24 October 2024
Activities Report for the
September Quarter
|
Aura Energy Limited (ASX:AEE,
AIM:AURA) ('Aura' or the 'Company') is pleased to provide its
quarterly activities report for the period ended 30 September 2024
to accompany the Company's Appendix 5B.
To view the Appendix 5B, please
click here: http://www.rns-pdf.londonstockexchange.com/rns/4451J_1-2024-10-24.pdf
Aura has continued to make
significant progress on the development of the Company's flagship
Tiris Uranium Project in Mauritania ('Tiris') as its progresses
towards a Final Investment Decision ('FID') in early 2025 while
advancing the licensing of the Häggån Polymetallic Project in
Sweden ('Häggån').
HIGHLIGHTS:
Updated production target improves economics at Tiris Uranium
Project[1]
· The
February 2024 Front End Engineering Design
('FEED')[2] study production
target and economics was updated in September using the recently
expanded 91.3Mlbs
U3O8 Mineral
Resource[3] at the
Tiris Uranium Project in Mauritania to produce a Production Target
Update
·
Production Target Update1 increased the total
project U3O8 life of mine production by
44% to
43.5Mlbs U3O8 and
extended the mine
life from 17 years to 25 years
·
Project economics have also significantly
improved:
· NPV8% of US$499
million (A$734 million), an increase of
29%
· IRR of 39% post tax
and payback only 2.25
years
·
Life of Mine
post tax cash flows of US$1,509 million, an
increase of 42%
|
Units
|
Update
Sept
24
|
FEED
Feb 24
|
%
Change
|
|
|
|
|
|
Uranium price
|
US$/lb
U3O8
|
$80
|
$80
|
0%
|
|
|
|
Valuations and returns
|
|
|
Post-tax NPV8
|
US$
million
|
499
|
388
|
29%
|
|
|
|
Post-tax IRR
|
%
|
39%
|
36%
|
8%
|
|
|
|
Payback period
|
Years
|
2.25
|
2.5
|
-10%
|
|
|
|
Cashflow summary
|
|
|
Initial Life of Mine (LOM)
|
Years
|
25
|
17
|
43%
|
|
|
|
LOM
production
|
Mlbspa
U3O8
|
43.5
|
30.1
|
44%
|
|
|
|
Annual production
|
Mlbspa
U3O8
|
1.8
|
1.9
|
-5%
|
|
|
|
Gross revenue (LOM)
|
US$
million
|
3,467
|
2,257
|
54%
|
|
|
|
Free
Cashflow pre-tax (LOM)
|
US$
million
|
1,922
|
1,327
|
45%
|
|
|
|
Free
Cashflow post tax (LOM)
|
US$
million
|
1,509
|
1,061
|
42%
|
|
|
|
Unit
operating costs
|
|
|
All
in Cost
|
US$/lb
U3O8
|
41.0
|
41.8
|
-2%
|
|
|
|
All-in Sustaining Costs
|
US$/lb
U3O8
|
35.7
|
34.5
|
3%
|
|
|
|
C1
Cash Cost
|
US$/lb
U3O8
|
31.4
|
30.1
|
4%
|
|
|
|
Capital cost
|
|
|
Development capital
|
US$
million
|
230
|
230
|
0%
|
|
|
|
Table 1 - Summary of updated
production target outputs
Tiris Uranium Project fully permitted for development and
operations
Aura received the last outstanding
material permit from the Mauritanian Government to allow the
construction and operation of the Tiris Uranium Project. The
authorisation to develop, mine and produce Uranium Oxide
Concentrate ('UOC') was issued by the National Authority for
Radiation Protection, Safety and Nuclear Security (L'Autorité
Nationale de Radioprotection de Sûreté et de Sécurité Nucléaire
('ARSN')) on the 12 July 2024.
Restructure of the Curzon Uranium Limited ('Curzon') offtake
agreement completed[4]
The previously reported Curzon offtake restructure[5]
was completed on the 12 August 2024 and included a
A$5.4 million restructuring fee paid in Aura shares priced at
A$0.18 per share plus a A$5.4 million private placement in Aura at
the same price. In aggregate, Curzon was issued 59,829,060 new
shares in Aura and 5,982,906 options (priced at A$0.20 per option
and expiring 1 September 2025). Curzon now hold approximately 7.2%
of the undiluted issued shares in the Aura.
The restructured offtake
materially increased the price receivable
for planned uranium production and released significant value for
Tiris:
·
Average fixed price contract
price increases 70% to US$74.75/lb U3O8 from
US$44.09/lb U3O8 subject
to FID by 31 March 2025
·
Total contracted volumes
(fixed and variable priced contracts) reduce from 2.6Mlbs to
2.1Mlbs over the same 7-year term
·
Additional revenue of US$41
million delivered to the Tiris Uranium Project cash flows at a
uranium price of US$80/lb
U3O8
Activities and milestones
Numerous activities have commenced
or have been completed during the quarter supporting Aura's
objective of finalising a mine development decision by Q1 2025,
including:
·
Funding activities continued including the appointment of RPM
Global as Independent Technical Experts ('ITE') to undertake due
diligence on behalf of the funders, with a site visit scheduled for
October
·
Water drilling commenced at the Taoudeni Basin, ~100km south
of the Project with very significant water flows, up to
55m3 per hour and over a 60% success rate in the
drilling
·
Government engagement including meeting the new Minister of
Mines and Industry, His Excellency Minister Thiam
Tidjani
·
Appointment of experienced West African project director Jan
Booyse to lead the project development at Tiris
·
Engineering, Procurement and Construction Management ('EPCM')
contractor selection process commenced
·
Environmental, Social and Governance ('ESG') framework
developed and resourced
·
Continued engagement with multiple nuclear utilities with
respect to securing offtake contracts for the future Tiris uranium
production, having attended the World Nuclear Association ('WNA')
conference in London in September
Häggån Project exploitation license submitted in
Sweden
Aura Energy submitted the processing
concession ('Exploitation Permit Application') for Häggån K no 1
with the Swedish Mining Inspectorate[6].
The Exploitation Permit Application incorporated a preliminary
assessment of the Project including economics and both
environmental and community impact. The Swedish Mining Inspectorate
will now consider the application.
The exploitation permit will secure
the tenure over the Häggån Project and be valid for 25 years,
pending approval from the Swedish government. Aura will then
undertake further environmental and social impact studies, with the
goal of developing a profitable mine that operates sustainably,
responsibly and in full compliance with Swedish
regulations.
In addition, applications were
submitted for a new exploration application, Häggån no 2, covering
the areas of the original Häggån no 1 concession and an exception
to the prohibition year. During the period this application was
rejected by the Swedish Mining Inspectorate as the Häggån no 1
concession remains valid and has not yet expired until the
determination of the Exploitation Permit Application, at which
point new exploration application and exemption will be
resubmitted.
The Company believes these
applications will be considered favourably due to the considerable
amount of work undertaken over the Project to date. However, there
is no guarantee either application with be granted.
Balance Sheet
As of 30 September 2024, the Company
had cash of A$15.8 million.
Aura Managing Director and
CEO, Andrew Grove commented:
"Our team at Aura continued to make significant progress
towards the development of our exciting Tiris Uranium Project. The
material update to the Project economics on the back of the
increased Mineral Resource is just the start of defining what will
be a globally significant Project and a new uranium producing
region.
With the work being undertaken to demonstrate the scale
opportunities within the current Mineral Resource, and the very
significant exploration potential, we hope to demonstrate material
opportunity that lies within Tiris and northern Mauritania more
broadly.
We
continue to advance the project on multiple fronts to meet our
commitment to progress Tiris towards a Final Investment Decision in
early 2025."
|
Tiris Uranium Project,
Mauritania
The Tiris Uranium
Project[7] located
in Mauritania is a potential near-term, low-cost, long-life uranium
mine producing 2Mlbs pa U3O8 over the
currently defined 25-year mine life with production expected to
commence in 2026/27.
During the September quarter,
important activities continued to progress Tiris towards a Final
Investment Decision ('FID') in early 2025 and, ultimately, the
development of Mauritania's first uranium mine,
including:
·
Updated the Project economics and mine plan based of the
expanded 91.3Mlbs U3O8 Mineral
Resource[8] delivered last
quarter
·
Achieved final permitting of the Tiris Project
·
Completed the restructured Curzon offtake contract including
a A$5.4 million placement by Curzon into Aura
·
Funding activities continued
·
Water drilling commenced with great success
·
Numerous other pre-development activities
progressed
Key
highlights and outcomes of the Tiris Production
Target[9] update:
The update to the production target
for the FEED study5 has allowed revenue to be moved
forward in the mining schedule and also increased the overall life
of mine.
·
Robust base case project financial economics demonstrated by
post-tax NPV8 of US$499 million (A$734
million) with IRR of 39%, and a 2.25-year payback at
realised uranium price of US$80/lb
U3O8
· At
uranium prices of US$100/lb U3O8 the
economics increase to post-tax NPV8 of US$779
million (A$1,145 million) with IRR of
55%
·
Initial mine life increased from 17 years to 25 years,
producing an average 1.8Mlbspa U3O8 from the
2.0Mlbspa U3O8 capacity process
plant
·
Life of Mine ('LOM') uranium production increased from
30.1Mlbs U3O8to 43.5Mlbs
U3O8
· 93%
Measured and Indicated Mineral Resources in mining schedule during
the first four years, LOM Inferred material totals 33% mostly
beyond ten years in the mining schedule
· The
open pit mining is a simple, low-risk, shallow, free digging
operation without the need for crushing and grinding
·
Beneficiation delivers a high-grade leach feed averaging
2,217ppm U3O8 increasing from 1,997ppm
U3O8 (over first 5 years) and overall remains
approximately the same at 1,752ppm U3O8 from
1,743ppm U3O8 (LOM) at a very low average
cost of US$9.16/lb U3O8
·
AISC increased to US$35.7/lb U3O8, an
escalation of 3% on the 2024 FEED estimate5, largely due
to a minor increase in waste to ore strip ratio from
0.7 to 0.8 waste to ore tonnes
·
CAPEX of US$230 million was not re-evaluated in this update
and remained unchanged from the February FEED
study7
·
Uranium production planned within 18 months of Final
Investment Decision
·
Modular design provides opportunities for further capital
efficient expansion and scalability
· The
construction and operation of the Tiris Uranium Project will
deliver significant and ongoing benefits to the people of
Mauritania
Aura sees additional potential for
growth of uranium resources in Mauritania, both within the Tiris
East region (Figure 1) and more widely in the Tiris Zemmour
province. The Company has applied for 29 additional exploration
tenements, covering 13,000 km2 that show very strong
uranium potential[10], (Figure 2) across
the region and will continue to work to build northern Mauritania
as a significant global uranium province.
Figure 1 - Radiometrics,
tenement boundaries, prospect locations, Mineral Resource
boundaries reported in 2024 and 2023, along with drilling completed
during the current and prior programs
Figure 2 - Aura tenements
including granted and applications also showing geology and
radiometric targets
Tiris Production Target update Financial
Analysis
Financial analysis of the Tiris
Project is inclusive of Mauritanian government royalties and
commitments relating to the offtake agreement with
Curzon[11].
Results are on an after-tax basis in
$USD, unless otherwise stated. Financial modelling is inclusive of
all capital items, including mining mobilisation, process plant,
project infrastructure and LOM sustaining capital.
Table 2 shows the variance in
NPV8, IRR, payback period and net cashflows between this
Production Target Update and the FEED Study7. Applying a
base case uranium price of US$80/lb U3O8,
the post-tax NPV8 of the Tiris Project is US$499 million, the post-tax IRR of
39%, and the project
payback of 2.25 years from
commencement of production. At this price the project generates
average annual net cashflows
(EBITDA) of US$89 million per annum for the first five years and
US$63 million per annum for the LOM.
Table 2 - Summary of outputs recommended for presentation of
Production Target Update and FEED update results
|
Units
|
FEED Update Sept
24
|
FEED
Feb 24
|
% Change
|
|
|
|
|
|
Uranium Price
|
US$/lb
U3O8
|
$80
|
$80
|
0%
|
|
|
|
Valuations and Returns
|
|
|
Post-tax NPV8
|
US$
million
|
499
|
388
|
29%
|
|
|
|
Post-tax IRR
|
%
|
39%
|
36%
|
8%
|
|
|
|
Payback period
|
Years
|
2.25
|
2.5
|
-10%
|
|
|
|
Cashflow Summary
|
|
|
Initial Life of Mine
|
Years
|
25
|
17
|
43%
|
|
|
|
LOM
Production
|
Mlbspa
U3O8
|
43.5
|
30.1
|
44%
|
|
|
|
Annual Production
|
Mlbspa
U3O8
|
1.8
|
1.9
|
-5%
|
|
|
|
Gross Revenue (LOM)
|
US$
million
|
3,467
|
2,257
|
54%
|
|
|
|
Free
Cashflow pre-tax (LOM)
|
US$
million
|
1,922
|
1,327
|
45%
|
|
|
|
Free
Cashflow post tax (LOM)
|
US$
million
|
1,509
|
1,061
|
42%
|
|
|
|
Unit
Operating Costs
|
|
|
All
in Cost
|
US$/lb
U3O8
|
41.0
|
41.8
|
-2%
|
|
|
|
All-in Sustaining Costs
|
US$/lb
U3O8
|
35.7
|
34.5
|
3%
|
|
|
|
C1
Cash Cost
|
US$/lb
U3O8
|
31.4
|
30.1
|
4%
|
|
|
|
Capital Cost
|
|
|
Development Capital
|
US$
million
|
230
|
230
|
0%
|
|
|
|
Sensitivity Analysis
The sensitivity of the project to
market and project factors was examined. Table 3 provides a
comparison of project returns (NPV and IRR) at various throughput
profiles and U3O8 prices. This demonstrated
robust returns for a range of pricing scenarios for both the Base
and Growth scenarios. This analysis determined that the greatest
capital efficiency could be achieved for the base case production
profile, targeting 2Mlbs U3O8 pa
production.
Table 3 - Economic comparison at varying
U3O8 prices for Base Case 2Mlbs
U3O8 pa production
Spot U3O8 Price
|
US$/lb
|
65
|
70[12]
|
80
|
86[13]
|
90
|
100
|
110
|
NPV8
|
US$
million
|
285
|
355
|
499
|
571
|
639
|
779
|
919
|
IRR
|
%
|
27%
|
29%
|
39%
|
41%
|
47%
|
55%
|
63%
|
The sensitivity of the project to
key variables was examined in Figure
3. This showed that the Project was most
sensitive to revenue drivers, including mined grade and
U3O8 spot price. The Project was least
sensitive to operating cost inputs.
Figure 3 - Tiris Project sensitivity analysis (NPV8
US$ million)
Tiris Uranium Project fully permitted for development and
operations
Aura received the last outstanding
material permit from the Mauritanian Government to allow the
construction and operation of the Tiris Uranium Project. The
authorisation to develop, mine and produce Uranium Oxide
Concentrate ('UOC') was issued by the National Authority for
Radiation Protection, Safety and Nuclear Security (L'Autorité
Nationale de Radioprotection de Sûreté et de Sécurité Nucléaire
('ARSN')) on the 12 July 2024.
Approvals for the export of uranium
will be granted as part of a routine export monitoring program and
in accordance with international safeguards for monitoring the
movement of radioactive materials. There are no limits on the
volumes of future uranium production, which will allow significant
flexibility for the operation including the potential for future
expansion of production rate beyond 2Mlbs pa
U3O8.
The Company has contracted Oranio
Logistics, a major international company specialising in the
transportation of radioactive materials, for the future seaborne
transportation of UOC produced from Tiris to international
converters.
Restructure of the Curzon offtake agreement
completed[14]
The previously reported Curzon offtake restructure[15]
was completed on the 12 August 2024 with the
following key highlights:
·
Average fixed price contract price increases 70% to
US$74.75/lb U3O8 from US$44.09/lb
U3O8 subject to Final Investment Decision
('FID') by 31 March 2025
·
Total contracted volumes (fixed and variable priced
contracts) reduce from 2.6Mlbs to 2.1Mlbs over same seven-year
term
·
Additional revenue of US$41 million delivered to the Tiris
Project cash flows at a uranium price of US$80/lb
U3O8
·
Consistent with its previous election, Curzon will receive
the US$3.5 million (A$5.4 million) restructuring fee in Aura shares
priced at A$0.18 per share ('Restructuring Fee
Shares')
·
Restructuring Fee Shares will be escrowed until first
production from the Project
·
Aura will make a private placement to Curzon of 29,914,530
Aura shares, valued at US$3.5 million (A$5.4 million) in aggregate
('Placement Shares')
· 50%
of the Placement Shares will be escrowed until the earlier of 30
June 2025 or FID is made on the Project
· In
addition, Aura issued 5,982,906 unlisted options
('Options') priced at A$0.20
per option and expiring 1 September 2025, to Curzon
· In
aggregate, Curzon were issued 59,829,060 new shares in Aura and
5,982,906 options. and Curzon holds approximately 7.1% of the
undiluted issued shares in the Aura
·
With the additional funds, Aura is well funded to progress
the Project through to FID by Q1 CY2025
Tiris funding continuing
As previously reported on 3 June
2024, Aura appointed Orimco Pty Ltd ('Orimco') to arrange debt
funding for Tiris. Aura also engaged Macquarie Capital (Australia)
Limited ('Macquarie') to progress a process to identify and engage
with potential strategic investors in relation to a potential
strategic investment in Tiris and Aura.
This process has continued during
the quarter. RPMGlobal were appointed as Independent Technical
Experts ('ITE') to undertake the technical and Environmental,
Social and Governance ('ESG') due diligence on behalf of the
funders with site visits scheduled for October. Legal due diligence
is also scheduled to commence in October.
A number of parties have expressed
interest in both funding and strategic investment, and the advisors
continue to progress conversations with these parties.
Water drilling update
Water targeting and drilling
activities commenced on site at the Taoudeni Basin, ~100km south of
the Project. In Figure 4, the images show significant water flows,
up to 55m3 per hour in air lift testing, and over a 60%
success rate in the drilling encountering water. Project water
demand has been estimated to be up to approximately
160m3 per hour.
During September, 19 holes were
completed for 1,989 metres in the Taoudeni Basin.
Pump testing of the identified
aquifers commenced in October. Drilling also commenced at the C22
water resource ~30km for the Project. This program will be
completed during the December quarter and the Company is confident
that the program will demonstrate that sufficient water resources
will be available for the Project.
Figure 4 - Taoudeni Basin
water drilling images
Environment Social Governance framework
During the quarter under the
guidance of Bruce Harvey of Resolution88 Social License Solutions
and specialist consultants, the Company's ESG framework was
developed. Chantelle De La Haye, a highly experienced health,
safety, security and environment ('HSSE') professional, has been
appointed to implement the ESG framework.
Aura's ESG framework is as
follows:
Purpose
Statement:
Aura Energy develops metals and minerals for a cleaner energy
world, respecting, listening to and creating value for host
nations, local communities and shareholders.
ESG-related Values
Statements
Business integrity - at all
times we conduct ourselves with integrity
Health, safety and wellbeing -
we are committed to ensuring our employees, contractors and
affected community members can work and live in a safe and healthy
way
Respect, diversity and inclusion - we strive to ensure that every member of our workforce and
the communities we affect feel respected and valued
Cooperation, responsibility and technical
excellence - we create value
for our business, our investors and our workforce by fostering
technical excellence, cultivating a collaborative approach to
problem solving, and encouraging responsibility and
innovation
Environmental responsibility -
we are committed to responsible environmental management
Social responsibility - we are
committed to being socially responsible and seek to obtain and
sustain broad-based support for our business activities. This
includes respecting the human rights of everybody affected by our
business and value chain activities
Regional employment and enterprise - we seek to contribute to local and regional development
wherever possible
Climate and energy transition -
we are committed to climate change mitigation and energy source
transition
Other Tiris Activities
Project update was delivered on 4
July 2024 outlining five key steps that have commenced supporting
Aura's objective of finalising a mine development decision by Q1
CY2025, including:
·
Appointment of experienced West African project director Jan
Booyse and his company, Project EQ, to lead the project development
at Tiris
·
Appointment of Kenmore Mine Consulting to complete a mine
plan optimisation review
·
Appointment of Lycopodium to oversee an optimisation and
project enhancement study
·
Knight Piésold Consulting appointed to oversee water resource
drilling in the abundant and proximate Taoudeni Basin
Further to that announcement during
the quarter various activities were undertaken aimed at progressing
towards a Final Investment Decision at Tiris and
included:
·
Continued strong engagement with Mauritanian government with
a focus on delivering a collaborative development schedule and an
Aura delegation (including Chair and Managing Director and CEO)
meeting the new Minister of Mines and Industry, His Excellency
Minister Thiam Tidjani
·
Recruitment of Mauritanian team including search for highly
calibre country manager
·
Engineering, Procurement and Construction Management ('EPCM')
contractor selection process commenced
·
Lycopodium optimisation and project enhancement study
resulted in no material variance in the FEED capital
estimate
·
Continued engagement with multiple nuclear utilities with
respect to securing offtake contracts for the future Tiris uranium
production, having attended the World Nuclear Association ('WNA')
conference in London in September
Häggån Project Update
The Häggån Polymetallic Project,
located in the municipality of Berg in the county of Jämtland,
hosts a globally significant two billion
tonne polymetallic Mineral Resource[16] which includes 800Mlbs of
U3O8[17]. The primary metals and minerals are vanadium, sulphate of
potash ('SOP') and uranium, with nickel, molybdenum and zinc also
present.
Approximately 14% of the known value
of the asset is uranium. Including uranium into the previously
published scoping study[18]
increased the Project NPV by 37% at a uranium
price of US$65/lb U3O8 from the previously
stated range of between US$456 million to US$1,307
million.
The Swedish Government announced on
23 February 2024 the launch of an inquiry into overturning the
existing ban on mining uranium, which has been in place since 2018.
The inquiry investigated the regulatory changes needed to make
uranium extraction legal and analyse whether mining of uranium
should be allowed. The inquiry was presented to the government but
has not yet been made public. Once the results of the inquiry are
published, the Government can choose to go forward with a
legislative proposal to Parliament.
Aura Energy submitted the processing
concession ('Exploitation Permit Application') for Häggån K no 1
with the Swedish Mining Inspectorate[19]. The Exploitation Permit
Application incorporated a preliminary assessment of the Project
including economics and both environmental and community impact.
The Swedish Mining Inspectorate will now consider the
application.
The exploitation permit will secure
the tenure over the Häggån Project and be valid for 25 years,
pending approval from the Swedish government. Aura will then
undertake further environmental and social impact studies, with the
goal of developing a profitable mine that operates sustainably,
responsibly and in full compliance with Swedish
regulations.
In addition, applications were
submitted for a new exploration application, Häggån no 2, covering
the areas of the original Häggån no 1 concession and an exception
to the prohibition year. During the period this application was
rejected by the Swedish Mining Inspectorate as the Häggån no 1
concession remains valid and has not yet expired until the
determination of the Exploitation Permit Application, at which
point new exploration application and exemption will be
resubmitted.
The Company believes these
applications will be considered favourably due to the considerable
amount of work undertaken over the Project to date. However, there
is no guarantee either application with be granted.
Corporate Activities:
Option Funding Agreements
On 25 January 2024, the Company
announced that it had entered into an option funding agreement with
investors who have agreed to prepay the Company approximately A$4.3
million, equal to the exercise monies for all remaining options
expiring 30 June 2024.
As of 30 June 2024, 1,543,958
options remained unexercised, with an options funding loan balance
of approximately A$80,000. On 9 July 2024, the Company issued the
shortfall shares to the underwriter at the option exercise price of
A$0.052 each. The options funding loans were fully repaid with
proceeds received from options holders and the issue of shortfall
shares to the underwriters.
Cash and Cash Forecast
The Company's cash position as of 30
September 2024 was A$15.8 million. The Company's major cashflow
movements for the quarter included:
·
Investments in the Company's exploration and evaluation
assets of A$2.9 million
·
Proceeds from Curzon placement A$5.4 million
·
Repayment of options funding loans of A$1.2
million
·
Administration and corporate costs of A$1.1
million
·
Staff costs of A$0.4 million
The forecasted net operating
cashflow and investment in the Company's exploration and evaluation
assets for the coming quarter is A$4.4 million. With a closing cash
balance of A$15.8 million, the company has enough cash for 3.6
quarters.
Remuneration Consultant
The Remuneration and Nomination
Committee engaged Arthur J. Gallagher & Co. ('Gallagher'), an
experienced remuneration consultant, to provide guidance on a
competitive, market-related remuneration program for senior
executives and non-executive directors. The results of this work
was included in the Company's annual report published on the 27
September 2024.
Gallagher is one of the leading
insurance brokerage, risk management, and human capital consultant
companies in the world. Gallagher employs over 52,000 people
providing services in more than 130 countries.
December Quarter Planned
Activities
At Tiris, the next steps in
progressing towards the construction and development of the Project
that will be undertaken or commenced during the December quarter
include:
·
Project development funding activities
·
Optimisation of mine plan and review potential Project scale
on the based upon the enhanced 91.3Mlbs
U3O8 Mineral Resource[20]
·
Offtake contract negotiations
·
Complete water drilling and revisor testing to confirm and
develop water infrastructure sufficient to support future
operations
·
Appoint EPMC contractors to develop the Tiris
Project
·
Commence basic engineering and early works development
planning
·
Geometallurgy, engineering and design work to support
development activities
·
Baseline environmental and radiation monitoring
·
Implementation of ESG framework
At Häggån the planned activities
include:
·
Work to support the exploitation permit
application
September 2024 Quarter ASX Announcements
This Quarterly Activities Report
contains information extracted from ASX market announcements
reported in accordance with the 2012 edition of the "Australasian
Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves" ("2012 JORC Code"). Further details (including 2012
JORC Code reporting tables where applicable) of 2012 JORC Code
related disclosures referred to in this Quarterly Activities Report
can be found in the relevant announcements lodged on the ASX and in
the section titled "ASX JORC Related Disclosures" set out on page
15 of this report. Following is a list of all market sensitive
announcements lodged by the Company during the September
Quarter:
·
Multiple project development activities underway at
Tiris
4 July 2024
·
Tiris Project fully permitted for development and
operations
15 July 2024
·
Curzon Restructure and
Placement
15 August 2024
·
Haggan Project Exploitation Permit application
submitted
5 September 2024
·
Updated Production Target Improves Economics at
Tiris
11 September 2024
·
Aura Annual Report
27 September 2024
These announcements are available
for viewing on the Company's website auraenergy.com.au. Aura
confirms that it is not aware of any new information or data that
materially affects the information included in any of these
original ASX announcements.
Tenement Summary
The Company holds the following
interest in mining tenements, farm-in and farm-out agreements at
the end of the quarter:
Table 4 - Tenement summary
Tenement
No.
|
Name
|
Grant
Date
|
Expiry
|
Km2
|
Holder
|
Equity
|
Mauritania
|
2491C4
|
Ain Sder
|
8/02/2019
|
7/02/2049
|
207
|
Tiris Ressources SA
|
85%
|
2492C4
|
Oued El Foule
|
8/02/2019
|
7/02/2049
|
190
|
Tiris Ressources SA
|
85%
|
2490C4
(formerly 561)
|
Oum Ferkik
|
19/05/2017
|
Pending approval of application for
Exploitation License
|
60
|
Aura Energy Limited
|
100%
|
2365B4
|
Oued El Foule Sud
|
04/12/2023
|
03/08/2026
|
166
|
Aura Energy Limited
|
100%
|
2457B2
|
Hadeibet Belaa
|
08/12/2023
|
07/08/2026
|
41
|
Tiris International Mining
Co.
|
100%
|
2458B2
|
Touerig Taet
|
08/12/2023
|
07/8/2026
|
134
|
Tiris International Mining
Co.
|
100%
|
Sweden
|
2007-243
|
Häggån nr 1
|
28/08/2007
|
Pending determination of
exploitation permit application
|
18
|
Vanadis Battery Metals AB
|
100%
|
2016:9
|
Möckelåsen nr 1
|
21/01/2016
|
21/01/202
|
18
|
Vanadis Battery Metals AB
|
100%
|
2016:7
|
Skallböle nr 1
|
20/01/2016
|
20/01/2028
|
8
|
Vanadis Battery Metals AB
|
100%
|
Farm-in agreement with Nomads Mining
Company sarl, Mauritania, Aura, through subsidiary Archean
Greenstone Gold has earned a 70% interest in Nomads 100%-owned
exploration permit in Mauritania (refer to ASX announcement 11 June
2019).
ENDS
The Board of Aura Energy Ltd has
approved this announcement.
This Announcement contains inside
information for the purposes of the UK version of the market abuse
regulation (EU No. 596/2014) as it forms part of United Kingdom
domestic law by virtue of the European Union (Withdrawal) Act 2018
("UK MAR").
For
further information, please contact:
Andrew Grove
Managing Director and CEO
Aura Energy Limited
agrove@auraee.com
+61 414 011 383
|
Paul
Ryan
Sodali & Co
Investor & Media
Relations
paul.ryan@sodali.com
+61 409 296 511
|
SP
Angel Corporate Finance LLP
Nominated Advisor and
Broker
David Hignell
Kasia Brzozowska
Grant Baker
+44 203 470 0470
|
About Aura Energy (ASX: AEE, AIM:
AURA)
Aura Energy is an Australian-based
mineral company with major uranium and polymetallic projects in
Africa and Europe.
The Company is focused on developing
a uranium mine at the Tiris Uranium Project, a major greenfield
uranium discovery in Mauritania. 2024 FEED Study[21] and Updated Production Target[22] demonstrated Tiris to be a near-term low-cost
2Mlbs U3O8 pa future uranium mine with a
25-year mine life with excellent economics and optionality to
expand to accommodate future resource growth.
Aura plans to transition from a
uranium explorer to a uranium producer to capitalise on the rapidly
growing demand for nuclear power as the world shifts towards a
decarbonised energy sector.
Beyond the Tiris Project, Aura owns
100% of the Häggån Project in Sweden. Häggån contains a
global-scale 2.5Bt vanadium, sulphate of potash ("SOP")[23] and uranium[24] resource.
Utilising only 3% of the resource, a 2023 Scoping Study[25] outlined a 17-year mine life based on mining
3.5Mtpa.
Disclaimer Regarding Forward-Looking
Statements
This ASX announcement (Announcement)
contains various forward-looking statements. All statements other
than statements of historical fact are forward-looking statements.
Forward-looking statements are inherently subject to uncertainties
in that they may be affected by a variety of known and unknown
risks, variables and factors which could cause actual values or
results, performance or achievements to differ materially
from the expectations described in such forward-looking
statements. The Company does not give any assurance or
guarantee that the anticipated results, performance or
achievements expressed or implied in those forward-looking
statements will be achieved.
The Company has concluded that it
has a reasonable basis for providing the forward-looking statements
and production targets included in this announcement and that
material assumptions remain unchanged. The detailed reasons for
this conclusion are outlined throughout this announcement, and in
the ASX Releases, "Scoping Study Confirms Scale and Optionality of
Häggån", 5 September 2023; "Aura's Tiris FEED Study returns
Excellent Economics" 28 February 2024; "Tiris Uranium Project
Enhanced Definitive Feasibility Study", 29 March 2023 and "Updated
Production Target improves economics at Tiris Uranium Project" 11
September 2024.
ASX and JORC Related
Disclosures
Mineral Resources
The information on Mineral Resources
for the Tiris Uranium Project in this report is extracted from the
ASX release on 12 June 2024 titled "Aura increases Tiris Mineral
Resources by 55% to 91.3Mlbs".
The information on Mineral Resources for the
Tiris Uranium Project in this report is extracted from the ASX
release on 10 October 2019 titled "Häggån Battery Metal Project
Resource Upgrade Estimate Successfully Completed". These reports
can be viewed at https://auraenergy.com.au/investor-centre/asx-announcements.
The company confirms that it is not
aware of any new information or data that materially affects the
information included in the original market announcement and, in
the case of estimates of Mineral Resources or Ore Reserves, that
all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and
have not materially changed. The company confirms that the form and
context in which the Competent Person's findings are presented have
not been materially modified from the original market
announcement.'
Production Targets
The information on Production
Targets for the Tiris Uranium Project in this report is extracted
from the ASX release on 11 Sept 2024 titled "Updated Production
Target Improves Economics at Tiris". This report can
be viewed at https://auraenergy.com.au/investor-centre/asx-announcements.
The company confirms that it is not
aware of any new information or data that materially affects the
information included in the original market announcement and that
all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and
have not materially changed.
Scoping Study
The information on Häggån Scoping
Study in this report is extracted from the ASX release on 5
September 2023 titled "Scoping Study Confirms Scale and Optionality
of Häggån". This report can be viewed at https://auraenergy.com.au/investor-centre/asx-announcements.
The company confirms that it is not
aware of any new information or data that materially affects the
information included in the original market announcement and that
all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and
have not materially changed.