27 November 2024
Prospex Energy plc
("Prospex Energy" or the "Company")
Viura-1B Well Test
Progress
Revenues from Viura-1B are Expected in
December
Prospex Energy plc (AIM:PXEN), the investment
company focused on European gas and power projects, wishes to
update shareholders on the schedule of the flow testing at the
Viura-1B development well, which is expected early in
December. The Viura-1B development well which has been
drilled by HEYCO Energy Iberia S.L. ("HEI") reached its revised
targeted Total Depth ("TD") of 4,500 metres, which is ≈4,100 metres
True Vertical Depth ("TVD"), on 21 October 2024 in the 6-inch hole
section of the bottom 450 metres of the well.
Prospex owns 7.2365% of the Viura field through
its ownership of 7.5% of HEI. Prospex will receive 14.473% of
the production income from the Viura gas field until payback of its
initial capital investment from the acquisition in August
2024.
The Viura-1B well is currently being connected
to the existing gas processing facilities on site in order to
prepare for the imminent flow testing programme, thus immediately
generating revenues, with production income expected early in
December 2024. Following flow testing, the well will be
placed on long-term production.
As previously reported, the Viura-1B well was
deepened by 450 metres in order to appraise the undrilled
Utrillas-B formation and assess if it was gas bearing. Having
confirmed the presence of gas-bearing reservoir quality sandstones
in the Utrillas-B, the operator completed this interval with a
cemented 4½ inch liner. The flow testing program for the
Utrillas B section will be performed during the planned plant
shut-down in H2 2025.
The drilling rig has been moved from the
Viura-1B well site location to the produced water disposal well
Viura-3 site in order to re-instate its operability to better
manage produced water from the existing Viura-1 ST3 production
well.
Mark Routh,
the CEO of Prospex, commented:
"The Viura-1B
development well has been successful and we await confirmation of
the anticipated flow rates from the substantial reservoir sections
encountered in the main reservoir target of the so-called
Utrillas-A formation. Analysis is ongoing to fully assess the
implications of the well results to the recoverable reserves from
the Viura field, the flow test numbers will enable confirmation
that the project has met and hopefully exceeded its pre-drill
objectives.
"I look
forward to updating shareholders with results from the flow testing
and further analysis as soon we have firm data to
share."
Further Information
About Viura:
Prior to drilling the current Viura-1B well,
the Viura producing gas field onshore in northern Spain had an
estimated gross original gas in place of 211 Bcf (6 Bcm) and
estimated reserves of 105 Bcf (3 Bcm). To date, just 16 Bcf
(0.5 Bcm) of gas has been produced from Viura meaning that the
remaining reserves were estimated as 90 Bcf (2.5 Bcm) which is 6.5
Bcf (0.18 Bcm) net to Prospex.
In Spain there are only three producing onshore
gas fields: El Romeral, Viura and Marismas. Prospex currently
owns a 49.9% share in El Romeral. HEI currently has a
58.7964% interest in Viura. The other participants in the
ownership of the Viura Field Development are Sociedad de
Hidrocarburos de Euskadi, S.A. ("SHESA") (owner of the 37.6901% of
the Concession) and Oil and Gas Skills, S.A. (owner of the 3.5135%
of the Concession). On 5 April 2024, HEI entered into an
asset purchase agreement with SHESA for the acquisition of the
participation of SHESA in the Viura Field Development, which is
subject to the fulfilment of certain conditions precedent.
Prospex through its 7.5% shareholding in HEI indirectly owns
7.2365% of the Viura concession, its reserves and the existing
surface production facilities of the Viura gas plant, which is
connected to the Spanish national grid.
HEI acquired its interest in the Viura gas
field and became operator in 2022. A new 3D seismic survey
was acquired in 2013. There is one well in production in the
field Viura-1 ST3, which had been shut in until
recently. This well produces intermittently as water
production is managed. There is a workover now underway on
the existing produced water disposal well Viura-3 to reinstate its
operability. HEI has permits in place to drill one further
development well, Viura-3B, scheduled to start in the second
quarter of 2025. Permits have been submitted to drill a third
development well on the concession Viura-3A batch drilled with
Viura-3B well in 2025.
The Viura-1B well commenced drilling operations
on 22 June 2024. The new investors (including Prospex) into
HEI are funding 31.58% of the development costs to earn 15.79%
ownership of HEI. Prospex is funding 15% of the development
costs of the HEI development programme comprising the current well
in 2024 and the proposed 2025 two well drilling programme to earn
7.5% ownership of HEI and indirectly 7.2365% of the Viura
asset.
Other new investors are funding 16.58% of the
development costs to earn an 8.29% ownership in HEI.
The two new wells to be drilled from the first
half of 2025 and completed in the second half of 2025 are to be
funded from revenues from existing and new production from Viura or
from new funds if required. Viura-1B is expected to be
generating revenues from production in early December 2024
following the completion of the testing programme. The 2025
development programme is to be funded by future cash calls or from
Phase 1 production or both.
There is a preferred pay-back mechanism for
Prospex and all participants (including HEGI and new investors) of
this new investment in HEI, the ("HEI Investors"). The HEI
Investors will enjoy a 10% interest on their capital investments
paid out from the existing and future production from Viura.
Until the HEI Investors have recovered their full capital
commitments, plus the 10% preferred interest return, HEGI will not
receive production income on their other 50% ownership of HEI over
and above operating expenses and an allowance for Spanish taxes and
royalties. This means that Prospex will earn 14.473% of the
revenues from the gas production from the Viura field until it has
achieved payback of the £4.2 million capital investment it made in
August 2024 to acquire the asset. The gross cost (including
the current Viura-1B well which has already been funded) of the
three phase, three-year Viura development programme is estimated at
a total of £55.4 million ($70.4 million). HEGI is funding
over 50% of that programme and the new HEI Investors are funding
31.58% through their interest in HEI which earns them an indirect
15.2368% ownership of the Viura asset (net 7.2365% to
Prospex).
Qualified
Person Signoff
In accordance with the AIM note for Mining and
Oil and Gas Companies, the Company discloses that Mark Routh, the
CEO and a director of Prospex Energy plc has reviewed the technical
information contained herein. Mark Routh has an MSc in
Petroleum Engineering and has been a member of the Society of
Petroleum Engineers since 1985. He has more than 40 years
operating experience in the upstream oil and gas industry.
Mark Routh consents to the inclusion of the information in the form
and context in which it appears.
For further
information, please contact:
Mark Routh
|
Prospex Energy PLC
|
Tel:
+44 (0) 20 7236 1177
|
Ritchie Balmer
Rory Murphy
David Asquith
|
Strand Hanson Limited
(Nominated Adviser)
|
Tel: +44
(0) 20 7409 3494
|
Andrew Monk (Corporate Broking)
Andrew Raca / Tommy Jackson (Corporate Finance)
|
VSA Capital Limited
|
Tel: +44
(0) 20 3005 5000
|
Ana Ribeiro / Charlotte
Page
|
St Brides Partners
Limited
|
Tel: +44
(0) 20 7236 1177
|
Further information on the Company can be found
on its website at www.prospex.energy.
Notes
Prospex Energy PLC is an AIM quoted
investment company focused on high impact onshore and shallow
offshore European opportunities with short timelines to
production. The Company's strategy is to acquire undervalued
projects with multiple, tangible value trigger points that can be
realised within 12 months of acquisition and then applying low-cost
re-evaluation techniques to identify and de-risk prospects.
The Company will rapidly scale up gas production in the short term
to generate internal revenues that can then be deployed to develop
the asset base and increase production further.
The Company currently has three
non-operated, revenue generating, onshore producing gas investments
in Europe with low operational risk:
• Selva
Malvezzi, northern Italy (37% interest)
• El Romeral
gas to power plant, southern Spain (49.9% interest)
• Viura Gas
Field, northern Spain (7.24% interest)
Prospex also owns a 15% interest in
the Tesorillo Exploration Permit in Southern Spain, with the option
to increase to 49.9%.
Glossary:
scm
Standard cubic
metres
scm/d
Standard cubic metres per
day
MMscm
Million standard cubic metres
MMscm/d
Million standard cubic metres per day
Bcm
Billion standard cubic
metres
Bcf
Billion standard
cubic feet
MMscfd
million standard cubic feet per day
MWh
Mega Watt hour
TTF
The 'Title Transfer
Facility' - a virtual trading point for natural gas in the
Netherlands.