African Copper Mowana Mine Update

- Concentrate currently being stockpiled for commencement of first shipment during September

- Mining to date shows higher mixed ore at better grades than previously modelled

- Increased presence of supergene mineralisation should provide overall improved recoveries

- Further optimisation of mining plans and ore reserves ongoing

LONDON, UNITED KINGDOM--(Marketwire - Sept. 17, 2008) - African Copper Plc ("African Copper" or "the
Company")(TSX:ACU)(AIM:ACU)(BOTSWANA:AFRICAN COPPER) is pleased to provide shareholders with an update
on the progress at the Mowana open pit mine in Botswana.

The commissioning of the mill is in its final stage following the successful resolution of some issues
with the mill's bearings and lubrication system during the commissioning process. Concentrate is
currently being stockpiled for commencement of first shipment during September. High grade ore is now
being put through the mill and the engineering, procurement, construction and management contractor is
currently undertaking the completion guarantees and will hand over the mill to African Copper during
September 2008. The period from the start of construction to final commissioning has been less than 24
months.

The mining operations, which commenced in January 2008, continue to perform well with over 850,000
tonnes of ore stockpiled, including 300,000 tonnes at 1.74% copper as at 8th September 2008. This
represents approximately 9 months of production, based on the mill capacity of 1 million tonnes per
annum.

The mining operations have now exposed ore along a 1.5 kilometre strike within the pit and have shown
an increased presence of supergene (high grade Chalcocite) mineralisation at shallow depths, compared
with the geological resource model which had anticipated primarily oxide mineralisation at these
elevations. For information on the geological resource model see Mineral Resource and Mineral Reserve
Estimates included in the report entitled "National Instrument 43-101 Technical Report On The Mowana
Mine, Botswana" dated 26 November 2007 by Read, Swatman & Voigt (Pty) Ltd. (the "Technical Report"),
which is available on www.sedar.com or on the Company's website.

As a result of the increased presence of supergene mineralisation, the mixed ore grades encountered
are higher than the oxide mineralisation grade predicted in the geological resource model. The current
operational strategy allows the segregation of stockpile ore into a high grade direct mill feed
stockpile and a Dense Medium Separation ("DMS") plant feed stockpile.

African Copper has also recently undertaken a reconciliation exercise between the geological resource
model and all the blocks mined to the end of July 2008. This indicates that higher ore grades are
being mined, primarily due to presence of mixed ore and operational grade control measures.

/T/

--------------------------------------------------------------------------
                                    Modelled                         Mined
--------------------------------------------------------------------------
                   Tonnes    Grade    Copper    Tonnes    Grades    Copper
                                       Units                         Units
--------------------------------------------------------------------------
Direct Feed       439,455     1.16%    5,084   224,031      1.78%    3,892
--------------------------------------------------------------------------
DMS               418,089     0.22%      903   487,660      0.62%    3,020
--------------------------------------------------------------------------
Total Ore         857,544     0.70%    5,987   711,691      0.97%    6,912
--------------------------------------------------------------------------
Total Net
 Gain (Loss)                                     -17.0%     39.1%     15.5%
--------------------------------------------------------------------------

/T/

A further in-pit reconciliation of the 980mL bench in the south of the pit confirms the above trend
and has indicated lower ore tonnages (27% decrease) but a significant increase (57%) in contained
copper as a result of higher grades.

The impact on the operation of a higher amount of mixed ore at better grades than previously modelled
is threefold. Firstly, due to the higher grades in the DMS stockpile material, the Company is
considering bringing forward the introduction of a DMS plant from 2010 to the third quarter 2009,
which is part of the detailed mine review underway and, if proceeded with, will require additional
financing. Secondly, higher input grades to the DMS will result in improved mill feed grade from the
DMS. Thirdly, the increased presence of supergene material will result in the direct mill feed having
approximately 25% higher overall recoveries than the oxide recoveries previously modelled.

African Copper will carry out a full mass balance reconciliation as mined material is processed
through the plant which is expected to lead to a re-assessment of Mowana's mineral reserves and
resources. This will be integrated into the mine plan that is currently under review.

This press release has been prepared under the supervision of James Arthur, FSAIMM, the General
Manager of the Mowana Mine and a "qualified person" within the meaning of Canadian National Instrument
43-101 - Standards of Disclosure for Mineral Projects. Mr. Arthur has verified the data disclosed in
this press release.

This press release contains or refers to forward-looking information, including statements regarding
estimates and/or assumptions about the first shipment of concentrate, the Company's plan and
expectations with respect to bringing forward the introduction of the DMS plant to the third quarter
of 2009, the Company's beliefs and expectations with respect to obtaining improved mill feed grade
from the DMS plant, the Company's expectations with respect to realizing improved recoveries, the
Company's expectations of completing a full mass balance reconciliation and reassessment of the Mowana
Mine's mineral resources and reserves, potential mineralization, potential mineral resources and
reserves, mine development plans, recoveries and timing of the commencement of operations, and is
based on current expectations that involve a number of business risks and uncertainties. Actual
results may vary from the forward-looking information contained herein. Factors that could cause
actual results to differ materially from any forward-looking information include, but are not limited
to, uncertainty regarding failure to convert estimated mineral resources to reserves, the possibility
that actual circumstances will differ from the estimates and assumptions used in the mining plan for
Mowana Mine (there is no certainty that the production schedule, recoveries and/or operating costs
proposed will be achieved), the grade and recovery of ore which is mined varying from estimates
(including, in particular the inferred mineral resources included in the mine plan not being
recoverable at the grade and/or volume used in the calculation of estimated operating costs), the
capital and operating costs varying significantly from estimates, political risks arising from
operating in Africa, uncertainties relating to the availability and costs of financing needed in the
future (including to build the DMS plant and complete the development of the Mowana Mine), changes in
equity and/or debt markets, inflation, changes in exchange rates, fluctuations in commodity prices,
delays in the development of projects and the other risks involved in the mineral exploration and
development industry. When used in this press release, words such as "schedule", "could", "plan",
"anticipate", "estimate", "expect", "believe", "intend", "will", "may" and similar expressions are
forward-looking statements.

Although the Company believes that its expectations reflected in this forward-looking information are
reasonable, such information involves risks and uncertainties and no assurance can be given that
actual results will be consistent with this forward-looking information. Forward-looking information
is subject to significant risks and uncertainties, and other factors that could cause actual results
to differ materially from expected results. Accordingly, readers should not place undue reliance on
forward-looking information. This forward-looking information is made as of the date hereof and the
Company assumes no responsibility to update it or to revise it to reflect new events or circumstances,
except as required by law.


For further information please visit: www.africancopper.com.


-30-

FOR FURTHER INFORMATION PLEASE CONTACT:

African Copper Plc
Alex Buck
Investor Relations
+44 (0) 20 7244 8053 or +44 7932 740 452
Website: www.africancopper.com

OR

Numis Securities Limited
John Harrison
Nominated Adviser
+44 (0) 20 7260 1000

OR

Numis Securities Limited
James Black
Corporate Broker
+44 (0) 20 7260 1000

                                                                
African Copper



                                                                

African Copper (LSE:ACU)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more African Copper Charts.
African Copper (LSE:ACU)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more African Copper Charts.