March 13,
2024
NEWS RELEASE
LUCARA ANNOUNCES UPDATED FEASIBILITY
STUDY FOR KAROWE UNDERGROUND PROJECT
VANCOUVER, BC - March 13,
2024 /CNW/ (LUC - TSX, LUC - BSE, LUC -
Nasdaq Stockholm)
Lucara Diamond Corp. ("Lucara" or
the "Company") is pleased to announce the filing of a technical
report (the "Report") for the updated Feasibility Study ("FS" or
"Study"), prepared in accordance with National Instrument 43-101 -
Standards of Disclosure for
Mineral Projects ("NI 43-101") on its Underground Expansion
Project
("UGP" or "Project") at the Karowe Diamond Mine ("Karowe") located
in Botswana. The Report is titled "Karowe Mine - Botswana 2023
Feasibility Study Technical Report", with an effective date of June
30, 2023, and was prepared for Lucara by JDS Energy & Mining
Inc. The Report is available under the Company's profile on SEDAR+
at www.sedarplus.ca or from the Company's website at www.lucaradiamond.com.
Karowe is located in north-central Botswana, one of the world's most
prolific diamond producing areas, and is a producer of large, high
value type IIa diamonds and the only diamond mine to have produced
four diamonds in excess of 1,000 carats in size. The underground
expansion at Karowe is expected to double the mine life, and to
generate significant revenue and cashflow out to 2040, extending
benefits to the Company, its employees, shareholders, communities
surrounding the mine, and Botswana. The Report provides an update
to the 2019 underground feasibility study ("2019 FS") and 2021
financed base case to reflect changes to project duration, capital
expenditure, and technical updates to the Project. All amounts are
in U.S. dollars unless otherwise noted.
Combined Open Pit/ Underground
Highlights
· Extending mine life by 15 years;
· Total
life of mine ("LOM") diamond recoveries of 6.8 million
carats;
· Operational highlights include ~42.4 million tonnes of ore
mined and ~52.2 million tonnes of ore processed;
· Highest
value EM/PK(S) unit of the South Lobe is the dominant rock type
mined over the LOM of the underground; a significant source of many
large high value diamonds, including the 1,109 carat Lesedi La
Rona, the 549 carat Sethunya, and more recently the 1,080 carat
Type IIa white stone recovered in August 2023;
· Pre-production capital costs for the UGP totalling $683
million, to be expended over an eight-year pre-production
construction and commissioning period until H2/2027, of which three
and a half years have already been successfully
completed;
· The
UGP is projected to generate $1.1 billion in cash flow;
· Fully
financed project as announced on January 9, 2024
(link
to Press Release), when the
Company amended its debt package that was originally entered into
in 2021; and
· The
amended facilities consist of a project finance facility ("Project
Loan") of $190.0 million (previously $170.0 million) to fund
underground development, and a $30.0 million (previously $50.0
million) senior secured working capital facility (the "WCF") which
is used to support ongoing operations along with operating cash
flow from the Karowe open pit.
William Lamb, President and CEO of
Lucara Diamond Corp., commented: "Lucara is excited to share the
updated Feasibility Study for the Karowe Underground Expansion
Project, which reinforces our strategic decision to extend mine
life and continue to generate benefits for our stakeholders. Karowe
is a world-class mine, and we look forward to continuing to recover
large, exceptional diamonds from the South Lobe at
Karowe."
This report is updated from the
original 2019 UGP FS (link
to Press Release) and 2021 financed
base case (link
to Press Release) and encompasses the
following significant modifications:
· Project construction progress (surface infrastructure and
underground development) to June 30, 2023;
· Revised economic modelling with updated diamond prices and
exchange rates, exclusion of sunk costs and inclusion of financing
costs;
· Re-baselining the UGP schedule and as a result, the open pit
mine and processing facility production plans;
· Re-estimation of the current operations budgets and project
capital and operating cost projections;
· Modifications to the mine design;
· Fine
tailings storage and management;
· Advancement of detailed engineering designs;
· Re-modeling of the hydrogeological conditions;
· Underground dewatering and grouting methodology;
and
· Groundwater management on surface.
Project description
· The
UGP is focused on the South Lobe of the AK06 kimberlite;
· The
UGP is designed to support operation of a 2.7 million tonnes per
annum underground mine and processing plant;
· 8.5
metre finished internal diameter Production Shaft approximately 767
metres deep equipped to hoist a nominal 7,400
tonnes per day of ore and additional development waste;
· 6 metre finished internal diameter unequipped Ventilation
Shaft with a planned final depth of 729 metres;
· Extraction of approximately 400 vertical metres of the South
Lobe of the AK06 kimberlite from 310 metres above sea level
("masl") (700 metres below surface) to the bottom of the depleted
open pit (approximately 710 masl or 300 metres below
surface).
Key Operational
Parameters
Table 1: Key Operational
Parameters
Tonnage and Grade
|
Karowe Base
Case
|
Waste Tonnes mined
(millions)
|
3.5
|
Ore Tonnes mined
(millions)
|
42.4
|
Processed Tonnes
(millions)
|
52.2
|
Diamond grade (carats per hundred
tonne or "cpht")
based on a 1.25mm bottom cut-off
size
and inclusive of estimated mining
dilution
|
13.10
|
Recovered carats
(millions)
|
6.8
|
Diamond revenue ($
millions)
|
5,073
|
Mine Life (years)
|
~15
years
|
Source: 2023 FS
Feasibility Study
Approach
The FS has been prepared following
Canadian Institute of Mining Guidelines for the development of an
underground mine. Production from the underground is planned after
open pit operations have been completed and the Company will rely
on the processing of stockpiled material during the latter part of
the underground development and ramp-up to full production in Q1,
2028.
The results of the FS represent
forward-looking information that are subject to a number of risks,
uncertainties and other factors that may cause results to differ
materially from those presented here. (See "Cautionary Note
Regarding Forward Looking Statements" below.)
operating and Capital Cost
Estimates
The mine operating cost estimate for
the Karowe Project is based on a combination of experience,
reference projects, first principle calculations, budgetary quotes,
and factors as appropriate for a FS.
Table 2: Summary of Operating Cost Estimate
Operating Costs
|
Average
Annual(1)
|
Life of
Mine
|
Tonnes
Processed(2)
|
Unit Cost per tonne
Processed
|
Weighting
|
M$
|
M$
|
Mt
|
$/t
|
%
|
Open Pit Mining Costs
|
24.2
|
72.6
|
5.5
|
13.2
|
4
|
Underground Mining Costs
|
29.5
|
413.2
|
37.0
|
11.2
|
24
|
Rehandle Costs
|
3.4
|
23.6
|
9.7
|
2.4
|
1
|
Process Costs
|
24.7
|
493.7
|
52.2
|
9.5
|
29
|
Other Power Costs
|
5.3
|
105.2
|
52.2
|
2.0
|
6
|
G&A
|
18.3
|
365.8
|
52.2
|
7.0
|
21
|
Cost of Sales
|
4.4
|
87.9
|
52.2
|
1.7
|
5
|
Corporate Charges
(Botswana)
|
8.0
|
159.2
|
52.2
|
3.1
|
9
|
Total
|
86.1
|
1,721.1
|
52.2
|
33.0
|
100
|
Notes:
(1) Average cost per year in which costs occur.
(2) Tonnes processed in relation to operating cost.
Source: 2023 FS
The capital cost estimate was
prepared using a combination of first principles, applying project
experience and using vendor/ contractor provided budgetary quotes
while avoiding the use of general industry factors. The estimate is
derived from engineers, contractors, and suppliers who have
provided similar services to existing operations and have
demonstrated success in executing the plans set forth in the
study.
Table 3: Capital Cost Summary
Capital Costs
|
Pre-Production
|
Sustaining
(M$)
|
LOM Total
(M$)
|
Weight
(%)
|
Sunk
(M$)
|
Estimated
(M$)
|
Subtotal
(M$)
|
Mining
|
140.4
|
253.1
|
393.5
|
124.8
|
518.2
|
63%
|
Site Development
|
12.7
|
13.4
|
26.1
|
6.6
|
32.7
|
4%
|
Process Plant
|
-
|
0.1
|
0.1
|
-
|
0.1
|
0%
|
Tailings and Mine Waste
|
-
|
-
|
-
|
42.8
|
42.8
|
5%
|
On-site Infrastructure
|
13.0
|
5.1
|
18.1
|
-
|
18.1
|
2%
|
Buildings and Facilities
|
2.1
|
3.1
|
5.2
|
-
|
5.2
|
1%
|
Off-site Infrastructure
|
23.3
|
0.4
|
23.7
|
-
|
23.7
|
3%
|
Project Indirects
|
9.4
|
21.7
|
31.1
|
1.4
|
32.5
|
4%
|
Owner Costs
|
63.6
|
89.9
|
153.5
|
-
|
153.5
|
19%
|
Subtotal
|
264.5
|
386.8
|
651.3
|
175.6
|
826.9
|
100%
|
Contingency
|
-
|
31.9
|
31.9
|
13.3
|
45.2
|
|
Closure
|
-
|
-
|
-
|
34.0
|
34.0
|
|
Total Capital Costs
|
264.5
|
418.7
|
683.3
|
222.9
|
906.1
|
|
Source: 2023 FS
Economics
The main assumptions with respect to
the economic model are listed in Table 4. Table 5 shows the
baseline diamond prices by zone.
Table 4: Economic Assumptions
Item
|
Unit
|
Value
|
BWP:US$ FX
|
BWP:US$
|
12.5
|
ZAR:US$ FX
|
ZAR:US$
|
17
|
Source: 2023 FS
Table 5: Baseline Diamond Prices
Unit
|
Unit
|
2023 FS
|
North
|
$/ct
|
273
|
Centre
|
$/ct
|
392
|
EM/PK(S)
|
$/ct
|
828
|
M/PK(S)
|
$/ct
|
707
|
Stockpiles
|
$/ct
|
574
|
Source: 2023 FS
Sensitivities
A univariate sensitivity analysis
was performed to examine which factors most affect the Project
economics when acting independently of all other cost and revenue
factors. Each variable evaluated was tested using the same
percentage range of variation, from -20% to +20%, although some
variables may actually experience significantly larger or smaller
percentage fluctuations over the LOM. The Project is most sensitive
to diamond prices and grade and the least sensitive to capital
costs.
Table 6: Sensitivity Results (Post-Tax NPV @
8%)
Variable
|
Post-tax NPV8%
(M$)
|
-20%
Variance
|
-10%
Variance
|
Base
|
+10%
Variance
|
+20%
Variance
|
Diamond Price
|
252.3
|
400.1
|
531.8
|
672.0
|
811.3
|
Mining Cost
|
556.8
|
544.3
|
519.2
|
506.7
|
Processing Cost
|
561.6
|
546.4
|
517.1
|
502.4
|
All Operating Costs
|
607.1
|
568.1
|
495.6
|
459.6
|
Upfront CAPEX
|
584.6
|
556.6
|
509.3
|
487.0
|
Sustaining CAPEX
|
548.1
|
539.9
|
523.6
|
515.5
|
All capital costs
|
602.3
|
565.4
|
501.2
|
473.1
|
Source: 2023 FS
Mineral Resources
The 2023 mineral resource estimate
for Karowe incorporates drilling and sampling data obtained prior
to 2018, and additional drilling and sampling information obtained
in 2018/ 2019 which targeted delineation of the deep extension of
South Lobe (deeper than approximately 600m from surface). In 2019,
the geological data were used to develop an updated internal
geology model for the South Lobe and to update the external
contacts for the South, Centre and North Lobes. The 2023 update
also includes geological information and production data derived
from open pit mining to the end of June 30, 2023.
The 2023 mineral resources for
Karowe, as summarized in Table 7, have been classified as either
Indicated or Inferred Mineral Resources, according to CIM
Definition Standards for Mineral Resources and Mineral Reserves
(CIM, 2014). Mineral Resources reported are inclusive of those
portions of the Mineral Resource that have been converted to
Mineral Reserves and have an effective date of June 30,
2023.
Table 7: Karowe 2023 Mineral Resource Statement (effective
date of June 30, 2023)
Classification
|
Domain
|
Volume
(Mm3)
|
Tonnes (Mt)
|
Density
(t/m3)
|
Carats
(Mcts)
|
Grade
(cpht)
|
Average
($/ct)
|
Indicated
|
South_M/PK(S)
|
7.02
|
20.92
|
2.96
|
2.27
|
10.8
|
707
|
South_EM/PK(S)
|
6.77
|
19.77
|
2.90
|
4.16
|
21.0
|
828
|
Centre
|
0.30
|
0.81
|
2.57
|
0.12
|
15.5
|
392
|
North
|
0.18
|
0.42
|
2.45
|
0.05
|
11.6
|
273
|
Total Indicated
|
14.27
|
41.92
|
2.90
|
6.60
|
15.8
|
793
|
Inferred
|
South_M/PK(S)
|
0.10
|
0.31
|
3.05
|
0.03
|
10.5
|
707
|
South_EM/PK(S)
|
1.40
|
4.18
|
2.97
|
0.87
|
20.9
|
828
|
South_KIMB3
|
0.32
|
0.94
|
2.94
|
0.10
|
10.9
|
707
|
Total Inferred
|
1.82
|
5.42
|
2.97
|
1.01
|
18.6
|
804
|
Notes:
1. Mineral Resources are not Mineral Reserves and do not have
demonstrated economic viability. All numbers have been rounded to
reflect accuracy of the estimate;
2. Mineral Resources are in-situ Mineral Resources and are
inclusive of in-situ Mineral Reserves;
3. The
base of the South Lobe Indicated Mineral Resource is 250masl and
60masl for the inferred resource;
4. Mineral Resources are exclusive of all mine stockpile
material;
5. Mineral Resources are quoted above a +1.25 mm bottom cut-off
and have been factored to account for diamond losses within the
smaller sieve classes expected within the current configuration of
the Karowe process plant;
6. Inferred Mineral Resources are estimated on the basis of
limited geological evidence and sampling, sufficient to imply but
not verify geological grade and continuity. They have a lower level
of confidence than that applied to an Indicated Mineral Resource
and cannot be directly converted into a Mineral Reserve;
7. Average diamond value estimates are based on 2023 diamond
sales data provided by Lucara Diamond Corp.; and
8. Mineral Resources have been estimated with no allowance for
mining dilution and mining recovery.
Source: 2023 FS
Mineral Reserves
The effective date for the Mineral
Reserve Estimate contained in the updated FS report is June 30,
2023 and was prepared by Qualified Person (QP) Brandon Chambers,
P.Eng. All Mineral Reserves in Table 8 are classified as Probable
Mineral Reserves. The Mineral Reserves, except stockpiles, are not
in addition to the Mineral Resources, but are a subset
thereof.
The QP has not identified any legal,
political, or environmental risks that would materially affect
potential Mineral Reserves development.
Table 8: Karowe Mineral Reserve Estimate (effective date of
June 30, 2023)
Lobe
|
Reserve Category
|
Ore Tonnage
|
Carats
|
Grade
|
LOM Diamond
Price
|
(Mt)
|
('000s ct)
|
(cpht)
|
($/ct)
|
Open Pit
|
Centre
|
Probable
|
0.6
|
96
|
16.3
|
392
|
South - EM/PK(s)
|
Probable
|
1.3
|
323
|
25.4
|
828
|
South - M/PK(s)
|
Probable
|
3.6
|
384
|
10.7
|
707
|
Open Pit
|
Total
|
5.5
|
803
|
14.7
|
718
|
Underground
|
South - EM/PK(s)
|
Probable
|
18.6
|
3,361
|
18.1
|
828
|
South - M/PK(s)
|
Probable
|
18.4
|
1,871
|
10.2
|
707
|
Underground
|
Total
|
37.0
|
5,232
|
14.2
|
785
|
Stockpile
|
Mixed Stockpile
|
Probable
|
4.0
|
502
|
12.7
|
433
|
Life of Mine
|
Probable
|
5.8
|
296
|
5.1
|
574
|
Stockpile
|
Total
|
9.7
|
798
|
8.2
|
485
|
Combined
|
All
|
Total
|
52.2
|
6,834
|
13.1
|
742
|
Notes:
1. Prepared
by Brandon Chambers, P.Eng. JDS Energy & Mining
Inc.;
2. CIM
definitions were followed for Mineral Reserves;
3. Process
recovery of the diamonds was assumed to be 100% as the recoveries
were included in the mineral resource block model assumptions and
therefore have taken recoveries into account;
4. The
bottom elevation of the Probable Reserve is 310 masl;
5. Mineral
Reserves are quoted above a +1.25 mm bottom cut-off and have been
factored to account for diamond loses within the smaller sieve
classes expected within the current configuration of the Karowe
Process Plant;
6. Diamond
price estimates are provided by Lucara; prices are derived from
historical sales and adjusted for current market
conditions;
7. Tonnages
are rounded to the nearest 100,000 t, diamond grades are rounded to
one decimal place to properly reflect the Reserve estimate
accuracy;
8. Tonnage
and grade measurements are in metric units; contained diamonds are
reported as thousands of carats;
9. Open pit
Mineral Reserves are estimated at a cut-off value of $37/t based on
an open pit mining cost of $13/t, a processing cost of $12/t and a
G&A cost of $12/t;
10. Underground Mineral
Reserves are estimated at a cut-off value of $35/t based on an
underground mining cost of $11/t, a processing cost of $12/t and a
G&A cost of $12/t;
11. Mine Call Factor is a
modifying factor used by Lucara which tracks the reconciliation
between the block model and actual recovered carats. Mine Call
Factor is assumed to be 100%, historically this factor has
reconciled either near or above 100%, however in the 12-month
period prior to the Reserve Statement the Mine Call Factor has
deviated away from historical average performance and is currently
at 95%;
12. Underground dilution
assumptions in the 2019 FS were revised in 2023. Underground
dilution included in the Reserve was estimated from the following
three sources:
• 1.0
m of zero-grade overbreak from stoping adjacent to the granite host
rock;
• 2.7
Mt of zero-grade overbreak from stoping adjacent to sedimentary
rocks (based on geomechanical modelling); and
• Inclusion of inferred KIMB3 kimberlite within the overall pipe
shape as zero-grade waste.
13. Stockpile Mineral Reserves
are estimated at a cut-off value of $19/t based on a rehandle cost
of $2/t, a processing cost of $12/t and a G&A cost of $5/t,
when processed at the end of mine life;
14. Stockpile Reserves are not
included in the Karowe Mineral Resource Estimate, which covered
only in-situ mineralized material;
15. Stockpile Reserves are
based on surveyed volumes and block model grades; and
16. Stockpile LOM diamond
price is determined from the weighted average of the North, Centre,
South - M/PK(s), and South - EM/PK(s) lobe ratios.
Source: 2023 FS
Geotechnical
A geotechnical investigation program
was carried out to support underground mine design, building on the
open pit and underground preliminary economic assessment ("PEA")
geotechnical modelling carried out in 2017. The geotechnical
drilling, sampling and testing program was designed to comply with
the data confidence requirements of a FS, in support of a
feasibility-level mine design, and leading into optimization of the
design implementation. The investigation focused on defining the
geotechnical characteristics of the surrounding country rock as
well as the South Lobe kimberlite and involved the drilling,
geotechnical logging and sampling of 37 diamond drillholes,
totaling more than 23,500m, with field and laboratory testing of
the core samples. Almost 11,000 tests were conducted on samples
across the various lithologies.
Hydrogeology
Water control and hydrogeological
context of the deposit and host rocks are key elements in the mine
plan. The AK6 deposit sits within layered, sedimentary, regional
aquifers that have been documented since the 1980's.
Since the release of the 2019
feasibility study report, five key updates were made:
· The
groundwater flow model was updated;
· A
planned drainage gallery at the 680 Level (680 L) was not
implemented;
· The
groundwater flow model in the 2019 FS assumed that grouting in the
granites will take place in all underground development and will be
75% successful. The predicted inflow rate in the updated model
(2023) only assumed 66% successful grouting during shaft sinking
and station development up to January 1, 2026; the model also
assumes that no grouting activities are undertaken once underground
pumping capacity is available unless particularly high inflows are
encountered that hinder development;
· The
underground drainage systems were updated; and
· The
depressurization target for the open pit slope was
updated.
Mineral Processing
The Karowe processing plant has been
treating unweathered South Lobe ore since 2015 and mineral
processing characteristics are very well understood.
A comminution test program was
conducted to test the milling characteristics of the South Lobe
material below the open pit to determine if the mill is suitable
for deeper EM/PK(S) ore.
The second test involved testing of
Tomra's X-ray Transmission (XRT) machines and associated software
to determine their ability to differentiate between diamonds, coal,
carbonaceous shale and other waste rock. Due to the high carbon
content of coal and carbonaceous shales, they were of greatest
concern. The dilution of ore with carbonaceous shales (and the
small, sporadic, coal seams contained therein) is anticipated to
occur during the later stages of mine life. Testing was conducted
by Tomra at their testing facilities in Germany.
Mining
The currently operating open pit at
Karowe is a conventional load and haul operation. Open pit mine
operations are expected to terminate mid-2025 at an elevation of
713 masl. The mine currently has over three years of surface
stockpiled reserves, which will be consumed as required while the
Underground mine operations ramp up to commercial
production.
The 2019 FS investigated several
underground mining methods based on data and information from an
exhaustive field program conducted in 2018 and 2019 to define
mineral resource, geotechnical, and hydrogeological characteristics
necessary for making informed decisions at a FS-level
study.
The inability for natural or
preconditioned caving to occur has resulted in the development of
the Long Hole Shrinkage ("LHS") mine method, which is essentially a
fully assisted cave. The method involves a combination of longhole
drilling and blasting to create a large muck pile within the South
Lobe, followed by the managed drawdown of the blast material
through a panel cave extraction level.
The benefits of the LHS mining
method include:
· Highest value ore to be extracted first due to the bottom-up
mining approach;
· Minimal development in weak, water-bearing lithologies near
surface;
· Dilution will be delayed (occurring after the payback period)
as the weaker host rock is not exposed until later in the mine
life;
· Development of the underground mine can occur simultaneously
with the open pit operations;
· Low
operating costs;
· Ease
of operation after the drilling and blasting phase is complete and
small underground work force requirements;
· Early
exclusion of precipitation into the underground workings until the
crown pillar is blasted;
· Significant ability to increase production after the drill and
blast phase is complete; and
· Designed to manage natural caving should it occur.
Infrastructure
The UGP at Karowe will include the
use of existing and new infrastructure at the Karowe Mine. Current
and planned infrastructure is designed to support the operation of
the mine and processing plant. Project construction over the past
two years has led to the completion of most of the surface
infrastructure components of the Project.
Permitting
Karowe, which has been operating
since 2012, completed its latest Environmental Impact Assessment/
Environmental Management Plan in 2020 (to incorporate the UGP) and
received approval from the Botswana Department of Environmental
Affairs during the same year.
The mining license was renewed in
2021 for a period of 25 years and expires on January 3,
2046.
Conclusions
It is the conclusion of the
Qualified Persons ("QPs") that the FS summarized in this press
release contains adequate data and information to support a FS.
Standard industry practices, equipment and design methods were used
in the FS. Since the 2019 FS, the UGP has advanced considerably in
terms of financing, detailed engineering and construction while the
open pit mine and processing facility have operated well and
maintained targeted production.
To date, the QPs are not aware of
any fatal flaws for the UGP.
Qualified Person ("QPs")
The FS was prepared under the
direction of JDS Energy & Mining Inc. and by leading
independent industry consultants. Mr. Gord Doerksen P. Eng is the
Project manager and responsible for the study completion and an
Independent Qualified Person under National Instrument 43-101. Dr.
J.P. Armstrong, Ph.D. P. Geo., the Company's VP Technical Services
and a Qualified Person under National Instrument 43-101, and Mr.
Doerksen have reviewed and approved the contents of this news
release.
The results of the Karowe
Underground FS will be summarized in a Technical Report prepared
pursuant to Canadian Securities Administrators' National Instrument
43-101 that will be filed on SEDAR+ (https://www.sedarplus.ca)
within 45 days of this press release and will also be available on
the Company's website (https://lucaradiamond.com/).
On
behalf of the Board,
William Lamb
President and Chief Executive
Officer
Follow Lucara Diamond on
Facebook,
Instagram,
and LinkedIn
For further information, please
contact:
ABOUT LUCARA
Lucara is a leading independent
producer of large exceptional quality Type IIa diamonds from its
100% owned Karowe Diamond Mine in Botswana. The Karowe Mine has
been in production since 2012 and is the focus of the Company's
operations and development activities. Clara Diamond Solutions
Limited Partnership ("Clara"), a wholly-owned subsidiary of Lucara,
has developed a secure, digital sales platform which ensures
diamond provenance from mine to finger. Lucara has an
experienced board and management team with extensive diamond
development and operations expertise. Lucara and its
subsidiaries operate transparently and in accordance with
international best practices in the areas of sustainability, health
and safety, environment, and community relations. Lucara has
adopted the IFC Performance Standards and the World Bank Group's
Environmental, Health and Safety Guidelines for Mining
(2007). Accordingly, the development of the Karowe
Underground Project adheres to the Equator Principles. Lucara is
committed to upholding high standards while striving to deliver
long-term economic benefits to Botswana and the communities in
which the Company operates.
The information is information that
Lucara is obliged to make public pursuant to the EU Market Abuse
Regulation and the Swedish Securities Markets Act. This information
was submitted for publication, through the agency of the contact
person set out above, on March 13, 2024 at 5:00 p.m. Pacific
Time.
CAUTIONARY NOTE REGARDING FORWARD
LOOKING STATEMENTS
Certain of the statements made
herein contain certain "forward-looking information" and
"forward-looking statements" as defined in applicable securities
laws. Generally, any statements that express or involve discussions
with respect to predictions, expectations, beliefs, plans,
projections, objectives, assumptions or future events or
performance and often (but not always) using forward-looking
terminology such as "expects", "is expected", "anticipates",
"believes", "plans", "projects", "estimates", "budgets",
"scheduled", "forecasts", "assumes", "intends", "strategy",
"goals", "objectives", "potential", "possible" or variations
thereof or stating that certain actions, events, conditions or
results "may", "could", "would", "should", "might" or "will" be
taken, occur or be achieved, or the negative of any of these terms
and similar expressions) are not statements of historical fact and
may be forward-looking statements.
Forward-looking information and
statements are based on the opinions and estimates of management as
of the date such statements are made, and they are subject to
several known and unknown risks, uncertainties and other factors
which may cause the actual results, performance or achievements of
the Company to be materially different from any future results,
performance or achievement expressed or implied by such
forward-looking statements, including risks related to. The Company
believes that expectations reflected in this forward-looking
information are reasonable, but no assurance can be given that
these expectations will prove to be accurate and such
forward-looking information included herein should not be unduly
relied upon.
In particular, this release may
contain forward looking information pertaining to the following:
potential to and length by which the UGP will extend the life of
mine; updated resource and reserves for the Karowe Mine, including
the Underground and the total expected life of mine production;
estimates of the Company's production, operating margins and sales
volumes for the Karowe Mine, including the Underground and
associated cash flow and revenues; estimates of the economic
benefits of the Underground, including the timing for the UGP to
pay back capital; anticipated total capital expenditures for the
Underground and the schedule to develop and complete the UGP;
continued availability of external financing; that expected cash
flows from open pit operations, combined
with external financing, will be sufficient to complete
construction of the UGP; the ability to integrate the underground
operations seamlessly into the existing infrastructure; the timing
of key construction milestones including shaft sinking activities;
the anticipated mine plan and mining methods; that the decisions
taken to de-risk the UGP will be successful; that the people,
equipment and materials required to build the UGP will be available
when required to maintain the proposed UGP schedule; anticipated
changes in diamond pricing, including trends in supplies and
demands; changes to foreign currency exchange rate; the Company's
adoption of and compliance with internationally recognized
standards including IFC Performance Standards and the Equator
Principles; and other forward looking information.
There can be no assurance that such
forward looking statements will prove to be accurate, as the
Company's results and future events could differ materially from
those anticipated in this forward-looking information as a result
of those factors discussed in or referred to under the heading
"Risks and Uncertainties"' in the Company's most recently filed
Annual MD&A and, in the Company's most recent Annual
Information Form available at SEDAR+
at www.sedarplus.ca, as well as the Company's ability to access the markets and
generate revenues at anticipated diamond prices, the Company's
ability to continue to comply with the terms of its debt financing,
changes in general business and economic conditions, changes in
interest and foreign currency rates, the supply and demand for,
deliveries of and the level and volatility of prices of rough
diamonds, costs of power and diesel, acts of foreign governments
and the outcome of legal proceedings, inaccurate geological and
recoverability assumptions (including with respect to the size,
grade and recoverability of mineral reserves and resources), and
unanticipated operational difficulties (including failure of plant,
equipment or processes to operate in accordance with specifications
or expectations, cost escalations, unavailability of materials and
equipment, government action or delays in the receipt of government
approvals, industrial disturbances or other job actions, adverse
weather conditions, and unanticipated events relating to health
safety and environmental matters).
The foregoing is not exhaustive of
the factors that may affect any of our forward-looking statements.
Forward-looking statements are statements about the future and are
inherently uncertain, and our actual achievements or other future
events or conditions may differ materially from those reflected in
the forward-looking statements due to a variety of risks,
uncertainties, and other factors, including, without limitation,
those referred to in this news release. Accordingly, readers and
investors should not place undue reliance on forward-looking
statements. Forward-looking information and statements are made as
of the date of this disclosure and accordingly are subject to
change after such date. Except as required by law, the Company
disclaims any obligation to revise any forward-looking information
and statements to reflect events or circumstances after the date of
such information and statements. All forward-looking information
and statements contained or incorporated by reference in this news
release are qualified by the foregoing cautionary
statements.