TSXV: ARTG
Project remains fully funded and on budget;
87% complete at the end of June 2024
and on schedule to pour first gold in Q4 2024
VANCOUVER, BC, July 30,
2024 /CNW/ - Artemis Gold Inc. (TSXV: ARTG)
("Artemis Gold" or the "Company") provides an update on Q2
construction progress at the Blackwater Mine in central
British Columbia. The project
remains fully funded and currently on schedule for first gold pour
in Q4 2024.
At June 30, 2024 overall
construction was approximately 87% complete, and approximately
C$650 million of the capital budget
of C$730 to C$750 million had been spent.
Steven Dean, Chairman and CEO of
Artemis Gold, stated: "Through to June 30,
2024, we continued to advance construction and progress our
operational readiness plans in-line with our expected timelines.
The development of gold mines is complex and requires multiple
skill sets and disciplines including risk management. This month we
were challenged again by wildfires in the area of the mine and I
would like to recognize the Blackwater team's efforts to safely and
orderly demobilize staff upon receipt of the recent wildfire
evacuation order. Last week's response to the lifting of the order
and commencement of an expedient return and ramp-up to full-scale
construction was a credit to our team."
Construction Update
Construction of the water management pond, excavation of the
cutoff trench through Mine Creek in
the tailings storage facility, and the earthworks and lining of the
central water management pond were completed. Work on the tailings
storage facility continues to progress well with increased
productivity and material movements through the quarter.
Total major works hours worked up to June
30, 2024 surpassed 2.5 million hours with a zero
LTIFR1 and an AIFR2 of 78.44.
Process Plant
At the end of June 2024, the
Sedgman EPC contract work on the processing plant was approximately
90% complete overall, with engineering, design and procurement
materially complete.
Equipment installation was a key focus area for Q2 as well as
installation of structural steel, conveyors, platework, pipework,
and electrical infrastructure. Installation of the primary crusher
commenced, and utilities were installed across the crushing
circuit, allowing for pre-commissioning activities on the crushing
circuit to commence. Mill installation advanced, while the cyclone,
gravity concentrators and the sulphur burner were installed.
Cladding of the reagents building was completed, and the mill
building will soon be ready to be clad following final equipment
installation. Hydro testing of the process and raw water tanks was
completed, and tank infrastructure completed, with tank top
installations well advanced.
Early pre-commissioning activities in the crushing area of the
process facility is underway.
Transmission Line
During Q2 2024 the transmission line continued to advance on
schedule. The line is being built in two parts, north and south of
the Nechako River. The length of the northern section is
approximately 50km and the southern section is approximately
80km.
In the North section, 98% of foundations are complete, 97% of
pole structures are installed, 95% of structural frames are
complete and 25% of the conductor was installed.
In the South section, 91% of foundations are complete, 84% of
pole structures are installed, 69% of structural frames are
complete and 10% of the conductor was installed.
Upgrades to the BC Hydro Glenannan substation were completed,
while commissioning planning with BC Hydro is advancing as
planned.
The main 25 kV electrical substation to power infrastructure at
Blackwater Mine was installed, and pole installation and conductor
stringing across the asset is well progressed.
Heavy Equipment
During Q2 2024, construction and commissioning of the initial
phase of the mining fleet was completed, with two 400-tonne
hydraulic backhoe excavators, nine 240-tonne rigid frame haul
trucks, and two large mining front-end loaders now fully assembled.
The fleet to support initial operations is now complete. Additional
units are on-site and are currently being assembled, with the
intent to add these to the fleet as operations ramp up.
Personnel
The Company maintained its workforce of approximately 350
employees in Q2 2024 and the ratios of the workforce have remained
consistent, approximately:
- 20% of the team are women;
- 30% identify as Indigenous;
- 45% are from the local region, and
- 80% are B.C. residents.
The total Blackwater Mine workforce, including staff and
contractors employed at the mine site and along the transmission
line, surpassed 800 at the end of June.
Operational Readiness
Recruitment of personnel for the Blackwater Mine operations
commenced earlier this year and the full operations management team
is now in place.
Key personnel have been mobilized to initiate pre-commissioning
activities in the crushing area.
Operations preparation and integration is now underway.
Wildfire Response
On July 22, 2024, the Company
announced that it responded to a wildfire evacuation order issued
across a region that included the Blackwater Mine. The Company
proactively removed all non-essential staff and contractors from
site and took the necessary precautions to safeguard the asset,
with essential staff remaining. On July
26, the Company announced the evacuation order had been
lifted, and began an expedient, staged return of employees and
contractors to site. The mine site was not impacted by any
wildfires.
Funding
During Q2 2024 the Company completed the third and final draw of
C$80 million under the project loan
facility, bringing the total drawn to C$380
million, along with approximately C$12 million in cumulative capitalized
interest.
At June 30, 2024, Artemis Gold had
estimated remaining Phase 1 capital expenditures of approximately
C$100 million. At the same date, the
committed sources of funding totalled C$164
million, comprising:
- cash and cash equivalents of C$111
million;
- approximately C$13 million of
capitalized interest remaining available, and
- a cost overrun facility of C$40
million.
In addition, the Company had 20.5 million warrants outstanding
at June 30, 2024, which are
exercisable at C$1.08 per warrant
before August 27, 2024, for
anticipated proceeds of C$22
million.
Artemis Gold President and COO Jeremy
Langford commented: "Looking ahead to Q3 2024, we expect to
complete construction of the new operations camp and decommission
the original exploration camp. We will commence the pre-production
mining works and expect to begin commissioning the process facility
and the water management pond. By the end of Q3, we anticipate the
transmission line will be nearing completion and we remain on track
for first gold pour in Q4 2024."
Video
Watch here for a Q2 project update video:
https://youtu.be/McTJRTSby-s
Photos – July 2024
About Artemis Gold
Artemis Gold is a well-financed, growth-oriented gold
development company with a strong financial capacity aimed at
creating shareholder value through the identification, acquisition,
and development of gold properties in mining-friendly
jurisdictions. The Company's current focus is the construction of
the Blackwater Mine in central British
Columbia approximately 160km southwest of Prince George and 450km northeast of
Vancouver. The project is one of
the largest capital investments in central British Columbia in over a decade. The first
pour of gold and silver at Blackwater is expected in Q4 2024.
Artemis Gold trades on the TSX-V under the symbol ARTG. For more
information visit www.artemisgoldinc.com.
Qualified Person
Jeremy Langford, FAUSIMM, a
Qualified Person as defined by National Instrument 43-101, has
reviewed and approved the scientific and technical information in
this press release.
On behalf of the Board of Directors
Steven Dean
Chairman and Chief Executive Officer
+1 604 558 1107
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this news release.
Cautionary Note Regarding Forward-looking Information
This press release contains certain forward-looking
statements and forward-looking information as defined under
applicable Canadian and U.S. securities laws. Statements contained
in this press release that are not historical facts are
forward-looking statements that involve known and unknown risks and
uncertainties. Any statements that refer to expectations,
projections or other characterizations of future events or
circumstances contain forward-looking statements. In certain cases,
forward-looking statements and information can be identified using
forward-looking terminology such as "may", "will", "expect",
"intend", "estimate", "anticipate", "believe", "continue", "plans",
"potential" or similar terminology. Forward-looking statements and
information are made as of the date of this press release, and
include, but are not limited to, statements regarding the potential
of the Blackwater mine project; the jobs to be created in
connection with the project; the contribution of the project to the
economy; opinions of the Province of British Columbia regarding the project and the
region; agreements and relationships with Indigenous partners; the
future of mining in British
Columbia; the plans of the Company with respect to the
project, including construction, site preparation, clearing,
consultation with indigenous groups, and other plans and
expectations of the Company with respect to the project.
These forward-looking statements represent management's
current beliefs, expectations, estimates and projections regarding
future events and operating performance, which are based on
information currently available to management, management's
historical experience, perception of trends and current business
conditions, expected future developments and other factors which
management considers appropriate. Such forward-looking statements
involve numerous risks and uncertainties, and actual results may
vary. Important risks and other factors that may cause actual
results to vary include, without limitation: risks related to the
ability of the Company to accomplish its plans and objectives with
respect to the development of the project within the expected
timing or at all, the timing and receipt of certain required
approvals, changes in commodity prices, changes in interest and
currency exchange rates, risks inherent in exploration estimates
and results, risks inherent in exploration and development
activities, changes in development or mining plans due to changes
in logistical, technical or other factors, unanticipated
operational difficulties (including failure of plant, equipment or
processes to operate in accordance with specifications, cost
escalation, unavailability of materials, equipment or third party
contractors, delays in the receipt of government approvals,
industrial disturbances, job action, and unanticipated events
related to heath, safety and environmental matters), changes in
governmental regulation of mining operations, political risk,
social unrest, changes in general economic conditions or conditions
in the financial markets, and other risks related to the ability of
the Company to proceed with its plans for the project and other
risks set out in the Company's most recent MD&A, which is
available on the Company's website at
www.artemisgoldinc.com and on SEDAR+ at
www.sedarplus.ca
In making the forward-looking statements in this press
release, the Company has applied several material assumptions,
including without limitation, the assumptions that: (1) market
fundamentals will result in sustained mineral demand and prices;
(2) any necessary approvals and consents in connection with the
development of the project will be obtained; (3) financing for the
development, construction and continued operation of the project
will continue to be available on terms suitable to the Company; (4)
sustained commodity prices will continue to make the project
economically viable; and (5) there will not be any unfavourable
changes to the economic, political, permitting and legal climate in
which the Company operates. Although the Company has attempted to
identify important factors that could affect the Company and may
cause actual actions, events, or results to differ materially from
those described in forward-looking statements, there may be other
factors that cause the actual results or performance by the Company
to differ materially from those expressed in or implied by any
forward-looking statements. Accordingly, no assurances can be given
that any of the events anticipated by the forward-looking
statements will transpire or occur, or if any of them do so, what
impact they will have on the results of operations or the financial
condition of the Company. Investors should therefore not place
undue reliance on forward-looking statements. The Company is under
no obligation and expressly disclaims any obligation, to update,
alter or otherwise revise any forward-looking statement, whether
written or oral, that may be made from time to time, whether
because of new information, future events or otherwise, except as
may be required under applicable securities laws.
1 LTIFR or
Lost Time Injury Frequency Rate refers to the number of lost time
injuries occurring per million man-hours worked, divided by total
man-hours worked.
|
2 AIFR
or All Injury Frequency Rate refers to the total number of
recordable incidents occurring per million man-hours worked,
divided by total man-hours worked.
|
SOURCE Artemis Gold Inc.