TIDMBRD
RNS Number : 0965R
BlueRock Diamonds PLC
19 September 2017
19 September 2017
BLUEROCK DIAMONDS PLC
("BlueRock" or the "Company")
Interim results for the six months ended 30 June 2017
Introduction
BlueRock Diamonds, the AIM listed diamond mining company, which
owns and operates the Kareevlei Diamond Mine in the Kimberley
region of South Africa, is pleased to announce its interim results
for the six months ended 30 June 2017. The interims will be
available today for download from www.bluerockdiamonds.co.uk
Operational Highlights
-- Monthly production is now in excess of 20,000 tonnes per
month and is nearing the target of 25,000 tonnes per month
-- Average grade continues to increase; average for the period
was 1.59cpht. Post period end the average grade has increased to
2.41cpht and the grade sold in the September tender reached
3.01cpht
-- Average value per carat achieved for the first 6 months of
2017 was USD 320, post period end the average price achieved rose
to USD 343
-- In August 2017, raised GBP860,000 (gross) through a placing and subscription
Chairman's Statement
The Company has made great strides during the first half of
2017.
Our new management team continues to improve existing mining
activities at Kareevlei; production is nearing target levels, value
per carat remains high and our recovered grade continues to
improve. As a consequence, our Kareevlei operations are nearing
breakeven.
We are now looking to expand our operations either through
developing our existing mining right at Kareevlei or by acquiring
rights to mine other areas. We intend to do this in a
cost-effective way, using our current facilities where possible to
assess other potential opportunities.
Production volumes
Production volumes have increased significantly since
recommencement of operations in March 2017.
2017 March April May June July August
---------------------------- ------ ------ ------ ------- ------- -------
Production volume (tonnes) 9,051 7,098 9,661 14,427 20,209 20,929
---------------------------- ------ ------ ------ ------- ------- -------
Following the end of the extreme rainfall in the first 10 weeks
of 2017, production recommenced in March 2017. During March, April
and May, production levels remained below expectation due to the
usual teething problems associated with the commissioning of a new
plant, the processing of wet kimberlite in March and an unwelcome
number of breakdowns caused by an over reliance on old
equipment.
Having identified these issues, management replaced the
equipment that was causing the breakdowns, leading to significant
increase in production volume in June and then July. Uptime in
March to May averaged approximately 6.4 hours per day and is now
running at approximately 16 hours per day. We currently operate two
shifts per day (over a five day week) and will be moving to three
shifts per day in early 2018, which is expected to further increase
our daily uptime. Our target monthly production volume remains at
25,000 tonnes.
Grade
The average pit grade for K2 as determined by Zstar (our
competent person) is 4.5 carats per hundred tonnes ("cpht"). We
have been concentrating on developing the K2 pit for the long term
and have, therefore, been drilling, blasting and processing the
remaining Level 1 kimberlite approximately 7m to 17m below the
surface, before commencing to the lower levels. The Level 1
kimberlite contains a significant amount of calcrete and,
accordingly, we expected grades from this ground to be lower than
average pit grade. Our average grade for the first 6 months of 2017
was 1.59cpht. Since the end of the half year, the average grade for
2017 has have improved to 2.40cpht with the grade for the parcel
sent to the September tender being 3.01cpht. The Company expects to
commence blasting of the Level 2 kimberlite later this month.
Pit development
We have now completed the remedial work required to ensure K2's
long-term production. The last of the calcretised Level 1
kimberlite will be processed by mid-October 2017 after which we
will begin to mine the Level 2 kimberlite, which consists of pure
kimberlite. We expect that the Level 2 kimberlite will produce a
significantly higher grade than Level 1, although it should be
noted that it is expected that different areas of the pit are
likely to produce differing recovered grades.
Value per carat
The value per carat continues to significantly exceed the
estimate provided by Zstar; the average for the first 6 months of
2017 was USD320 per carat compared with the Zstar estimate of
USD232. The higher value reflects the quality of our diamonds and
the coarseness of our production. As our production continues to
grow, so does our reputation for producing high quality
diamonds.
The recent introduction of our tertiary crusher into the circuit
is designed as a further method of liberation and is expected to
result in an increase in grade. It may, however, have an impact on
the average value per carat due to the increase in smaller
diamonds. We are in the process of assessing whether the likely
increased grade from the tertiary crusher outweighs the costs of
its operation.
Costs of production
The new management team have concentrated on reducing costs of
production in order to reduce the breakeven point and hence to
improve the long-term profitability of the mine.
In the first 6 months of 2017, we reduced the costs of
loading/hauling significantly by appointing a new contractor on
significantly better terms than hitherto. Since the end of the
interim period, we have reduced these costs further by leasing the
loading and hauling equipment directly and operating them
ourselves. We have also replaced ageing key pieces of equipment
with new equipment, which has reduced operating costs, while
increasing reliability. It has improved the plant's ability to
process continuously, resulting in a significant positive impact on
production volumes.
New opportunities
During the first half of 2017, we reached an agreement with
Koedonza Olives CC to mine a 1.5 hectare kimberlite pipe located in
Windsorton, approximately 40km north of Kimberley in the Northern
Cape known as Jubilee. Whilst there is no empirical data for the
pipe, there is evidence of diamonds being found near the surface by
alluvial mining operators. We intend to carry out a bulk sample of
up to 2,500 tonnes in the next month, which will be processed at
our Kareevlei facility for minimal cost. A decision as to how to
proceed with Jubilee will be made once the results of this limited
bulk sample have been analysed.
We continue to assess how best to exploit the 3,000 hectares
covered by our existing mining right across the Kareevlei Mining
Area, on which there are 5 known kimberlite pipes in existence. Of
the 5 pipes, K5 is the least known about, although the data that
does exist suggests that the coarseness of the diamonds in pipe 5
could be significantly greater than the other pipes. Similarly to
Jubilee, we intend to carry out a bulk sample of K5 in order to
provide further evidence as to whether K5 is an economically viable
pit to mine, despite its relatively small size of 0.25ha. Test work
on Pipe 5 and Jubilee is expected to be completed within the next
four weeks.
Financing
In May 2017, we raised GBP360,000 at 3p a share, which was used
to fund working capital.
Further to this raise, in July 2017 a loan agreement was entered
into with Mark Poole, a significant BlueRock shareholder, of up to
GBP315,000 in order to fund some of the required replacement
equipment. We have drawn down GBP251,000 of this amount and we do
not intend to draw down any further funds under this facility.
In July 2017, the term of the unsecured loans provided by Tim
Leslie and Paul Beck (both directors) and Mark Poole was extended
to 31 December 2017. Tim Leslie and Paul Beck agreed to advance a
further GBP20,000 each under the same facility. We intend to repay
these amounts prior to maturity, subject to the normal cashflow
considerations.
In August 2017, we raised a further GBP860,000 (gross of
expenses) through a placing and subscription at 1.25p, of which
Adam Waugh, Chief Executive Officer of the Company agreed to
subscribe for 4,000,000 new shares. These funds are expected to
provide sufficient working capital in order to reach break-even
based on our current internal forecasts.
Issue of new share options
On the 10 August 2017, BlueRock Diamonds plc announced that it
granted the following new share options to Adam Waugh (the
Company's CEO), Johan Milho, (the Company's mine manager) and Paul
Beck (the Company's non-executive Chairman). The details of the
issue are noted below:
Individual Tranche A Tranche B
No. of New No. of New Share
Share Options Options
Adam Waugh 3,417,740 3,417,740
Johan Milho 683,548 683,548
Paul Beck 992,096 992,096
Tranche A options have an exercise price of 1.25p, and Tranche B
options have an exercise price of 2.25p.
Further details of the financings in June, July and August are
set out in the announcements made via the London Stock Exchange's
RNS system on 1 June 2017, 20 July 2017 and 10 August 2017.
Diamond sales and production update
Since the period end, the number of carats sent and average
grade of the parcel sold at the monthly tender has continued to
increase and the average value per carat remains significantly
above expectations.
2017 Carats recovered Average Average
(cpht) price/carat Grade
(USD)
----------- ----------------- ------------- --------
July 329.66 396 1.82
----------- ----------------- ------------- --------
August 400.06 330 2.08
----------- ----------------- ------------- --------
September 545.63 323 3.01
----------- ----------------- ------------- --------
In July, August and September, we sold 1,275 carats at tender
and achieved grades ranging from 1.82cpht to 3.01cpht. The average
price achieved for our goods over this period was USD 343.
Production has continued to improve with July producing 20,200
tonnes representing an increase of 40% on production achieved in
June 2017. The total tonnage for August showed an increase of 3.5%
to 20,929 tonnes. Production throughout September continues to move
towards our target of 25,000 tonnes.
Paul Beck
Non-executive Chairman
Market Abuse Regulation (MAR) Disclosure
Certain information contained in this announcement would have
been deemed inside information for the purposes of Article 7 of
Regulation (EU) No 596/2014 until the release of this
announcement.
Enquiries:
BlueRock Diamonds
plc awaugh@bluerockdiamonds.co.uk
Adam Waugh, CEO
SP Angel (NOMAD and
Broker)
Stuart Gledhill
Lindsay Mair +44 (0)20 3470 0470
Yellow Jersey PR
Felicity Winkles
Joe Burgess
Katie Bairsto +44 (0) 7769 325254
CONDENSED INTERIM CONSOLIDATED FINANCIAL STATEMENTS 30 JUNE
2017
Consolidated Statement of Financial Position
As at As at As at
30 June 30 June 31 December
2017 2016 2016
Unaudited Unaudited Audited
Note GBP GBP GBP
Assets
Non-current assets
Property, plant and equipment 5 821,415 517,367 783,314
Mining assets 255,179 164,449 216,276
1,076,594 681,816 999,590
------------ ------------ -------------
Current assets
Inventories 6 15,930 26,874 2,202
Trade and other receivables 7 44,311 41,953 131,997
Cash and cash equivalents 8 106,347 458,222 291,555
------------ ------------ -------------
166,588 527,049 425,754
------------ ------------ -------------
Total assets 1,243,182 1,208,865 1,425,344
------------ ------------ -------------
Equity and liabilities
Equity Attributable to
Equity Holders of the Parent
Share capital 10 679,096 388,046 556,796
Share premium 10 2,656,728 2,012,781 2,443,826
Retained losses (2,352,940) (2,018,022) (1,828,598)
Convertible loan note reserve 12 - 293,818 -
Foreign exchange reserve (279,982) (9,689) (332,160)
------------ ------------ -------------
702,902 666,934 839,864
Non-controlling interest (1,071,106) (567,084) (817,386)
(368,204) 99,850 22,478
------------ ------------ -------------
Liabilities
Current liabilities
Trade and other payables 11 632,757 387,716 413,681
Non-current liabilities
Embedded derivative 12 72,451 - 292,839
Borrowings 12 761,531 626,236 583,548
Provisions 13 144,647 95,063 112,798
------------ ------------ -------------
1,611,386 1,109,015 1,402,866
------------ ------------ -------------
Total equity and liabilities 1,243,182 1,208,865 1,425,344
------------ ------------ -------------
Consolidated Statement of Comprehensive Income
6 months 6 months 12 months
ended ended ended
30 June 30 June 31 December
2017 2016 2016
Unaudited Unaudited Audited
Note GBP GBP GBP
--------------------------------- ----- ----------- ----------- -------------
Revenue 150,551 206,072 239,646
Other income - 58 500
Operating expenses (901,660) (516,454) (1,545,018)
Operating loss (751,109) (310,324) (1,304,872)
Finance charges (30,186) - (60,229)
Foreign exchange (loss)
/ gain 3 (85,869) - 869,608
----------- ----------- -------------
Loss before taxation (867,164) (310,324) (495,493)
----------- ----------- -------------
Taxation (7,134) - (90,566)
----------- ----------- -------------
Total loss for the period (874,298) (310,324) (586,059)
----------- ----------- -------------
Other Comprehensive Income:
Exchange differences on
translating foreign operations 70,511 (264,264) (700,035)
----------- ----------- -------------
Total comprehensive loss,
net of tax (803,787) (574,588) (1,286,094)
----------- ----------- -------------
Total comprehensive loss,
net of tax attributable
to:
Owners of the parent (550,067) (353,777) (814,981)
Non-controlling interest (253,720) (220,811) (471,113)
(803,787) (574,588) (1,286,094)
----------- ----------- -------------
Earnings per share - from
continuing activities
Basic and diluted 15 (0.01) (0.01) (0.02)
Consolidated Statement of Changes in Equity
Share Share Retained Foreign Total Non-controlling Total
Convertible capital premium losses exchange attributable interest equity
loan reserve to equity
note holders GBP
reserve GBP GBP GBP GBP of the GBP
Group
GBP GBP
------------ -------- ---------- ------------ ---------- ------------- ---------------- ---------------
Balance at 1
January 2016: 293,818 321,604 1,335,952 (1,859,800) 185,866 277,440 (346,273) (68,833)
Loss for the
period - - - (158,222) - (158,222) (152,102) (310,324)
Other
comprehensive
income:
Foreign
exchange
movements - - - - (195,555) (195,555) (68,709) (264,264)
------------ -------- ---------- ------------ ---------- ------------- ---------------- ---------------
Total
comprehensive
loss: - - - (158,222) (195,555) (353,777) (220,811) (574,588)
Transactions
with
shareholders:
Issue of share
capital - 66,442 676,829 - - 743,271 - 743,271
------------ -------- ---------- ------------ ---------- ------------- ---------------- ---------------
Total
transactions
with
shareholders: - 66,442 676,829 - - 743,271 - 743,271
------------ -------- ---------- ------------ ---------- ------------- ---------------- ---------------
Balance at 30
June 2016
(unaudited): 293,818 388,046 2,012,781 (2,018,022) (9,689) 666,934 (567,084) 99,850
============ ======== ========== ============ ========== ============= ================ ===============
Balance at 1
July 2016: 293,818 388,046 2,012,781 (2,018,022) (9,689) 666,934 (567,084) 99,850
Loss for the
period - - - (138,733) - (138,733) (137,002) (275,735)
Other
comprehensive
income:
Foreign
exchange
movements - - - - (322,471) (322,471) (113,300) (435,771)
------------ -------- ---------- ------------ ---------- ------------- ---------------- ---------------
Total
comprehensive
loss: - - - (138,733) (322,471) (461,204) (250,302) (711,506)
Transaction
with
shareholders:
Extinguish
convertible
loan note
reserve (293,818) - - 293,818 - - - -
Issue of share
capital - 168,750 506,250 - - 675,000 - 675,000
Share issue
expenses - - (75,205) - - (75,205) - (75,205)
Issue of share
options - - - 34,339 - 34,339 - 34,339
Total
transactions
with
shareholders: (293,818) 168,750 431,045 328,157 - 634,134 634,134
------------ -------- ---------- ------------ ---------- ------------- ---------------- ---------------
Balance at 31
December 2016 - 556,796 2,443,826 (1,828,598) (332,160) 839,864 (817,386) 22,478
(audited):
============ ======== ========== ============ ========== ============= ================ ===============
Balance at 1
January 2017: - 556,796 2,443,826 (1,828,598) (332,160) 839,864 (817,386) 22,478
Loss for the
period - - - (602,245) - (602,245) (272,053) (874,298)
Other
comprehensive
income:
Foreign
exchange
movements - - - - 52,178 52,178 18,333 70,511
------------ -------- ---------- ------------ ---------- ------------- ---------------- ---------------
Total
comprehensive
loss: - - - (602,245) 52,178 (550,067) (253,720) (803,787)
Transactions
with
shareholders:
Issue of share
capital - 122,300 243,700 - - 366,000 - 366,000
Share issue
expenses - - (30,798) - - (30,798) - (30,798)
Issue of share
options - - - 77,903 - 77,903 - 77,903
------------ -------- ---------- ------------ ---------- ------------- ---------------- ---------------
Total
transactions
with
shareholders: - 122,300 212,902 - - 413,105 - 413,105
------------ -------- ---------- ------------ ---------- ------------- ---------------- ---------------
Balance at 30
June 2017
(unaudited): - 679,096 2,656,728 (2,352,940) (279,982) 702,902 (1,071,106) (368,204)
============ ======== ========== ============ ========== ============= ================ ===============
Consolidated Statement of Cash Flows
6 months 6 months 12 months
ended ended ended
30 June 30 June 31 December
2017 2016 2016
Unaudited Unaudited Audited
GBP GBP GBP
-------------------------------- --- ----------- ----------- -------------
Operating activities
Cash used in operations 14 (724,344) (121,493) (163,258)
Net cash used in operating
activities (724,344) (121,493) (163,258)
Investing activities
Purchase of property, plant
and equipment (210,454) (51,692) (350,260)
Acquisition of Diamond
Resources (Pty) Limited - - (32,826)
Proceeds on disposal of
property, plant and equipment - - 19,113
Purchase of non-current - (23,355) -
assets
Net cash used in investing
activities (210,454) (75,047) (363,973)
Financing activities
Proceeds on share issue 10 335,202 700,000 1,343,066
Proceeds from borrowings 343,877 - -
Exercised share options - 43,270 -
Net cash received from
financing activities 679,079 743,270 1,343,066
Net (decrease) / increase
in cash and cash equivalents (255,719) 546,730 815,835
----------- ----------- -------------
Cash and cash equivalents
at the beginning of the
period 8 291,555 175,755 175,755
Foreign exchange differences 70,511 (264,263) (700,035)
Cash and cash equivalents
at the end of the period 8 106,347 458,222 291,555
Notes to the Interim Consolidated Financial Statements
1. Accounting policies
1.1 General information and basis of preparation
The condensed interim consolidated financial statements (the
"interim financial statements") are for the six-month period ended
30 June 2017.
These interim financial statements have not been audited, and
the financial information set out in this report does not
constitute statutory accounts as defined by the Companies Act 2006.
The comparative figures for the year ended 31 December 2016 were
derived from the statutory accounts for the year to 31 December
2016, which have been delivered to the Registrar of Companies.
Those accounts received an unqualified audit report which did not
contain statements under sections 498(2) or (3) (accounting records
or returns inadequate, accounts not agreeing with records and
returns or failure to obtain necessary information and
explanations) of the Companies Act 2006.
The interim financial statements have been prepared on the basis
of the accounting policies set out in the December 2016 financial
statements of BlueRock Diamonds plc and IAS 34 "Interim Financial
Reporting" on a going concern basis. They are presented in
sterling, which is also the functional currency of the parent
company. They do not include all of the information required in
annual financial statements in accordance with IFRS and should be
read in conjunction with the consolidated financial statements of
the Group for the period ended 31 December 2016.
The interim financial statements have been approved for issue by
the Board of Directors on 18 September 2017.
1.2 Standards issued but not adopted
The following relevant new IFRS standards, amendments to
standards and interpretations have been issued by the IASB, but are
not effective for the financial year beginning on 1 January 2017
and have been adopted by the EU and have not been early
adopted.
The Directors anticipate that the adoption of these standards
and interpretations in future periods will have no material impact
on the financial statements of the Company when the relevant
standards and interpretations come into effect. The principal
accounting policies applied in the preparation of these financial
statements are set out below. These policies have been consistently
applied to all the years presented, unless otherwise stated:
Standard Key requirements Effective date as adopted by the EU
IFRS 9 Financial Instruments - Replacement to IAS 39 and is built on a 1 January 2018
single classification and
measurement approach for financial assets which reflects both the
business model in which
they are operated and their cash flow characteristics.
IFRS 15 Revenue from contracts with customers - Introduces requirements for 1 January 2018
companies to recognise
revenue for the transfer of goods or services to customers in
amounts that reflect the consideration
to which the Company expects to be entitled in exchange for those
goods or services. Also
results in enhanced disclosure about revenue.
1. Accounting policies (continued)
The following relevant new IFRS standards, amendments to
standards and interpretations have been issued by the IASB, but are
not effective for the financial year beginning on 1 January 2017
and have not been endorsed by the EU and have not been early
adopted:
Standard Key requirements Effective date as adopted by the EU
IFRS 16 Leases - Introduces a single lessee accounting model and 1 January 2019
eliminates the previous distinction
between an operating and a finance lease.
2. Significant judgements and sources of estimation
uncertainty
In the application of the Group's accounting policies the
Directors are required to make estimates and assumptions about the
carrying amounts of assets and liabilities that are not readily
apparent from other sources. Actual results may differ from these
estimates.
The judgements, estimates and assumptions applied in the interim
financial statements including the key sources of estimation
uncertainty were the same as those applied in the financial
statements for the period ended 31 December 2016.
The estimates and underlying assumptions are reviewed on an
ongoing basis. Revisions to accounting estimates are recognised in
the period in which the estimate is revised if the revision affects
only that period, or in the period of the revision and future
periods if the revision affects both current and future
periods.
3. Foreign exchange (loss) / gain
6 months 6 months 12 months
ended 30 ended ended
June 30 June 31 December
2017 2016 2016
GBP GBP GBP
Unaudited Unaudited Audited
Foreign exchange (loss)
/ gain (85,869) - 869,608
----------- ----------- -------------
The foreign exchanges (loss) / gain relate to translation
differences on subsidiary balances that are translated into the
reporting currency of the Company at the reporting date and do not
constitute a movement through the other comprehensive income
reserve.
4. Segmental reporting
Operating segments are identified on the basis of internal
reports about components of the Group that are regularly reviewed
by the chief operating decision maker in order to allocate
resources to the segments and to assess their performance.
The Group's operations relate to the exploration for, and
development of mineral deposits in the Kimberley region of South
Africa and as such the Group has only one reportable segment. The
non-current assets in the Kimberley region in June 2017 were
GBP1,043,043 (June 2016: GBP681,816; December 2016: GBP999,590)
All revenue consists of sales of diamonds in South Africa
through auctions as is customary in the industry. The Company sells
its diamonds through auctions run by CS Diamonds (Pty) Ltd.
5. Property, plant and equipment
Cost / Accumulated Carrying
Valuation depreciation value
30 June GBP 30 June
2017 2017
GBP GBP
Unaudited
----------- -------------- -----------
Mine infrastructure 55,803 (9,643) 46,160
Motor vehicles 12,435 (2,749) 9,686
Plant and machinery 884,213 (118,644) 765,569
Total 952,451 (131,036) 821,415
Reconciliation of property, plant and equipment
Carrying Additions Depreciation Disposals FX revaluation Carrying
value GBP value
1 January GBP GBP GBP 30 June
2017 2017
GBP GBP
Audited Unaudited
----------- ---------- ------------- ---------- --------------- -----------
Mine infrastructure 52,321 4,057 (9,643) - (575) 46,160
Motor vehicles 13,191 - (2,749) (618) (138) 9,686
Plant and
machinery 717,802 197,248 (118,644) (17,579) (13,258) 765,569
----------- ---------- ------------- ---------- --------------- -----------
783,314 201,305 (131,036) (18,197) (13,971) 821,415
----------- ---------- ------------- ---------- --------------- -----------
6. Inventories
30 June 30 June 31 December
2017 2016 2016
GBP GBP GBP
Unaudited Unaudited Audited
Diamonds on hand 15,930 26,874 2,202
----------- ----------- ------------
7. Trade and other receivables
30 June 30 June 31 December
2017 2016 2016
GBP GBP GBP
Unaudited Unaudited Audited
Prepayments 6,943 6,690 2,073
VAT 37,356 35,263 53,952
Other receivables 12 - 75,972
44,311 41,953 131,997
----------- ----------- ------------
The carrying value of all trade and other receivables is
considered a reasonable approximation of fair value.
8. Cash and cash equivalents
30 June 30 June 31 December
2017 2016 2016
GBP GBP GBP
Unaudited Unaudited Audited
Cash in bank and on hand 106,347 425,396 291,555
Deposit - Diamond Resources - 32,826 -
----------- ----------- ------------
106,347 458,222 291,555
----------- ----------- ------------
9. Share Based Payments
The Directors were granted share options under the share option
agreements dated 19 August 2013. There were no amendments to the
terms of the options granted during the period.
The share options held by current and former Directors as at 30
June 2017 and the exercise prices were as follows:
Tranche Tranche Tranche Tranche Tranche
1 2 3 4 5
Number
of ordinary
shares
subject
to share
Director options Number and Exercise Price (pence)
157,625 157,626
P. Beck 315,251 - - 40 - 55 - -
57,625 157,625 157,626
T. Leslie 372,876 - 18 - 40 - 55 - -
57,625 157,625 157,626
A. Markgraaff 372,876 - 18 - 40 - 55 - -
776,091 1,670,387
A. Waugh 2,446,478 - - - - 11 - 5
Total 3,507,481 115,250 472,875 472,878 776,091 1,670,387
------------- -------- -------- -------- -------- ------------
The following share options were granted during the period to 30
June 2017:
On 19 January 2017 1,670,387 share options were granted to Adam
Waugh and 556,795 share options were granted to the Company's mine
manager, Johan Milho, both issues of share options have an exercise
price of 5p per Ordinary Share.
Movements in the number of share options outstanding and their
related weighted average prices are as follows:
30 June 2017 31 December 30 June 2016
2016
Average Number Average Number Average Number
exercise of options exercise of options exercise of options
price price price
in pence in pence in pence
per share per share per share
Outstanding at
the beginning
of the period 29.2 3,555,720 34 4,616,722 34 4,121,131
Granted 5 2,227,182 - - 11 776,091
Lapsed - - 31 1,261,002 - -
Exercised - - - - 15 280,500
----------- ------------ ----------- ------------ ----------- ------------
Outstanding at
the period / year
end 19.55 5,582,902 29.2 3,555,720 30 4,616,722
Exercisable at
the period / year
end 19.55 5,582,902 29.2 3,555,720 30 4,616,722
Options are valued at date of grant using the Black-Scholes
option pricing model. The fair value per option of options granted
during the period and the assumptions used in the calculation are
shown below:
6 months ended Year ended
30 June 31 December
2017 2016
---------------------------------------------------- --------------- --------------
Pricing model used Black-Scholes Black-Scholes
Weighted average share price at grant date (pence) 5.75 13.5
Weighted average exercise price (pence) 5 11
Weighted average contractual life (years) 5 5
Share price volatility (%) 50% 50%
Dividend yield (%) 0% 0%
Risk-free interest rate (%) 0.70% 0.56%
----------------------------------------------------- --------------- --------------
The total share-based payment expense for the period ended 30
June 2017 was GBP77,903 (June 2016: GBPnil; December 2016:
GBP34,399).
10. Share capital and share premium issued
30 June 30 June 31 December
2017 2016 2016
GBP GBP GBP
Unaudited Unaudited Audited
Number of Ordinary shares 67,879,580 38,804,580 55,679,850
Ordinary share capital of
1p per share 679,096 388,046 556,796
Share premium 2,656,728 2,012,781 2,443,826
3,335,824 2,400,827 3,000,622
---------------- ----------- ----------------
In the period ended 30 June 2017 the following Ordinary share
issues occurred:
Date of issue Details of issue Number of ordinary Share capital Share premium
shares GBP GBP
At 1 January
2017 55,679,580 556,796 2,443,826
Placing and equity
1 June 2017 issue 12,200,000 122,000 243,700
Placing and equity
1 June 2017 issue expenses - - (30,798)
Placing and equity
issue SP Angel
1 June 2017 advisory fees 30,000 300 -
At 30 June
2017 67,879,580 679,096 2,656,728
------------------- ------------- -------------
On 1 June 2017, a placing and subscription raised an aggregate
of GBP335,202 after expenses via the issue of 12,200,000 new
ordinary shares of 1 pence each in the capital of the Company at a
price of 3 pence per New Share; this transaction is further
discussed in Note 16. Additionally 30,000 new shares were issued to
SP Angel as payment for advisory work completed in connection with
the placing and subscription.
11. Trade and other payables
30 June 30 June 31 December
2017 2016 2016
GBP GBP GBP
Unaudited Unaudited Audited
Trade payables 290,801 174,304 260,116
Accrued expenses 24,297 182,460 37,025
Corporation tax payables 97,699 - 90,566
Other payables 219,960 30,952 25,974
----------- ----------- ------------
632,757 387,716 413,681
----------- ----------- ------------
An amount of GBP192,376 is included within trade payables for
amounts being claimed as being due to companies related to a former
director of the Company. This amount is disputed in full by the
Company based on legal advice received.
Within other payables is a balance due to a major shareholder of
the Company, Mark Poole, the total advanced of GBP194,377 (June and
December 2016: GBPnil), was sent in advance of agreeing the asset
finance facility which was agreed on 20 July 2017, see note 17 for
further details. In addition, within other payables is an amount of
GBP25,974 which relates to an amount claimed by a former director
and which, based on legal advice received by the company, is
disputed in full.
12. Borrowings and embedded derivative
30 June 30 June 31 December
2017 2016 2016
GBP GBP GBP
Unaudited Unaudited Audited
Convertible loans 612,031 626,236 583,548
Draw down facility 149,500 - -
----------- ----------- ------------
761,531 626,236 583,548
----------- ----------- ------------
Convertible loans
The movement on each convertible loan liability component can be
summarised as follows:
Convertible loans 1 - 3 Convertible loan 4 Total
GBP GBP GBP
Balance at 1 January 2016 596,123 - 596,123
Finance charge: unwinding the discount factor 30,113 - 30,113
------------------------ --------------------- ----------
Balance at 30 June 2016 626,236 - 626,236
------------------------ --------------------- ----------
Issued on 2 November 2016 - 574,352 574,352
Finance charge: unwinding the discount factor 20,920 9,196 30,116
Embedded derivative - 300,503 300,503
Fair value adjustment to embedded derivative - (7,664) (7,664)
Extinguished on 2 November 2016 (647,156) - (647,156)
------------------------ --------------------- ----------
Balance at 31 December 2016 - 876,387 876,387
------------------------ --------------------- ----------
Finance charge: unwinding the discount factor - 28,483 28,483
Fair value adjustment to embedded derivative - (220,388) (220,388)
Balance at 30 June 2017 - 684,482 684,482
------------------------ --------------------- ----------
Equity component at 1 January 2016 and 30 June 2016 293,818 - 293,818
Extinguished on 2 November 2016 (293,818) - (293,818)
------------------------ --------------------- ----------
Equity component at 31 December 2016 and 30 June 2017 - - -
======================== ===================== ==========
All convertible loan stock is repayable on the 16 October 2019
and carries a zero coupon (nil interest).
The loan note will be convertible:
-- at the note holder's option at any time up to the end of the
term at a conversion price of 11 pence per ordinary share; and
-- at the Company's option after the second anniversary of
initial subscription provided that the one month volume weighted
average price of the Company's ordinary shares is in excess of 120%
of the conversion price and the closing mid-market price on the
date prior to the Company opting to convert exceeds 120% of the
conversion price.
In addition, if the Company sells its interest in its subsidiary
undertaking before the final repayment date for consideration
equivalent to or greater than 120% of the loan note outstanding
then the notes will become redeemable and a 20% premium will be
payable to the note holder.
A fair value exercise to determine the value of the three
components was undertaken by the Directors at the date the
convertible loan was initially drawn down.
The fair value of the host loan instrument (including the
embedded redemption feature) been valued as the residual of:
a) The fair value of the first draw down on 16 October 2014 is
discounted at a commercially applicable rate of 9.25%. The fair
values of the draw downs on 27 May 2016 and 2 October 2016 have
been discounted at a commercially applicable rate of 10.5%.
b) The residual amount between the transaction price of the loan
and the fair value of the liability has been allocated to an equity
reserve.
12. Borrowings and embedded derivative (continued)
Draw down facility - GBP150k
On 15 March 2017, BlueRock Diamonds plc agreed an unsecured loan
facility of up to GBP150,000 with Tim Leslie (Director), Mark Poole
(Major Shareholder) and Segar Properties (Hyde Park) Limited, a
company wholly owned by Paul Beck (Director). The loan term is to
31 December 2017 and carries a coupon of 10% per annum, payable at
the end of the term and contains no conversion provisions. The
transaction is further discussed in note 16.
13. Provisions
Reconciliation of provisions
Rehabilitation costs
GBP
Balance at 1 January 2016 81,718
Unwinding of discount 13,345
Balance at 30 June 2016 95,063
--------
Unwinding of discount 17,735
Balance at 31 December 2016 112,798
--------
Revaluation of provision 31,849
Balance at 30 June 2017 144,647
--------
The provision for environmental rehabilitation closure cost was
independently assessed by Ndi Mudau of NDI Geological Consulting
Services. The closure cost assessment reports over the Remainder of
the Farm No. 113 (Skietfontein), Portion of Portion 2
(Kareeboompan) of the Farm 142, Portion 1 (Westhoek) of the Farm
113, and Portion 2 (Klipvlei) of the Farm 113. The financial
provision was calculated in accordance with Regulation 54 of the
Minerals and Petroleum Resources Development Act 2002 (Act 28 of
2002) and is dated 23 June 2017.
14. Cash used in operations
30 June 30 June 31 December
2017 2016 2016
GBP GBP GBP
Unaudited Unaudited Audited
Loss before taxation (867,164) (310,324) (495,493)
Adjustments for non-cash items:
Depreciation and amortisation 131,036 79,905 171,258
Loss on disposal of fixed
assets 18,197 7,809 -
Embedded derivative charge (220,388) - 292,839
Share based payment expense 77,903 - 34,339
Impairment on acquisition
of Diamond Resources (Pty)
Limited - - 32,826
Finance charge on convertible
loan notes 28,483 30,113 60,229
Foreign exchange revaluation
gain / (loss) on fixed assets 17,768 (75,384) (220,602)
Movements in provisions (1,701) 13,345 31,080
Changes in working capital:
Decrease / (increase) in trade
and other receivables 87,686 (34,330) (124,374)
Increase in trade and other
payables 17,564 143,582 6,177
(Increase) / decrease in inventories (13,728) 23,791 48,463
(724,344) (121,493) (163,258)
---------- ---------- -----------
15. EPS (Earnings per share)
30 June 30 June 31 December
2017 2016 2016
GBP GBP GBP
Unaudited Unaudited Audited
Loss attributable to ordinary
shareholders (550,067) (353,777) (814,981)
Weighted average number of
shares 57,645,136 35,009,972 39,466,581
Loss per share basic and
diluted (0.01) (0.01) (0.02)
Weighted average number of
shares after dilution 57,645,136 35,009,972 39,466,581
Fully diluted earnings per
share (0.01) (0.01) (0.02)
Share options granted to directors could potentially dilute EPS
in the future but are not included in a dilutive EPS calculation
because they are antidilutive for the period.
16. Related party transactions
Relationships
Minority Interest -- William Kgalagadi Engineering
van Wyk & Mining Supplies (Pty)
Ltd
Ghaap Mining (Pty)
Ltd
Shareholder - Mark Poole BlueRock Diamond
Shareholder's Daughter - BlueRock Diamond
Emma Poole
Placing and Subscription
As part of the GBP366,000 placing and subscription on 1 June
2017, Paul Beck, Non-Executive Chairman of the Company, has
subscribed for 333,333 New Shares, following which he will have a
beneficial interest in 2,551,231 Ordinary Shares representing 3.8%
of the issued share capital and total voting rights of the Company.
Included in Mr Beck's beneficial interest are 455,455 Ordinary
Shares held by Front Square Securities Limited, a company wholly
owned by Mr Beck and his wife and of which Mr Beck is a
director.
Borrowings
On 15 March 2017, the Company agreed the terms of a GBP150,000
unsecured loan facility with Tim Leslie and Paul Beck, two of its
directors, and Mark Poole, one of its major shareholders (the "Loan
Facility") in order to provide extra working capital.
The Loan Facility, comprising of a maximum contribution from Tim
Leslie and Mark Poole of GBP62,500 each and Segar Properties (Hyde
Park) Limited, a company wholly owned by Paul Beck, GBP25,000, has
a term until 31 December 2017 and a coupon of 10% per annum,
payable at the end of the term. At 30 June 2017 the full loan
facility had been drawn down and remained outstanding, for further
detail see note 12.
Additionally, in June 2017 Mark Poole advanced GBP194,377 in
advance of agreeing the asset finance facility, which was agreed on
20 July 2017, see note 17 for further details.
Transactions with related party companies
Kareevlei Mining made payments of GBP43,499 (2016: nil) to
Kgalagadi Engineering & Mining Supplies (Pty)Ltd for the
acquisition of mine equipment and related services. William van Wyk
is a shareholder in Kgalagadi Engineering & Mining Supplies
(Pty) Ltd.
17. Events after the reporting period
Asset finance facility
On 20 July 2017, BlueRock Diamonds plc and its subsidiary
Kareevlei Mining PTY Limited have entered into an asset finance
facility of up to GBP310,000 ("Loan Facility") with Mark Poole, a
substantial shareholder in the Company. The Loan Facility will be
used to purchase essential equipment for the efficient and cost
effective operation of the mine.
The Loan Facility carries an interest rate of 10% over a
five-year term, repayable in 19 equal quarterly instalments
following an initial three-month interest free period. The Loan
Facility is unsecured but it carries the right for the purchase of
the capital goods acquired utilising the Loan Facility for ZAR 1 in
the event of the Group's default.
Placing and subscription update
On 10 August 2017, the Company raised an aggregate of GBP860,000
(before expenses) via the issue of 68,800,000 new ordinary shares
of 1 pence each in the capital of BlueRock Diamonds plc (the "New
Shares") through a placing and subscription at a price of 1.25
pence per New Share.
Adam Waugh, Chief Executive Officer of the Company has agreed to
subscribe for 4,000,000 New shares in the Fundraising.
Extension of loan facility
On 10 August 2017, BlueRock Diamonds plc successfully agreed the
extension of the maturity date on the six month loan facility of up
to GBP150,000 entered into on 15 March 2017 with Tim Leslie, Mark
Poole and Segar Properties (Hyde Park) Limited, a company wholly
owned by Paul Beck. The extension from the current maturity date of
15 September 2017 has been agreed to the 31 December 2017. The loan
carries a coupon of 10% per annum, payable at the end of the term
and contains no conversion provisions.
Issue of new share options
On the 10 August 2017, BlueRock Diamonds plc announced that it
has granted the following new share options to Adam Waugh (the
Company's CEO), Johan Milho, (the Company's mine manager) and Paul
Beck (the Company's non-executive Chairman). The details of the
issue are noted below:
Individual Tranche A Tranche B
No. of New No. of New Share
Share Options Options
Adam Waugh 3,417,740 3,417,740
Johan Milho 683,548 683,548
Paul Beck 992,096 992,096
Tranche A options have an exercise price of 1.25p, and Tranche B
options have an exercise price of 2.25p.
This information is provided by RNS
The company news service from the London Stock Exchange
END
IR BVLLFDKFEBBX
(END) Dow Jones Newswires
September 19, 2017 02:01 ET (06:01 GMT)
Bluerock Diamonds (LSE:BRD)
Historical Stock Chart
From Apr 2024 to May 2024
Bluerock Diamonds (LSE:BRD)
Historical Stock Chart
From May 2023 to May 2024