Arcadis develops and implements new building standard to accelerate the roll-out of offshore wind energy
27 January 2022 - 5:00PM
Arcadis develops and implements new building standard to accelerate
the roll-out of offshore wind energy
Amsterdam, January 27
2022: Arcadis (EURONEXT: ARCAD),
the leading global design and consultancy
organization for the natural and built environment, is supporting
high-voltage grid operator, TenneT
develop and implement a standard design for future 2GW
land converter stations
to boost the rollout of renewable wind
energy and support energy transition. The new standard design will
be implemented at three locations across the
Netherlands.
The new stations will connect the IJmuiden Ver Wind Farm to be
built in the North Sea with the high-voltage grid on land. These
land converter stations meet the new 2-GigaWatt (GW) standard that
TenneT developed to accelerate the roll-out of offshore wind. One
land station will be located at Borssele in the province of Zeeland
and the two others on the Maasvlakte near Rotterdam. This contract
will initially be worth 4.75 million euros.
The new standard will help reduce the costs of offshore wind and
minimizes the impact on space and the environment. Furthermore,
capacity will more than double compared to the previous 900 MW HVDC
standard that TenneT applied in Germany and almost triples compared
to the Dutch 700 MW AC standard for connecting offshore wind farms
to the high-voltage grid. With the ambition to accelerate the
production of renewable wind energy, future wind farms will be
designed to the 2GW standard. The first grid connection is planned
for 2028.
The three land stations are the first projects to be delivered
in accordance with this new standard and Arcadis will manage the
detailed design, planning and tender process for the new buildings.
The designs will also consider the full life cycle of the asset,
including maintenance and operation. The energy generated by the
offshore wind turbines will be brought onshore via direct current
cables and must be converted in the land stations into 380
kilovolts alternating current for the high-voltage grid. The high
voltage components will be designed and supplied by a specialized
company.
Frank Goossensen, Sales
& Business Development
Director, Resilience at
Arcadis said:
“Investing in renewable energy and developing the infrastructure
required for a greener future are both key when it comes to
realizing the world’s net zero ambitions. Capturing the energy from
wind is a powerful means for achieving this goal, and our work with
TenneT to develop a design standard that will support accelerated
roll-out and boost capacity marks a crucial step in providing
future generations with affordable, reliable and sustainable
energy.”
For more information about our work on the Energy Transition and
the ‘Supercharging Net Zero’ research paper, please visit:
https://www.arcadis.com/energytransition.
-End-
FOR FURTHER INFORMATION PLEASE
CONTACT:ARCADIS CORPORATE COMMUNICATIONSChris Wiggan
Mobile: +44 7881 845741E-mail: chris.wiggan@arcadis.com
ARCADIS INVESTOR RELATIONSJurgen PullensMobile: +31 6
51599483E-mail: jurgen.pullens@arcadis.com
ABOUT ARCADISArcadis is the leading global
design & consultancy organization for natural and built assets.
We maximize impact for our clients and the communities they serve
by providing effective solutions through sustainable outcomes,
focus and scale, and digitalization. We are 28,000 people, active
in more than 70 countries that generate €3.3 billion in revenues.
We support UN-Habitat with knowledge and expertise to improve the
quality of life in rapidly growing cities around the world.
www.arcadis.com
- Arcadis develops and implements new building standard to
accelerate the roll-out of offshore wind energy
Arcadis NV (EU:ARCAD)
Historical Stock Chart
From Jan 2025 to Feb 2025
Arcadis NV (EU:ARCAD)
Historical Stock Chart
From Feb 2024 to Feb 2025