Fortuna Silver Mines, Inc. (NYSE:FSM) (TSX:FVI) is
pleased to announce 2017 production figures from its two
underground operating silver mines, the San Jose Mine in Mexico and
the Caylloma Mine in Peru. The company produced 8.5 million
ounces of silver and 56.4 thousand ounces of gold or 11.9 million
AgEq1 ounces.
2017 Consolidated Production
Highlights
- Silver and gold production were 4 %
and 8 % respectively above 2017 guidance
- Silver production of 8,469,593
ounces; 15 % increase over 2016
- Gold production of 56,441 ounces;
21 % increase over 2016
- Zinc production of 44,347,035
pounds; 3 % increase over 2016
- Lead production of 29,877,890
pounds; 9 % decrease over 2016
Note: 1. Silver equivalent is calculated using
silver to gold ratio of 60 to 1
2017 Consolidated Operating
Results
|
Q4 2017 |
2017 |
|
Caylloma,Peru |
San Jose,Mexico |
Consolidated |
Caylloma,Peru |
San Jose,Mexico |
Consolidated |
Processed Ore |
|
|
Tonnes milled |
134,635 |
271,370 |
|
529,704 |
1,070,791 |
|
Average tpd milled |
1,496 |
3,015 |
|
1,484 |
3,035 |
|
Silver |
|
|
Grade (g/t) |
65 |
259 |
|
66 |
238 |
|
Recovery (%) |
84.69 |
91.86 |
|
84.31 |
91.82 |
|
Production (oz) |
238,414 |
2,071,762 |
2,310,176 |
943,038 |
7,526,555 |
8,469,593 |
|
Q4 2017 |
2017 |
|
Caylloma,Peru |
San Jose,Mexico |
Consolidated |
Caylloma,Peru |
San Jose,Mexico |
Consolidated |
Gold |
|
|
Grade (g/t) |
0.18 |
1.89 |
|
0.18 |
1.77 |
|
Recovery (%) |
13.85 |
92.17 |
|
15.87 |
91.62 |
|
Production (oz) |
106 |
15,177 |
15,283 |
491 |
55,950 |
56,441 |
Lead |
|
|
Grade (%) |
2.91 |
|
|
2.81 |
|
|
Recovery (%) |
90.75 |
|
|
91.06 |
|
|
Production (lbs) |
7,846,302 |
|
7,846,302 |
29,877,890 |
|
29,877,890 |
Zinc |
|
|
Grade (%) |
4.36 |
|
|
4.21 |
|
|
Recovery (%) |
90.14 |
|
|
90.23 |
|
|
Production (lbs) |
11,676,397 |
|
11,676,397 |
44,347,035 |
|
44,347,035 |
Note: Metallurgical recovery for silver at the
Caylloma Mine is calculated based on silver content in lead
concentrate
San Jose Mine, Mexico
The San Jose Mine produced 2,071,762 ounces of
silver and 15,177 ounces of gold in the fourth quarter, 15 % and 16
% above budget respectively. Average head grades for silver
and gold were 259 g/t and 1.89 g/t, 12 % and 13 % above budget
respectively.
Silver and gold production for 2017 totaled 7.5
million ounces and 55,950 ounces respectively; being 5 % and 8 %
above the mine’s annual guidance. Average head grades for
silver and gold were 238 g/t and 1.77 g/t, 3 % and 6 % above the
mine’s annual guidance respectively.
In 2017, mine production was sourced from
Trinidad Central and Trinidad North with each area contributing 57
% and 43 % of ore respectively. The processing plant treated
an average of 3,035 tpd.
Caylloma Mine, Peru
The Caylloma Mine produced 238,414 ounces of
silver in the fourth quarter, 8 % below budget. Average
silver head grade of 65 g/t, 13 % below budget, was offset by
higher metallurgical recovery of 84.69%, 6 % above
budget.
Silver production for 2017 totaled 943,038
ounces; 4 % below the mine’s annual guidance. Average head grade
for silver was 66 g/t, 7 % below the mine’s annual guidance.
Lead and zinc production for the fourth quarter
was 7,846,302 pounds and 11,676,397 pounds respectively, 4 % below
budget and 13 % above budget. Average head grades for lead
and zinc were 2.91% and 4.36%, 1 % below budget and 13 % above
budget respectively.
Base metals production for 2017 totaled
29,877,890 pounds of lead and 44,347,035 pounds of zinc; in line
with annual guidance and 8 % above the mine’s annual guidance,
respectively. Average head grades for lead and zinc were 2.81% and
4.21%, 3 % and 9 % above annual guidance.
In 2017, mine production was sourced primarily
from the Animas NE and Animas Central areas with each contributing
58 % and 32 % of ore respectively. The processing plant
treated an average of 1,484 tpd.
2018 Consolidated Production and Cash
Cost Guidance
|
|
Silver(Moz) |
Gold(koz) |
Lead(Mlbs) |
Zinc(Mlbs) |
Cash Cost($/t) |
AISC1($/oz
Ag) |
|
|
|
San Jose
Mine, Mexico |
|
7.5 |
48.3 |
|
NA |
|
NA |
61.2 |
6.6 |
|
|
|
|
Caylloma Mine, Peru |
|
0.8 |
-- |
|
25.8 |
|
44.8 |
81.3 |
(5.2 |
) |
|
|
|
|
Total |
|
8.3 |
48.3 |
|
26.5 |
|
44.1 |
|
|
|
- 2018 silver equivalent2 production guidance of 11.4 million
ounces
- 2018 consolidated AISC1 of $6.8/oz Ag
Notes:
- All-in sustaining cash cost (AISC) per ounce of silver is net
of by-products gold, lead and zinc;
see appendix for breakdown
- Silver equivalent production does not include lead or zinc and
is calculated using a silver to gold ratio of 65 to 1
- Total figures may not add due to rounding
2018 Outlook
San Jose Mine, Mexico
San Jose plans to process 1,050,000 tonnes of
ore averaging 240 g/t Ag and 1.56 g/t Au. Capital investments are
estimated at $16.9 million; includes $8.5 million for sustaining
CAPEX1 and $8.4 million for exploration programs.
Major capital investment projects include:
- Mine development:
$3.5 million
- Equipment and
infrastructure:
$4.1 million
Note: 1. Capital Expenditure
Caylloma Mine, Peru
Caylloma plans to process 535,500 tonnes of ore
averaging 57 g/t Ag, 2.41% Pb and 4.21% Zn. Capital investments are
estimated at $21.3 million; including $16.4 million for sustaining
CAPEX, $2.8 million for non-sustaining CAPEX, and $2.2 million for
Brownfields exploration programs.
Major capital investment projects include:
- Mine development:
$6.4 million
- Equipment and infrastructure:
$4.3 million
- Tailings dam expansion
$5.7
million
Non-sustaining investments of $2.8 million
relate to improving productivity and efficiency. Main projects
include power transmission capacity upgrade, mill flotation cells
upgrade and pavement of principal mine haulage ways. These
investments have payback periods ranging between 6 months and 3
years. The tailings dam expansion allows for additional storage
capacity until 2021.
Lindero gold Project,
Argentina
The initial capital cost for the construction of
Lindero is estimated at $239 million (see Fortuna news release
dated September 21, 2017). For 2018, capital expenditures are
estimated at $201 million, representing 84 % of the construction
budget.
Project Construction Milestones
Selected milestones from the project
construction schedule were released on December 2017 (see Fortuna
news release dated December 21, 2017) and include:
2018
- February: Start mass earthworks
- April: First concrete for permanent installations
- August: Start of equipment installation, including HPGR
tertiary crusher
- November: Construction of roads and platforms in preparation
for initiation of mining activities
2019
- January: Commissioning of power plant
- March: Placing of first ore on the leach pad
- May: First doré poured as part of commissioning
Brownfields Exploration
Highlights
San Jose Mine, Mexico
Brownfields exploration program budget for 2018
at the San Jose Mine is $8.4 million, which includes 45,500 meters
of diamond drilling and 340 meters of underground development for
drilling access and platforms. Exploration drilling will focus on
the Trinidad Central and Trinidad North zones and on the
sub-parallel Victoria vein.
Caylloma Mine, Peru
Brownfields exploration program budget for 2018
at the Caylloma Mine is $2.2 million, which includes 10,250 meters
of diamond drilling. Drilling will focus on a previously unexplored
area between ore shoots on the Animas NE vein that were discovered
in 2017 (see Fortuna news release dated October 11, 2017).
Lindero gold Project, Argentina
The Arizaro gold-copper porphyry target lies
within the Lindero Project concession block. We plan to investigate
the economic potential of including Arizaro mineralization into the
existing Lindero resource through additional surface mapping and
2,000 meters of core drilling targeting shallow, high-grade
copper-gold mineralization with a budget of $321,000.
The Company is also revisiting the extensive
reconnaissance exploration database comprising over fifteen years
of sampling and generative work in northern Argentina, acquired
from Goldrock Mines along with the Lindero Project in 2016.
Evaluation of new opportunities on third-party properties is
ongoing.
Greenfields Exploration Highlights
Serbia
Through two C$1.5 million equity investments in
Medgold Resources Corp. (TSX.V:MED), Fortuna funded a Strategic
Alliance with Medgold and joint ventured the Tlamino Project as its
first Selected Property (see Medgold news releases dated January 9,
2017, February 9, 2017, and March 7, 2017).
Exploration work on the Tlamino joint venture
will consist of 2,000 meters of core drilling with a budget of
$340,000. Fortuna retains the right to nominate a second Selected
Property over the course of 2018. Exploration remains centered on
high and low-sulfidation epithermal gold-silver mineralization in
the western portion of the Tethyan orogenic system. Each joint
venture, when formed, will allow Fortuna the right to earn a 51 %
interest by spending $3.0 million over three years, and gain an
additional 19 % interest by spending a further $5.0 million and
completing a preliminary economic assessment.
Mexico
Fortuna entered into an equity investment
agreement with Prospero Silver Corp. (TSX.V:PSL) in early 2017
(see Prospero Silver news release dated April 17, 2017). This
Strategic Alliance provides for the initial drilling of multiple
targets at Prospero’s Matorral, Petate, Pachuca SE and Bermudez
properties located in Durango, Hidalgo and Chihuahua States,
respectively. High-level epithermal clay alteration with anomalous
gold, silver or pathfinder elements are present at each property,
none of which has been previously drilled.
The agreement gives Fortuna the right to select
one of the projects to joint venture with Prospero, potentially
earning a 70 % interest by spending $8 million over six years and
completing a preliminary economic assessment on the selected
property. Should Fortuna exercise its Prospero warrants, the right
to select a second project under the same terms as above is
retained. The exploration strategy is to complete the planned
drilling at all targets, assess the data and select properties as
dictated by the results.
Drilling at the Matorral and Petate projects was
completed in 2017 (see Prospero Silver news releases dated
August 24, 2017, September 18, 2017, November 8, 2017, and January
10, 2018) and drilling at the Pachuca SE and Bermudez projects will
be completed during the first quarter of 2018.
Qualified Person
Edwin A. Gutierrez, Technical Services Corporate
Manager, is the Qualified Person for Fortuna Silver Mines Inc. as
defined by National Instrument 43-101. Mr. Gutierrez is a
Registered Member of the Society for Mining, Metallurgy and
Exploration, Inc. (SME Registered Member Number 4119110RM) and is
responsible for ensuring that the information contained in this
news release is an accurate summary of the original reports and
data provided to or developed by Fortuna Silver Mines.
About Fortuna Silver Mines
Inc.
Fortuna is a growth oriented, precious metal
producer with its primary assets being the Caylloma silver mine in
southern Peru, the San Jose silver-gold mine in Mexico and the
Lindero gold Project in Argentina. The company is selectively
pursuing acquisition opportunities throughout the Americas and in
select other areas. For more information, please visit its
website at www.fortunasilver.com.
ON BEHALF OF THE BOARD
Jorge A. Ganoza President, CEO and
DirectorFortuna Silver Mines Inc.
Trading symbols: NYSE:FSM | TSX:FVI
Investor Relations:
Carlos Baca- T (Peru): +51.1.616.6060, ext.
0
Forward looking Statements
This news release contains forward looking
statements which constitute “forward looking information” within
the meaning of applicable Canadian securities legislation and
“forward looking statements” within the meaning of the “safe
harbor” provisions of the Private Securities Litigation Reform Act
of 1995 (collectively, “Forward looking Statements”). All
statements included herein, other than statements of historical
fact, are Forward looking Statements and are subject to a variety
of known and unknown risks and uncertainties which could cause
actual events or results to differ materially from those reflected
in the Forward looking Statements. The Forward looking Statements
in this news release may include, without limitation, statements
about the Company’s plans for its mines and mineral properties,
including the Lindero gold Project; the Company’s business
strategy, plans and outlook; the merit of the Company’s mines and
mineral properties; mineral resource and reserve estimates;
timelines; the future financial or operating performance of the
Company; expenditures; approvals and other matters. Often, but not
always, these Forward looking Statements can be identified by the
use of words such as “estimated”, “potential”, “open”, “future”,
“assumed”, “projected”, “used”, “detailed”, “has been”, “gain”,
“planned”, “reflecting”, “will”, “containing”, “remaining”,
“to be”, or statements that events, “could” or “should” occur or be
achieved and similar expressions, including negative
variations.
Forward looking Statements involve known and
unknown risks, uncertainties and other factors which may cause the
actual results, performance or achievements of the Company to be
materially different from any results, performance or achievements
expressed or implied by the Forward looking Statements. Such
uncertainties and factors include, among others, whether the
Company’s activities at the Lindero gold Project will proceed as
planned; changes in general economic conditions and financial
markets; changes in prices for silver and other metals;
technological and operational hazards in Fortuna’s mining and mine
development activities; risks inherent in mineral exploration;
uncertainties inherent in the estimation of mineral reserves,
mineral resources, and metal recoveries; governmental and other
approvals; political unrest or instability in countries where
Fortuna is active; labor relations issues; as well as those factors
discussed under “Risk Factors” in the Company's Annual Information
Form. Although the Company has attempted to identify important
factors that could cause actual actions, events or results to
differ materially from those described in Forward looking
Statements, there may be other factors that cause actions, events
or results to differ from those anticipated, estimated or
intended.
Forward looking Statements contained herein are
based on the assumptions, beliefs, expectations and opinions of
management, including but not limited to: that the Company’s
activities at the Lindero gold Project will proceed as planned;
expectations regarding mine production costs; expected trends in
mineral prices and currency exchange rates; the accuracy of the
Company’s current mineral resource and reserve estimates; that the
Company’s activities will be in accordance with the Company’s
public statements and stated goals; that there will be no material
adverse change affecting the Company or its properties; that all
required approvals will be obtained; that there will be no
significant disruptions affecting operations and such other
assumptions as set out herein. Forward looking Statements are made
as of the date hereof and the Company disclaims any obligation to
update any Forward looking Statements, whether as a result of new
information, future events or results or otherwise, except as
required by law. There can be no assurance that Forward looking
Statements will prove to be accurate, as actual results and future
events could differ materially from those anticipated in such
statements. Accordingly, investors should not place undue reliance
on Forward looking Statements.
This news release also refers to non-GAAP
financial measures, such as cash cost per tonne of processed ore;
cash cost per payable ounce of silver; total production cost per
tonne; all-in sustaining cash cost; all-in cash cost; adjusted net
(loss) income; operating cash flow per share before changes in
working capital, income taxes, and interest income; and adjusted
EBITDA. These measures do not have a standardized meaning or method
of calculation, even though the descriptions of such measures may
be similar. These performance measures have no meaning under
International Financial Reporting Standards (IFRS) and therefore,
amounts presented may not be comparable to similar data presented
by other mining companies.
Appendix
2018 AISC Guidance Breakdown
San Jose Mine:
Item |
$/oz Ag |
Cash cost net of by-product credits |
1.4 |
Commercial and government royalties/mining tax |
1.2 |
Workers’ participation |
0.9 |
Subsidiary G&A |
0.7 |
Sustaining capex |
1.2 |
Brownfields exploration |
1.2 |
AISC |
6.6 |
Caylloma Mine:
Item |
$/oz Ag |
Cash cost net of by-product credits |
(40.3 |
) |
|
Commercial and government royalties/mining tax |
4.1 |
|
|
Workers’ participation |
2.4 |
|
|
Subsidiary G&A |
4.7 |
|
|
Sustaining capex |
21.1 |
|
|
Brownfields exploration |
2.8 |
|
|
AISC |
(5.2 |
) |
|
Consolidated:
Item |
$/oz Ag |
Cash cost net of by-product credits |
(2.7 |
) |
|
Commercial and government royalties/mining tax |
1.5 |
|
|
Workers’ participation |
1.1 |
|
|
Subsidiary G&A |
1.1 |
|
|
Corporate G&A |
1.4 |
|
|
Sustaining capex |
3.1 |
|
|
Brownfields exploration |
1.3 |
|
|
AISC |
6.8 |
|
|
Note: Total figures may not add up due to
rounding
Prospero Silver (TSXV:PSL)
Historical Stock Chart
From Oct 2024 to Nov 2024
Prospero Silver (TSXV:PSL)
Historical Stock Chart
From Nov 2023 to Nov 2024