West Red Lake Gold Mines Ltd. (“West Red Lake Gold” or the
“Company”) (TSXV: WRLG) (OTCQB: WRLGF) is pleased to
provide an update on restart readiness activities, including the
in-progress bulk sample, at its 100% owned Madsen Mine project in
the Red Lake Gold District of Northwestern Ontario, Canada.
“With test mining underway, bulk sample
stockpiles building on surface, and the mill set to initiate
campaign processing in the coming weeks, we have achieved many key
operational milestones at the mine site,” said Shane Williams,
President and CEO. “The connection drift development and test
mining efforts have been very successful to date, which is a
testament to our mine crews’ ability to operate safely and
efficiently. I’m proud to say that the ramps, sills, and stopes we
are developing at Madsen are best in class.”
“Things are increasingly busy across the site
with final installation work underway for the camp and mine dry
facilities, mine engineering picking up pace, and a headcount that
stands at 185 employees and 50 contractors currently active on
site. The team is excited to get the bulk sample complete, which is
expected to demonstrate that our approach to mining at Madsen
works, followed by rolling into production mining and processing
with an aim to start selling gold into this record price
environment, where gold is selling for over CAD$4,100 per ounce
today.”
Bulk SampleThe bulk sample
program includes plans to mine at least 10,000 tonnes of material
from six stopes.
The Company prioritized parts of the Madsen
resource for extraction early in the mine life based on grade,
tonnage, and ease of access. These areas saw access development,
definition drilling, and mine engineering over the last 16 months
and now constitute the mineral inventory in the 12-month detailed
mine plan.
The bulk sample program targets stopes in three
such areas: the 1099/1100 area of the Austin resource, the 1407
area of the McVeigh resource, and the 987 area of the South Austin
resource.
FIGURE 1: Long section showing part of
the Madsen Mine deposit with bulk sample areas highlighted. Modern
workings (post 2019) shown in green; Connection Drift in
blue.
Bulk sampling from several areas amplifies the
benefits of test mining by:
- Testing drill
density and modeling techniques for different zones of the
deposit,
- Allowing crews
to deploy the range of mining methods that will be used at Madsen,
and
- Helping to
solidify mining procedures in proximity to old workings by
validating historical data and confirming geotechnical competence
assumptions (with respect to both void and backfilled historical
stopes).
At present, 3,380 tonnes of bulk sample material
are on surface from two stopes. The remaining stopes will be
drilled, blasted, and mucked over the coming weeks.
“The first stopes mined have provided valuable
insights into the effectiveness of the drill and blast designs, the
geological modelling techniques, and the overall development
processes required,” said Maurice Mostert, Vice President Technical
Services. “Initial results are showing that our drill and blast
techniques and design criteria are very effective at controlling
fragmentation size and dilution.”
FIGURE 2: Bulk sample stockpiles at the
Madsen Mine site.
West Red Lake Gold has engaged independent
third-party engineering contractors Entech Inc. and Soutex Inc. to
audit the mining and processing portions of the bulk sample
process, respectively.
Entech is monitoring the mining schedule and
providing third-party QA/QC on all sampling and stoping activities.
Soutex will review all processing plans and will supervise
operations and analyses.
“The bulk sample program is our first
opportunity to demonstrate that our Madsen Mine approach, based on
intensive definition drilling, clear confidence and financial
requirements for mine engineering, and appropriate mining methods,
can deliver the expected tonnes and grades to the mill,” said
Williams. “We hired Entech and Soutex because we want the results
of this bulk sample to be further substantiated by third party
independent review.”
FIGURE 3: An underground sampler
measuring interval length along the sampling line across an ore
face.
Mill Startup for Bulk Sample
ProcessingThe mill is scheduled to restart later this
month, after 28 months of maintained dry shutdown. First feed will
be 3,000 tonnes of legacy low-grade material to pack out the
grinding mills and establish dead beads in the process tanks. Feed
will then transition to low-grade material mined by West Red Lake
Gold.
Once re-commissioned, the mill will process the
bulk sample. Each stope will be processed individually to enable
full reconciliation calculations between expected and actual
tonnes, grades, and ounces.
West Red Lake Gold has completed multiple
pre-commissioning projects and tests at the mill. This includes
replacing the mill liners and discharge lines, reclaiming water
feed lines, recycling process water through the system,
revitalizing the CIP circuit, carbon circuit, and carbon kiln,
reassembling the flocculant and reagent systems and leach
agitators, and commissioning the refinery.
“All operational readiness milestones have been
met for the process plant,” said Hayley Halsall-Whitney, Vice
President Operations. “The facility is fully staffed and ready for
this first phase of mill operations.”
Connection Drift 80%
CompleteThe Connection Drift, the largest of the capital
projects supporting restart of the Madsen Mine and a cornerstone of
West Red Lake Gold’s approach to efficient mine operations, is now
80% complete. To date 1,148 metres have been completed, of the
1,440-metre total length. The project remains on track for
completion by the end of March 2025.
“The Connection Drift is a best-in-class haulage
way,” said Mostert. “This large cross-section, moderately inclined,
straight ramp with sufficient passing bays will optimise our
trucking operations. I am extremely proud of the quality of work
our teams have put into this key project.”
The Connection Drift is a 1.4-km haulage way
connecting the small historic West Portal, which through extensive
workings provides access to most parts of the Madsen mine, and the
East Portal, a modern portal from which development only extends a
modest distance into one resource area.
With the Connection Drift, West Red Lake Gold
will be able to move all material on large haul trucks through the
East Portal, which is situated close to the crusher and the
mill.
Underground DevelopmentThe
ability to develop access to mining areas efficiently and
accurately is essential in an underground mine, in particular a
mine where the deposit necessitates multiple working faces. For
this reason, West Red Lake Gold focused in H2 2024 on increasing
the pace of underground development, while maintaining strong
emphasis on safety and quality.
The effort has generated good results. In
January 2024 new development at the mine averaged just over 4
metres per day. This increased modestly to 6.6 metres a day by
mid-2024.
From August 2024 to January 2025 the pace of new
underground development increased notably, with average daily
meterage rising 23% each month. In January underground development
averaged above 20 metres per day and the pace continues to
increase.
FIGURE 4: Total underground development
at the Madsen mine by month.
Camp and Mine Dry
InstallationsThe last outstanding construction permit for
the Madsen Mine camp was received from the Municipality of Red Lake
on January 31st. Final installation work is now underway, which is
primarily power, water, sewer, and propane connections.
The Company expects to start housing workers in
the camp in the second half of March, pending receipt of an
occupancy permit that is in progress. The camp is a 114-person
facility. It offers individual rooms with ensuite bathrooms for
each worker, a kitchen and dining hall, and recreation space.
The mine dry facility is largely constructed.
Once a final permitting requirement is met, the Company expects to
be able to complete the installation and have the facility in
service for miners transitioning in and out of shifts by the end of
February.
FIGURE 5: The dining hall of the Madsen
mine camp, with accommodation buildings visible
behind.
QUALIFIED PERSONThe technical
information presented in this news release has been reviewed and
approved by Maurice Mostert, P.Eng., Vice President of Technical
Services for West Red Lake Gold and the Qualified Person for
technical services at the West Red Lake Project, as defined by
National Instrument 43-101 Standards of Disclosure for Mineral
Projects.
ABOUT WEST RED LAKE GOLD
MINESWest Red Lake Gold Mines Ltd. is a mineral
exploration company that is publicly traded and focused on
advancing and developing its flagship Madsen Gold Mine and the
associated 47 km2 highly prospective land package in the Red
Lake district of Ontario. The highly productive Red Lake Gold
District of Northwest Ontario, Canada has yielded over 30 million
ounces of gold from high-grade zones and hosts some of the world’s
richest gold deposits. WRLG also holds the wholly owned Rowan
Property in Red Lake, with an expansive property position covering
31 km2 including three past producing gold mines – Rowan,
Mount Jamie, and Red Summit.
ON BEHALF OF WEST RED LAKE GOLD MINES
LTD.“Shane Williams”Shane WilliamsPresident & Chief
Executive Officer
FOR FURTHER INFORMATION, PLEASE CONTACT:Gwen
PrestonVice President CommunicationsTel: (604)
609-6132Email: investors@wrlgold.com or visit the
Company’s website at https://www.westredlakegold.com
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
CAUTIONARY STATEMENT AND FORWARD-LOOKING
INFORMATIONCertain statements contained in this news
release may constitute “forward-looking information” within the
meaning of applicable securities laws. Forward-looking information
generally can be identified by words such as “anticipate”,
“expect”, “estimate”, “forecast”, “planned”, and similar
expressions suggesting future outcomes or events. Forward-looking
information is based on current expectations of management;
however, it is subject to known and unknown risks, uncertainties
and other factors that may cause actual results to differ
materially from the forward-looking information in this news
release and include without limitation, statements relating to
the plans and timing for the potential restart of mining operations
at the Madsen Mine, the potential (including the amount of
tonnes of material from the bulk sample program) of the Madsen
Mine; the benefits of test mining; the timing for the completion of
the Connection Drift; the timing of completion of the Madsen Mine
Camp; any untapped growth potential in the Madsen deposit or Rowan
deposit; and the Company’s future objectives and plans. Readers are
cautioned not to place undue reliance on forward-looking
information.
Forward-looking information involve numerous
risks and uncertainties and actual results might differ materially
from results suggested in any forward-looking information. These
risks and uncertainties include, among other things, market
volatility; the state of the financial markets for the Company’s
securities; fluctuations in commodity prices; timing and results of
the cleanup and recovery at the Madsen Mine; and changes in the
Company’s business plans. Forward-looking information is based on a
number of key expectations and assumptions, including without
limitation, that the Company will continue with its stated business
objectives and its ability to raise additional capital to proceed.
Although management of the Company has attempted to identify
important factors that could cause actual results to differ
materially from those contained in forward-looking information,
there may be other factors that cause results not to be as
anticipated, estimated or intended. There can be no assurance that
such forward-looking information will prove to be accurate, as
actual results and future events could differ materially from those
anticipated in such forward-looking information. Accordingly,
readers should not place undue reliance on forward-looking
information. Readers are cautioned that reliance on such
information may not be appropriate for other purposes. Additional
information about risks and uncertainties is contained in the
Company’s management’s discussion and analysis for the year ended
November 30, 2023, and the Company’s annual information form for
the year ended November 30, 2023, copies of which are available on
SEDAR+ at www.sedarplus.ca.
The forward-looking information contained herein
is expressly qualified in its entirety by this cautionary
statement. Forward-looking information reflects management’s
current beliefs and is based on information currently available to
the Company. The forward-looking information is made as of the date
of this news release and the Company assumes no obligation to
update or revise such information to reflect new events or
circumstances, except as may be required by applicable law.
For more information on the Company, investors
should review the Company’s continuous disclosure filings that are
available on SEDAR+ at www.sedarplus.ca.
Photos accompanying this announcement are available
at:https://www.globenewswire.com/NewsRoom/AttachmentNg/c7c39618-5020-4e77-8703-6edb6f6b3595https://www.globenewswire.com/NewsRoom/AttachmentNg/b7afa98f-9e98-4fc0-9889-fb0cb596cba1https://www.globenewswire.com/NewsRoom/AttachmentNg/59a21106-cdf2-40af-8c36-d734074e1029https://www.globenewswire.com/NewsRoom/AttachmentNg/c937e557-dd1a-4afd-bb9c-8f2cdf75664chttps://www.globenewswire.com/NewsRoom/AttachmentNg/89d40cb2-9e60-42d9-97cf-594e7f5187f8https://www.globenewswire.com/NewsRoom/AttachmentNg/6888525e-5fb1-495b-babf-340b809165c3
West Red Lake Gold Mines (TSXV:WRLG)
Historical Stock Chart
From Jan 2025 to Feb 2025
West Red Lake Gold Mines (TSXV:WRLG)
Historical Stock Chart
From Feb 2024 to Feb 2025