VANCOUVER, BC, Oct. 24,
2024 /CNW/ - Foran Mining Corporation (TSX: FOM)
(OTCQX: FMCXF) ("Foran" or the "Company") is pleased provide a
construction update on its 100% owned McIlvenna Bay project in
Saskatchewan, Canada. As of the
quarter ending September 30, 2024,
the project continues to advance steadily, with significant
progress made across key areas of development.
Key Achievements as of September 30,
2024:
- Safety performance remains strong with no Lost Time injuries
year-to-date, and a workforce of approximately 141 Foran
employees and over 330 contractors on-site.
- Significant progress was made with the completion of concrete
pouring for the semi-autogenous grinding ("SAG") and ball mill
monuments, nearing completion on foundation work for grinding,
copper flotation, and zinc flotation areas, and pouring
approximately 2,911m³ of concrete, exceeding the year-to-date
plan.
- Key equipment, including the 275-tonne crane and SAG/ball mill
components, arrived on site, with structural steel and regrind
mills in transit, and the concentrate filter press and pebble
crusher in final assembly or testing.
- Camp was fully commissioned, increasing bed capacity to
approximately 450. Notable progress included commissioning the
water and sewage plants, concrete work for the truck shop, and
advancing earthworks on the water containment pond, pipeline, and
ore pad expansion.
- Detailed engineering is approximately 78% complete, and 2024
and early 2025 activities including the mill foundation, process
and paste plant buildings, sewage and potable water treatment
plants, roads, ponds, berms, and truck shop are at
approximately 97% completion.
- Underground development has reached a total of approximately
1,375 metres, including 1,196 metres completed year-to-date, with
the decline extending 10 vertical meters below the 120-metre
level.
- Surface construction is approximately 14% complete, with the
overall schedule tracking as planned and commercial production
expected in H1 2026.
- The images offer a detailed look at key milestones reached
during the quarter and can be viewed below or in the image gallery
on our website at www.foranmining.com/news-media.
- A video, showcasing the McIlvenna Bay project,
highlighting management, key milestones and the Company's vision
towards initial phase production can be viewed here.
Dan Myerson, Executive Chairman
and CEO of Foran, commented "We are proud of the substantial
progress made this past quarter, achieved through the dedication of
our team and an unwavering commitment to safety. Building mines is
demanding work, but we believe there is no greater way to create
value, and it's incredibly rewarding for everyone involved. I'm
especially proud of the tireless efforts of our people in seizing
this unique opportunity to bring a greenfield asset into
production, while remaining focused on delivering the project on
time and on budget. Our people are our greatest asset, and it's
their exceptional talent and the incredible culture we've built
that drive our success every day. As we approach producer status,
we look forward to providing regular construction updates and
continuing to unlock the full value of our district."
Construction Progress Summary
Description
|
Progress to Date (as
of September 30, 2024, unless otherwise stated)
|
Health &
Safety
|
o
Lost Time Incident Frequency Rate (LTIFR) year-to-date of zero and
a Total
Recordable Incident Frequency Rate (TRIFR)
year-to-date of 2.3 after over
515,000 total person-hours worked in
2024.
|
Construction
Progress &
Schedule
|
o As at
quarter end, overall completion of surface construction stood
at
approximately 14%. The overall schedule remains
in line with previous
guidance, with commercial production
anticipated in H1/26.
|
Engineering
|
o
Engineering progress for activities planned for 2024 and early
2025, such as
the mill foundation, process and paste plant
buildings, sewage and potable
water treatment plants, roads, ponds, berms,
and truck shop building are approximately 97%.
o
Approximately 78% of overall detailed engineering has been
completed.
|
Procurement
|
o
Procurement is managing 191 work packages, with 128 packages
awarded to
date.
|
Underground
Development
|
o
Approximately 1,196m of total underground development has been
completed YTD, bringing total development
underground of approximately
1,375m.
o
Lateral development rates increased to over 290m in September, with
a total
of approximately 607m of underground
development completed during the
quarter.
o The
decline is approximately 10 vertical metres below the 120m
level.
o The
excavation of the main surface ventilation fresh air raise to
approximately
20 metres in depth.
|
Permitting
|
o Key
permits continue to be received to continue with progress at site.
Recent
requests have been submitted for the Return
Air Raise (RAR) construction,
process water line alteration
and treated water use. The worker noise expo-
sure assessment, crown work authorization
amendment and extensions for
permits to construct have been
submitted.
|
Human
Resources
|
o
Approximately 141 Foran employees and over 330 contractors are
currently
employed at the project.
|
Process Plant
During the third quarter of 2024, the construction team
completed concrete pouring for the SAG mill and ball mill
monuments, with construction of the foundations for the columns for
the grinding, copper flotation and zinc flotation areas nearing
completion.
A total of approximately 2,911m3 of concrete was poured during
the quarter, with approximately 4,503m3 completed year-to-date and
ahead of plan of 3,084m3.
Approximately 85% of the lean concrete has been poured in the
process plant. The concrete footings for the primary
structural steel columns for Zones 1, 2 and 3 (grinding, copper
flotation and zinc flotation) were also completed. Over the
quarter, concrete works began on the reagents, concentrate loadout,
and concentrate filtration areas.
Various components for both the SAG mill and ball mill arrived
on site in late September, with the regrind mills and the
structural steel for the process plant being in transit at the end
of the quarter. Also in September, the concentrate filter press was
in factory acceptance testing and the pebble crusher was being
assembled.
Permanent Camp and Surface Infrastructure
During the quarter, all phases of the permanent camp were
completed and commissioned for occupancy in addition to temporary
construction camps, bringing total bed capacity to approximately
450 persons. Average camp occupancy during September was between
approximately 250 and 300 persons, with increased requirements
expected over the next 12 months.
The company commissioned the potable water and sewage treatment
plants over the quarter while also constructing the weeping tile
bed. The lean concrete for the truck shop has been completed and
work began on forming and pouring of the concrete walls for the
surface maintenance shop equipment bay in preparation for standing
structural steel columns scheduled to commence in October. The
floor of the soon-to-be-relocated underground equipment shop was
also formed and poured during the month of September.
Additional earthworks operations progressed on the contact water
holding pond, with the removal of topsoil to bedrock. Drilling
operations began to excavate the underlying bedrock to the design
elevation. Earthworks also progressed on the Winn Bay treated water
discharge pipeline and the waste rock and ore pad expansion.
Transmission Line
As announced on July 15, 2024,
SaskPower and Foran are constructing a dedicated, 77km long power
transmission line with 138 kV capacity originating from the Island
Falls Hydro Generating Station, terminating at the McIlvenna Bay
project site. This transmission line will have additional load
capacity available, potentially enhancing economies of scale in any
future expansion phases.
As part of the construction schedule, SaskPower has submitted
the Environmental Impact Study ("EIS") application, which is
currently under review by the Ministry of the Environment. Comments
from the Environmental Accreditation Board ("EAB") have been
received and are in progress of being responded to and addressed by
mid-October. Long lead items such as pole structures have been
ordered.
Engineering and Procurement
Detailed engineering is substantially complete on the mill
foundation, process and paste plant buildings, treatment plants,
roads, ponds, berms, and truck shop building. The remaining focus
will be primarily on the civil, structural, architectural and
electrical and instrumentation disciplines, which are related to
the process plant. To date, total detailed engineering is
approximately 78% complete.
Procurement work in progress stands at approximately 72%
completed as of September 30, 2024.
Several long-lead items, including major mill components and a
portion of the project's mobile mining equipment fleet, have been
procured. Major construction packages remaining outstanding at the
quarter end are steel installation and SMPEI packages for the
process plant.
Underground Development & Pre-Production Mining
The Company successfully reached first ore over the quarter,
with the first development round in ore blasted in September and
contact locations reconciling favourably to the block model. The
ore will remain underground before being hauled to surface in
Q1/25. The Company is targeting to have approximately 275,000
tonnes of mineralized material in stockpile prior to ramp up in
December 2025.
To-date, the Company has advanced approximately 752 metres of
decline development and completed 623 metres of level development,
for a total of 1,375 metres to-date, including metres advanced in
the advanced exploration phase and prior to the start of the Phase
1 capital budget. The company remains focused on accelerating
development rates by maintaining crews at full strength, with
additional miners to fill unplanned contractor labour shortages.
Efforts are also underway to reduce cycle times and ensure the
operation of a reliable equipment fleet. The Company expects to
complete approximately 1,200 metres of total development in Q4/24
and approximately 7,000 metres in 2025, which is expected to be
sufficient to build the intended mill stockpile and ensure the
required production stopes are accessible prior to scheduled
production ramp up.
The collar of main surface ventilation fresh air raise has been
established and has progressed down approximately 20 metres,
reaching the sandstone layer. Concrete rings are now being
installed at this elevation to ensure any potential water inflows
are properly sealed.
Human Resources
As of September 30, 2024, 474
persons were employed by or contracted to Foran. Foran collects
diversity employment data based on voluntary declaration. On this
basis, 16% are female and 26% are Indigenous persons. 21% of our
site employees and contractors are residents of Saskatchewan
North.
Schedule and Budget
The project remains on schedule to start hot commissioning in
H2/25 and commercial production in H1/26. The project's main
critical path activities include installation of the primary
structural steel and cladding for the mill, installation of the SAG
mill and Ball mill, installation of the copper and zinc flotation
circuits and commissioning and the ramp up to commercial
production.
As disclosed concurrently with the Formal Investment Decision
made by the Company's Board of Directors on July 15, 2024, the Phase 1 project capital costs
have been estimated to completion at $826
million, excluding advanced exploration, early works and
other costs incurred up to and including May
31, 2024. From June 1, 2024 to
September 30, 2024, the Company
incurred approximately $124.4 million
of costs on an unaudited basis towards its Phase 1 Capital budget.
As at September 30, 2024, a total of
29% of construction costs were committed.
As at September 30, 2024, the
project has not drawn from its C$77M
contingency reserve, resulting in an unused contingency of
C$77M. As at the end of September 30, 2024 the total Phase 1 Capital
Budget remains unchanged.
Financial & Corporate Update
During the quarter ended September 30,
2024, the Company successfully received shareholder approval
and closed the second and final tranche of its previously announced
$360 million private placement.
Subsequent to quarter end, the Company also announced the execution
of an amended and restated credit agreement and closing of an
upsized US$250 million senior secured
project credit facility (the "Credit Facility") with a fund managed
by Sprott Resource Lending Corp. Funds from the Credit Facility
will be used towards construction of the McIlvenna Bay project in
east-central Saskatchewan as well
as general corporate purposes.
During the quarter, the Company also successfully reduced its
outstanding surety bond from $14.9
million to $5.5 million,
resulting in the release of restricted cash by approximately
$3.5 million. Furthermore, over the
quarter, the Company obtained a $19.3
million amended and restated revolving letter of credit
facility (the "LC Facility") to support certain requirements under
its transmission line construction agreement with Saskpower. The LC
Facility is now fully drawn and supported by a $13.5 million performance guarantee from the
Export Development Canada, with the company posting approximately
$5.8 million of restricted cash as
collateral.
The Company intends to file its financial statements and
MD&A for the quarter ended September 30,
2024 on or about November 7th,
2024.
Qualified Person
Mr. Samuele Renelli, P. Eng.,
Vice President, Technical Services for Foran, is the Qualified
Person for all technical information in this news release and has
reviewed, verified and approved the technical information in this
news release.
About Foran Mining
Foran Mining is a copper-zinc-gold-silver exploration and
development Company, committed to supporting a greener future,
empowering communities and creating circular economies which create
value for all our stakeholders, while also safeguarding the
environment. The McIlvenna Bay project is located entirely
within the documented traditional territory of the Peter Ballantyne
Cree Nation, comprises the infrastructure and works related to
development and advanced exploration activities of the Company, and
hosts the McIlvenna Bay Deposit and Tesla Zone. The Company also
owns the Bigstone Deposit, a resource-development stage deposit
located 25 km southwest of the McIlvenna Bay Property.
The McIlvenna Bay Deposit is a copper-zinc-gold-silver rich VHMS
deposit intended to be the centre of a new mining camp in a
prolific district that has already been producing for 100 years.
The McIlvenna Bay Property sits just 65 km West of Flin Flon, Manitoba, and is part of the world
class Flin Flon Greenstone Belt that extends from Snow Lake, Manitoba, through Flin Flon to Foran's ground in eastern
Saskatchewan, a distance of over
225 km.
The McIlvenna Bay Deposit is the largest undeveloped VHMS
deposit in the region. The Company announced the results from its
NI 43-101 compliant Technical Report on the 2022 Feasibility Study
for the McIlvenna Bay Deposit ("2022 Feasibility Study") on
February 28, 2022, outlining that
current Mineral Reserves would potentially support an 18-year mine
life producing an average of 65 million pounds of copper equivalent
annually. The Company filed the 2022 Feasibility Study on
April 14, 2022, with an effective
date of February 28, 2022. The
Company also filed a NI 43-101 Technical Report for the Bigstone
Deposit resource estimate on January 21,
2021, as amended on February 1,
2022. Investors are encouraged to consult the full text of
these technical reports which may be found on the Company's profile
on www.sedarplus.ca.
The Company's head office is located at 409 Granville Street,
Suite 904, Vancouver, BC,
Canada, V6C 1T2. Common Shares of
the Company are listed for trading on the TSX under the symbol
"FOM" and on the OTCQX under the symbol "FMCXF".
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS
This news release contains certain forward-looking information
and forward-looking statements, as defined under applicable
securities laws (collectively referred to herein as
"forward-looking statements"). These statements relate to future
events or to the future performance of Foran Mining Corporation and
reflect management's expectations and assumptions as of the date
hereof or as of the date of such forward looking statement. Such
forward-looking statements include, but are not limited, statements
regarding our objectives and our strategies to achieve such
objectives; our beliefs, plans, estimates, projections and
intentions, and similar statements concerning anticipated future
events; as well as specific statements in respect of our
development of the McIlvenna Bay project, including in respect of
construction, targets, timelines, activities, speed, and progress;
our ability to develop the McIlvenna Bay Project safely and timely;
our intention to provide construction updates following the quarter
ending September 30, 2024; our
plans and objectives in respect of our underground development; our
commitment to safety; our ability to develop the McIlvenna Bay
project and deliver critical minerals to market; the expectation
that global demand for critical minerals is growing; our
construction progress targets and estimates, including in respect
of engineering, procurement, underground development, permitting,
and human resources; our goal of achieving commercial production in
H1 2026; our applications for certain key permits; expectations and
objectives regarding the process plant, permanent camp and surface
infrastructure, transmission line, engineering and procurement,
pre-production mining, and our schedule and budget; our expectation
that camp occupancy will increase in the coming months; our
intention to focus on certain disciplines in connection with
engineering and procurement; our ability to complete major
construction packages that remain outstanding; our intention to
haul ore to surface in Q1 2025 and target to have approximately
275,000 tonnes of mineralized material in stockpile prior to
December 2025; the reconciliation of
ore to our block model; our ability to accelerate development
rates, fill unplanned contractor labour shortages, reduce cycle
times and ensure that we operate a reliable equipment fleet; our
targeted completion of approximately 1,200 metres of total
development in Q4 2024 and approximately 7,000 metres in 2025, and
that this will be sufficient to build the intended mill stockpile
and ensure required production stope accessibility prior to
production ramp up; starting hot commissioning in H2 2025; our
ability to successfully complete critical path activities,
including in respect of structural steel, mills, flotation
circuits, and commissioning and ramp up to commercial production;
estimated Phase 1 project capital completion costs of $826 million; potential future reclamation
liabilities; our commitment to support a greener future, empower
communities and create circular economies which create value for
all our stakeholders while safeguarding the environment;
expectations regarding our development and advanced exploration
activities; and expectations, assumptions and targets in respect of
our 2022 Feasibility Study. All statements other than statements of
historical fact are forward-looking statements. The forward-looking
statements in this news release speak only as of the date of this
news release or as of the date specified in such statement.
Inherent in forward-looking statements are known and unknown
risks, estimates, assumptions, uncertainties and other factors that
may cause the actual results, performance or achievements of the
Company to be materially different from any future results,
performance or achievements expressed or implied by the
forward-looking statements contained in this news release. These
factors include management's belief or expectations relating to the
following and, in certain cases, management's response with regard
to the following: the Company's reliance on the McIlvenna Bay
Property; the Company is exposed to risks related to mineral
resources exploration and development; the Company has no history
of mineral production; the Company's operations are subject to
extensive environmental, health and safety regulations; mining
operations involve hazards and risks; and the additional risks
identified in our filings with Canadian securities regulators on
SEDAR+ in Canada (available at
www.sedarplus.ca). The forward-looking statements contained in this
news release reflect the Company's current views with respect to
future events and are necessarily based upon a number of
assumptions that, while considered reasonable by the Company, are
inherently subject to significant operational, business, economic
and regulatory uncertainties and contingencies. These assumptions
include the availability of funds for the Company's projects;
availability of equipment; sustained labour stability with no
labour-related disruptions; all necessary permits, licenses and
regulatory approvals are received in a timely manner; and the
ability to comply with environmental, health and safety laws.
Although the Company has attempted to identify important factors
that could cause actual results to differ materially, there may be
other factors that cause results not to be as anticipated,
estimated, described or intended.
Readers are cautioned not to place undue reliance on
forward-looking statements and should note that the assumptions and
risk factors discussed in this press release are not exhaustive.
Actual results and developments are likely to differ, and may
differ materially, from those expressed or implied by the forward
looking statements contained in this press release. All
forward-looking statements herein are qualified by this cautionary
statement. The Company disclaims any intention or obligation to
update or revise any forward looking statements, whether as a
result of new information, future events or otherwise, except as
may be required by law. If the Company does update one or more
forward-looking statements, no inference should be drawn that it
will make additional updates with respect to those or other
forward-looking statements, unless required by law. Additional
information about these assumptions, risks and uncertainties is
contained in our filings with securities regulators on SEDAR+ in
Canada (available at
www.sedarplus.ca).
SOURCE Foran Mining Corporation