Conference Call and Webcast Scheduled:
December 14, 2021 at 10:00 am EST
TORONTO, Dec. 14, 2021 /CNW/ - Argonaut Gold
Inc. (TSX: AR) (the "Company", "Argonaut Gold" or "Argonaut")
announces that it has completed a review of the estimated
construction capital at completion ("EAC") of its 100%-owned Magino
project in Ontario, Canada
("Magino" or the "Project"). The Company also announces a
change in leadership. All dollar amounts are expressed in
Canadian dollars, unless otherwise specified. "US$" refers to
United States dollars.
Leadership Change
The Company announces that Pete
Dougherty has ceased to be the President and Chief Executive
Officer of Argonaut Gold effective immediately. The Board of
Directors has commenced a search to replace these roles and is
working in real time to put interim leadership in place. The
Board of Directors believes the existing executive team, with the
support and guidance of the Board, is well suited to continue to
run the business while a lasting leadership decision is being
made.
Argonaut would like to thank Mr. Dougherty for his contributions
during his tenure as President and Chief Executive Officer.
James Kofman, Chair of the Board,
commented: "Pete Dougherty was the
founder of the Company and has taken Argonaut from a small Company
to a diversified gold producer operating in three
countries. The Board of Directors intends to work actively
with and be available to the executive leadership team. Our
Board consists of four members with mining CEO experience and a
wealth of knowledge in both financing and strategic alternatives.
We have full confidence in the existing executive team to step up
during this interim period."
Magino Construction Capital Estimate
After a review of the impacts of cost increases, inflation,
COVID-19, adjustments to the development plans and contingencies,
the updated Magino EAC is approximately $800
million. It is forecasted that through December 31, 2021, approximately $342 million will have been invested into the
Project, leaving approximately $459
million remaining to be invested to complete the
Project.
Magino EAC Variance – October
2020 Construction Decision vs. Current (CAD $M)
Area
|
October 2020
EAC
|
Change
|
Current EAC
|
Process
Facilities
|
$193
|
$26
|
$219
|
Tailings Management
Facility ("TMF")
|
$77
|
$53
|
$130
|
Site
Development
|
$63
|
$75
|
$138
|
Site
Infrastructure
|
$32
|
($8)
|
$24
|
Permanent
Power
|
$17
|
$24
|
$41
|
Owner Pre-Production
G&A
|
$25
|
$30
|
$55
|
Project
Indirects
|
$75
|
$57
|
$132
|
Sub
Total
|
$482
|
$257
|
$739
|
Contingency
|
$28
|
$33
|
$61
|
Total
EAC
|
$510
|
$290
|
$800
|
While the Project has experienced capital increases in several
areas, the largest increases have been related to cost increases,
inflation and COVID-19 impacts as well as changes in scope for site
development, the TMF and permanent power.
In this press release and the subsequent conference call and
webcast, Argonaut aims to walk through the main areas of the
Project in detail to provide an understanding of where and why
capital has increased in those areas.
EAC Variances by Category (CAD $M)
Area
|
Cost/
Inflation
/COVID-
19
|
Scope
|
Quantities
|
Schedule
Recovery
|
Contin-
gency
|
Total
Variance
|
Process
Facilities
|
$3
|
$11
|
-
|
$12
|
-
|
$26
|
TMF
|
$17
|
$25
|
$12
|
-
|
-
|
$53
|
Site
Development
|
$21
|
$30
|
$24
|
-
|
-
|
$75
|
Site
Infrastructure
|
$7
|
($15)
|
-
|
-
|
-
|
($9)
|
Permanent
Power
|
-
|
$24
|
-
|
-
|
-
|
$24
|
Owner Pre-Production
G&A
|
$15
|
$2
|
$5
|
$9
|
-
|
$31
|
Project
Indirects
|
$31
|
$4
|
$18
|
$4
|
-
|
$57
|
Contingency
|
-
|
-
|
-
|
-
|
$33
|
$33
|
Total
Project
|
$94
|
$80
|
$58
|
$25
|
$33
|
$290
|
There are several areas that have led to the increase in the
Project capital estimate. The Company estimates impacts from
cost increases, inflation and COVID-19 account for approximately
32% of the capital increase. Changes in scope account for
approximately 28% of the capital increase and primarily relate to
site development, the TMF and permanent power. Approximately
20% of the increase in capital is related to increases in
quantities, primarily in site development and project indirects
areas. Due to the initial challenges in civil works, primarily at
the process facilities site, this area of the Project is currently
behind schedule. Argonaut is able to recover the schedule in
this area due to schedule compression where multiple trades will
work in parallel; however, there is a cost associated with
compressing the schedule. When the Company examined the cost
of schedule recovery compared to delaying the entire project, it
was more economic to compress and recover the schedule than delay
the overall Project. The Company estimates 8% of the increase
in capital for the Project is due to schedule recovery to meet
first gold pour by the end of March 2023. Each of these areas
are discuss in detail below.
Process Facilities (CAD $M)
Process
Facilities
October 2020 EAC
|
Schedule
Recovery
|
Scope
|
Cost
/Inflation/
COVID-19
|
Current
EAC
|
$193
|
$12
|
$11
|
$2
|
$219
|
Argonaut has been largely shielded from cost increases and
inflation in the area of process facilities due to its EPC contract
with Ausenco Engineering Canada Inc. ("Ausenco"). The largest
increases associated with process facilities capital are related to
an increase in earthwork quantities and previously unbudgeted lean
concrete and aggregate in order to prepare the foundation for the
plant site. The uneven nature of the surface bedrock, once
exposed below the glacial till, required much more time and capital
to create a suitable foundation area than originally estimated. The
additional work to prepare this area led to delays in delivering
the plant site to Ausenco. Argonaut and Ausenco have worked
together to finalize a recovery schedule for the plant site, and
the overall Project remains on schedule for first gold pour by the
end of March 2023. Increases in plant and facilities costs are
primarily related to the late delivery of the plant site to
Ausenco, which required schedule compression and investment into
operational readiness.
TMF (CAD $M)
TMF October 2020
EAC
|
Scope
|
Cost/
Inflation/
COVID-19
|
Quantities
|
Other
|
Deferral to
Sustaining
Capital
|
Current
EAC
|
$77
|
$25
|
$20
|
$12
|
$3
|
($7)
|
$130
|
Increases in capital for the TMF are primarily related to a
change in scope to include bedrock cleaning and slush grout and
increased quantities along with higher unit cost for sand cement
bentonite. There were also increases in both unit cost and
quantities for the embankment filter, which was partially offset by
a reduction in embankment mine rock fill due to a lower dam
elevation plan at construction completion. The remaining embankment
mine rock fill to reach the required dam elevation has been
reallocated to sustaining capital, as this work can be completed
after start up of operations.
Site Development (CAD $M)
Site
Development
October 2020 EAC
|
Scope
|
Quantities
|
Cost/
Inflation/
COVID-19
|
Other
|
Current
EAC
|
$63
|
$30
|
$24
|
$16
|
$6
|
$138
|
The largest increases in capital associated with site
development were driven by the construction environmental
management plan ("CEMP") and permit requirements with respect to
site access. As part of the CEMP, the Company was required to
construct 11 water dams for water management that were not
estimated in the October 2020
EAC. Dewatering costs were also not included in the
October 2020 EAC.
Site Infrastructure (CAD $M)
Site
Infrastructure
October 2020 EAC
|
Cost/
Inflation/
COVID-19
|
Scope
|
Other
|
Deferral to
Sustaining
Capital
|
Current
EAC
|
$32
|
$7
|
$2
|
($3)
|
($15)
|
$24
|
The Company has deferred capital associated with the truck shop
and site office complex to sustaining capital. Argonaut has
instead purchased and renovated a building in the town of
Dubreuilville, Ontario near the
Magino site that serves as offices. Cost increases and inflation
are primarily related to the costs associated with the main camp,
plant maintenance building and warehouse.
Permanent Power (CAD $M)
Permanent
Power
October 2020 EAC
|
Scope
|
Current
EAC
|
$18
|
$24
|
$41
|
After further study, there was significant risk to the Project
on timing and cost for delivery of line power by upgrading the
existing system. Therefore, there was a scope change from the
October 2020 EAC, and the Company now
envisions having a liquefied natural gas power plant on site.
Owner Pre-Production G&A (CAD $M)
Owner
Pre-Production
G&A October 2020 EAC
|
Cost/
Inflation/
COVID-19
|
Schedule
Recovery
|
Quantities
|
Scope
|
Other
|
Current
EAC
|
$25
|
$19
|
$9
|
$5
|
$2
|
($4)
|
$55
|
The largest increase in owner pre-production G&A is
primarily related to increased labour cost and cost associated with
Argonaut's COVID-19 testing programs. Also, in order to maintain
Project schedule, additional headcount is required during
construction.
Project Indirects (CAD $M)
Project
Indirects
October 2020 EAC
|
Cost/
Inflation/
COVID-19
|
Quantities
|
Scope
|
Schedule
Recovery
|
Current
EAC
|
$75
|
$31
|
$18
|
$4
|
$4
|
$132
|
The increase in capital in Project indirects is primarily due to
additional services required for the main camp and associated with
offsite accommodations such as the temporary camp for Argonaut's
earthworks contractor as well as housing in both Dubreuilville and Wawa, Ontario. There were also increases
in third-party engineering costs as well as construction management
costs.
Magino Technical Report
Argonaut is in the process of preparing an updated National
Instrument ("NI") 43-101 Technical Report for the Magino project,
which it expects will be published during the first quarter of
2022. In the interest of finalizing the updated technical
report in a timely manner, this updated report will be focused on
the Project currently under construction and will not include
expansion opportunities, including future potential underground
mining. The updated report will include the current EAC and
other items including, but not limited to, revised gold price
assumptions, an updated mineral resource model which includes all
grade control drilling data to date, optimizations to equipment
sizing and the processing facilities, updated operating cost and
sustaining capital. While the updated report will not
contemplate expansion potential and future potential underground
mining, Argonaut believes that these are future opportunities for
Magino.
Remaining Required Investment to Project Completion (CAD
$M)
Area
|
Forecasted
Spend
through
December
31, 2021
|
Q1
2022
|
Q2
2022
|
Q3
2022
|
Q4
2022
|
Q1
2023
|
Q2
2023
|
Total
|
Process
Facilities
|
$110
|
$54
|
$14
|
$23
|
$11
|
$5
|
$3
|
$219
|
TMF
|
$45
|
$24
|
$21
|
$15
|
$13
|
$9
|
-
|
$128
|
Site
Development
|
$80
|
$21
|
$18
|
$13
|
$8
|
-
|
-
|
$140
|
Site
Infrastructure
|
$1
|
$1
|
$8
|
$10
|
$4
|
-
|
-
|
$24
|
Permanent
Power
|
$4
|
$10
|
$10
|
$9
|
$9
|
-
|
-
|
$41
|
Owner Pre-Production
G&A
|
$20
|
$10
|
$5
|
$5
|
$6
|
$9
|
-
|
$55
|
Project
Indirects
|
$70
|
$16
|
$15
|
$15
|
$11
|
$5
|
-
|
$132
|
Contingency
|
$12
|
$16
|
$11
|
$11
|
$7
|
$3
|
-
|
$61
|
Total
Project
|
$342
|
$152
|
$103
|
$101
|
$68
|
$32
|
$3
|
$800
|
Argonaut forecasts it will have invested $342 million into the Project at the end of
2021. The Company estimates it will invest $424 million in 2022 and $35 million during the first half of 2023 to
complete the Project.
Liquidity Outlook
The Company forecasts it will end 2021 with approximately
US$230 million (~$290 million CAD) available between its cash and
existing revolving credit facility. As well, Argonaut's
existing consolidated operating portfolio is expected to generate
positive cash flow throughout the remainder of the Project at the
current gold price. However, at the current gold price, the
Company expects there to be a funding shortfall to complete the
Project. Therefore, Argonaut is conducting a review of its
financing and strategic alternatives.
Level of Confidence Going Forward
Argonaut has a much higher level of confidence in the current
EAC now that it is a year into the Project, has worked through the
process facilities' foundational preparation challenges that were
encountered due to rock unevenness, stripped approximately 75% of
the TMF area and completed construction of approximately 20% of the
TMF. Going forward, many of the unknowns when the Project
commenced were in the area of civil works and are now very well
known. The bulk of the remaining work is primarily
construction-related (i.e. bolting items together). With the
remaining civil work is better defined and understood, the Company
believes the risk of further significant increases to the EAC are
low with a significant contingency in place.
When evaluating the remaining investment required to complete
the Project that are critical to schedule and undertaking a
detailed risk assessment of all areas that make up the EAC, there
were seven areas that accounted for 90% of the risk for variance.
It is estimated that these seven areas account for approximately
60% of the remaining capital. Within these seven areas, as
detailed below, all have a reasonably high level of confidence
after a detailed risk assessment given either the high level of
engineering for these Project areas or the low level of complexity
for the remaining work.
Critical Areas of Remaining Investment to Project Completion
and Level of Engineering
Area
|
Percentage of
Engineering
Completed
|
Level of
Confidence in
Captial Estimate for Each
Area After Detailed Risk
Assessment
|
Process
Facilities
|
65%
|
90%
|
TMF
|
100%
|
85%
|
Power
Plant
|
2%
|
75%
|
Site Water
Management
|
85%
|
90%
|
Fish Habitat
Compensation
|
100%
|
85%
|
Camp
Facilities
|
100%
|
90%
|
Earthworks
Indirects
|
100%
|
90%
|
Dan Symons, Vice President,
Corporate Development and Investor Relations stated: "We are all
seeing cost increases, inflation and the impacts of COVID-19 in our
everyday lives and the Magino construction project is no
exception. However, we have a much higher degree of
confidence in the updated Magino capital estimate now that we are
nearly a year into the Project and have vastly reduced the unknowns
around civil works both at the plant site and TMF. We
anticipate ending the year with approximately $290 million (US$230
million) in liquidity between our cash and existing
revolving credit facility, and we also anticipate positive cash
flow from the existing operating portfolio through the remainder of
the Magino construction project. Yet given the substantial
increase in the Magino construction capital estimate, we now expect
a funding shortfall to see the Project through to completion, and
we are conducting an immediate review of both financing and
strategic alternatives."
Argonaut Gold Magino EAC Conference Call and Webcast:
The Company will host conference call and webcast at
10:00 am EST today, Tuesday, December 14, 2021 to discuss the current
Magino EAC.
Conference Call Information
Toll Free (North
America):
|
1-888-664-6392
|
International:
|
1-416-764-8659
|
Conference
ID:
|
63421174
|
Webcast:
|
www.argonautgold.com
|
Conference Call Replay:
Toll Free Replay Call
(North America):
|
1-888-390-0541
|
International Replay
Call:
|
1-416-764-8677
|
Replay Entry
Code:
|
421174#
|
The conference call replay will be available from 1:00 pm EST on December
14, 2021 until 11:59 pm EST on
December 21, 2021.
Qualified Person, Technical Information and Mineral
Properties Reports
Technical information in this release was supervised and
approved by Brian Arkell, Argonaut's
Vice President, Exploration and Mine Technical Services, and a
Qualified Person under NI 43-101. For further information on
the material mineral properties, please see the reports listed
below on the Company's website or on www.sedar.com:
El Castillo
Complex
Mine
|
NI 43-101 Technical
Report on Resources and Reserves, El Castillo Complex,
Durango, Mexico dated March 27, 2018 (effective date of March 7,
2018)
|
La Colorada
Mine
|
NI 43-101 Technical
Report on Resources and Reserves, La Colorada Gold/Silver
Mine, Hermosillo, Mexico dated March 27, 2018 (effective date of
December 8,
2017)
|
Florida Canyon
Gold Mine
|
NI 43-101 Technical
Report on Mineral Resource and Mineral Reserve Florida
Canyon Gold Mine Pershing County, Nevada, USA dated July 8, 2020
(effective date
June 1, 2020)
|
Magino Gold
Project
|
Feasibility Study
Technical Report on the Magino Project, Ontario, Canada dated
December 21, 2017 (effective date November 8, 2017)
|
Cerro del Gallo
Project
|
Pre-Feasibility Study
Technical Report on the Cerro del Gallo Project, Guanajuato,
Mexico dated January 31, 2020 (effective date of October 24,
2019)
|
Cautionary Note Regarding Forward-looking Statements
This press release contains certain "forward-looking statements"
and "forward-looking information" under applicable Canadian
securities laws concerning the business, operations and financial
performance and condition of Argonaut Gold Inc. ("Argonaut" or
"Argonaut Gold"). Forward-looking statements and forward-looking
information include, but are not limited to statements with respect
to the Magino EAC, the realization of mineral reserve estimates;
the timing and amount of estimated future production; costs of
production; estimated production and mine life of the various
mineral projects of Argonaut; timing of approval for modifications
to existing permits; permitting and legal processes in relation to
mining permitting and approval; the benefits of the development
potential of the properties of Argonaut; the future price of gold,
copper, and silver; the estimation of mineral reserves and
resources; success of exploration activities; and currency exchange
rate fluctuations. Except for statements of historical fact
relating to Argonaut, certain information contained herein
constitutes forward-looking statements. Forward-looking statements
are frequently characterized by words such as "plan," "expect,"
"project," "intend," "believe," "anticipate", "estimate" and other
similar words, or statements that certain events or conditions
"may", "should" or "will" occur. Forward-looking statements are
based on the opinions and estimates of management at the date the
statements are made and are based on a number of assumptions and
subject to a variety of risks and uncertainties and other factors
that could cause actual events or results to differ materially from
those projected in the forward-looking statements. Many of these
assumptions are based on factors and events that are not within the
control of Argonaut and there is no assurance they will prove to be
correct.
Factors that could cause actual results to vary materially from
results anticipated by such forward-looking statements include the
possibility of project cost overruns or unanticipated costs and
expenses; variations in ore grade or recovery rates; changes
in market conditions; risks relating to the availability and
timeliness of permitting and governmental approvals; risks relating
to international operations; fluctuating metal prices and currency
exchange rates; changes in project parameters; labour disputes and
other risks of the mining industry, failure of plant, equipment or
processes to operate as anticipated.
These factors are discussed in greater detail in Argonaut's most
recent Annual Information Form and in the most recent Management's
Discussion and Analysis filed on SEDAR, which also provide
additional general assumptions in connection with these statements.
Argonaut cautions that the foregoing list of important factors is
not exhaustive. Investors and others who base themselves on
forward-looking statements should carefully consider the above
factors as well as the uncertainties they represent and the risk
they entail. Argonaut believes that the expectations reflected in
those forward-looking statements are reasonable, but no assurance
can be given that these expectations will prove to be correct and
such forward-looking statements included in this press release
should not be unduly relied upon. These statements speak only as of
the date of this press release.
Although Argonaut has attempted to identify important factors
that could cause actual actions, events, or results to differ
materially from those described in forward-looking statements,
there may be other factors that cause actions, events or results
not to be anticipated, estimated or intended. There can be no
assurance that forward-looking statements will prove to be
accurate, as actual results and future events could differ
materially from those anticipated in such statements. Argonaut
undertakes no obligation to update forward-looking statements if
circumstances or management's estimates or opinions should change
except as required by applicable securities laws. The reader is
cautioned not to place undue reliance on forward-looking
statements. Statements concerning mineral reserve and resource
estimates may also be deemed to constitute forward-looking
statements to the extent they involve estimates of the
mineralization that will be encountered if the property is
developed. Comparative market information is as of a date prior to
the date of this document.
About Argonaut Gold
Argonaut Gold is a Canadian gold company engaged in exploration,
mine development and production. Its primary assets are the
El Castillo mine and San Agustin mine, which together form the El
Castillo Complex in Durango,
Mexico, the La Colorada
mine in Sonora, Mexico and the
Florida Canyon mine in Nevada,
USA. The Company also holds the construction stage Magino
project, the advanced exploration stage Cerro del Gallo project and several other
exploration stage projects, all of which are located in North
America.
Argonaut Gold Inc.
Dan
Symons
Vice President, Corporate Development & Investor Relations
Phone: 416-915-3107
Email: dan.symons@argonautgold.com
Source: Argonaut Gold Inc.
SOURCE Argonaut Gold Inc.