 20 7523
Thomas Diehl Broker 8000
-------------------------- ----------------------------
Bobby Morse Buchanan Tel: +44 (0) 20 7466
Oonagh Reidy Financial PR/IR 5000
George Cleary Email: HUM@buchanan.uk.com
-------------------------- ----------------------------
This information is provided by RNS, the news service of the
London Stock Exchange. RNS is approved by the Financial Conduct
Authority to act as a Primary Information Provider in the United
Kingdom. Terms and conditions relating to the use and distribution
of this information may apply. For further information, please
contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms
and conditions, to analyse how you engage with the information
contained in this communication, and to share such analysis on an
anonymised basis with others as part of our commercial services.
For further information about how RNS and the London Stock Exchange
use the personal data you provide us, please see our Privacy
Policy.
END
UPDTJMPTMTBMBRJ
(END) Dow Jones Newswires
February 06, 2023 02:00 ET (07:00 GMT)
Hummingbird Resources (AQSE:HUM.GB)
Historical Stock Chart
From Nov 2024 to Dec 2024
Hummingbird Resources (AQSE:HUM.GB)
Historical Stock Chart
From Dec 2023 to Dec 2024