TSXV: GMIN
OTCQX: GMINF
All amounts are in USD unless stated
otherwise
- Project remains on track and on budget for commercial
production in H2-2024
- Safety remains a priority with over 856,329 man-hours worked
with no Lost Time Incidents
- 1,100 employees and contractors currently employed by the
Project (93% from within Brazil)
- Detailed engineering 62% completed
- Procurement 88% complete with remaining 12% in progress
- Project commitments total $235
million (51% of total) tracking in line with Feasibility
Study
- Updated virtual site tour available through VRIFY platform
BROSSARD, QC, March 6,
2023 /CNW/ - G Mining Ventures
Corp. ("GMIN" or the "Corporation") (TSXV:
GMIN) (OTCQX: GMINF) announced today that it hosted investor and
analyst site visits to its 100% owned Tocantinzinho Gold Project
("TZ" or the "Project") on Thursday, March 2, and Friday, March 3, 2023. GMIN is also pleased to
provide an update on the progress made at TZ, currently under
construction in the State of Pará, Brazil. Advancements include detailed
engineering, procurement, equipment delivery, workforce ramp up,
construction, and progress on open pit mining. The Project remains
on track and on budget for commercial production in H2-2024. All
updates are dated as of January 31st,
2023, unless stated otherwise.
Louis-Pierre Gignac, President
& Chief Executive Officer, commented: "The
dedication of our project staff and the flawless execution of our
proven self-perform approach has ensured that we continue to make
excellent progress on all fronts on our TZ project. I am pleased
that engineering, procurement, delivery, hiring, training,
construction and mining are all progressing well in terms of both
budget and schedule, as we continue to target commercial production
at TZ in the second half of 2024. At the same time, I am proud of
our commitment to continue to safeguard the wellbeing of our
workforce, community and the environment."
Virtual Site Tour and
Presentation
The site visit presentation, which contains construction and
other updates, is available on GMIN's website at
https://www.gminingventures.com, and through the following link at:
https://vrify.com/decks/12781
Tocantinzinho Project
Update
Detailed Engineering
Detailed engineering is 62% complete, allowing for project
procurement to progress to completion. Notable advancements to date
include:
- Engineering areas completed or near completion include: camp
with all supporting infrastructure, wash bay, administration
building, site guard house, assay laboratory, mill office, fuel
bay, temporary truck shop, temporary explosive storage and
powerline;
- Geotechnical parameters are finalized to proceed with final
stability analyses of the flotation tailings storage facility
("FTSF");
- Permanent camp civil and mechanical work is complete, with
piping and electrical work on schedule to allow for full occupancy
by end of March 2023; and
- Process plant detailed design (Figure 1) has reached
60%.
Figure 1 - Process Plant 3D Design
Procurement and Delivery
Overall Project procurement has progressed to 88% completion.
Expenditures and commitments to date total $235 million (51% of total), with expenditures
and schedule tracking in line with the Feasibility Study dated
February 09, 2022 (filed under GMIN's
profile on Sedar, entitled "Feasibility Study – NI 43-101 Technical
Report, Tocantinzinho Gold Project.").
A portion of the equipment has been delivered to date (Figure
2) commissioned, and is comprised of:
- Four CAT 777E Haul Trucks
- One CAT 6030 Hydraulic Mining Excavator
- One Sandvik Leopard Di650 Drill
Rig
- Two CAT 395 Hydraulic Excavators
- Two CAT 352 Hydraulic Excavators
- One CAT 980 Loader
- Three CAT 730 Articulated Trucks
Major bulk material packages issued include steel, cement and
form work, rebar, architectural material and buildings, and
powerline material (cables, towers, etc.).
Major equipment procured includes mining, processing and
electrical equipment, cranes, aggregate plant and batch plant.
Major services procured include blasting, forest suppression,
bussing and air transport, catering and freight forwarding.
Figure 2 – CAT 6030 Hydraulic Mining Excavator & CAT 777E
Mine Truck
Logistics network is working well, having moved 811 truckloads
of material and supplies to site during Q4-2022.
Figure 3 – Logistics Base in Morais
Almeida
Construction
The following major milestones have been reached in
construction:
- Improvements of deteriorated sections of the Transgarimpeira
State Road from Morais Almeida to
Jardim do Ouro were initiated;
- The municipal access road from Jardim do Ouro to site under the
responsibility of Brazauro was upgraded with the installation of
several culverts to improve overall drainage and to help control
erosion during the rainy season. All wooden bridge approaches were
installed and have enhanced safety on the road;
- The internal site road to the industrial area was
completed;
- Four dorms of the 1,200-person permanent camp are completed and
occupied, with work on track for completion of the full camp
including welcome center, sewage treatment plant and water
treatment plant in March;
- Permanent kitchen footings and walls were poured. The
structural erection of the kitchen is advancing well with Civil,
Structure and Architecture progress of 55% and overall completion
reaching 50%; and
- Bulk fuel storage of 420,000 liters is in process with civil
works completed and tanks installed.
Figure 4 – Site Access Road and Bridge Upgrades
Figure 5 – Permanent Camp Construction
Figure 6 – Fuel Storage Tank Installation
Pre-Production Mining
Pre-production mining in the starter pit was initiated with
commissioning of the first mine fleet units with 590,000 tonnes of
waste material excavated. The waste material was used for road
construction and in the future will be used to construct the
tailings dam. This material has undergone rigorous geotechnical
testing to assure its suitability. The starter pit has recently
reached fresh rock as expected, which provides competent material
for construction purposes, as a source for aggregate, and filter
material for constructing the FTSF. During the pre-production
period the ore stockpile will reach approximately 2.4 million
tonnes prior to commissioning representing about 6 months of mill
feed.
Figure 7 – Open Pit Mining
Powerline Construction (as of Feb
26, 2023)
Since the November 2022 issuance
of the Declaration of Public Utility ("DUP") on the 138 kV
power transmission line from Novo Progresso to TZ, by The National
Agency of Electric Energy ("ANEEL"), powerline construction
has commenced.
In summary:
- Detailed engineering of the powerline and substations was
completed, submitted, and approved by Equatorial Pará Distribuidora
de Energia S.A., the entity responsible for energy distribution in
the state of Pará;
- Selection of contractors for forest suppression and powerline
installation was finalized and all materials purchased;
- Powerline construction was initiated in December and is
progressing along two segments (1) from Novo Progresso to Jardim do
Ouro for 112 km and (2) Jardim do Ouro to TZ Project for 81
km;
- 84 foundations have been poured and 34 towers have been
assembled and erected out of a total of 483.
Figure 8 – Transmission Line Tower
Human Resources
1,100 employees and contractors are currently employed by the
Project with 93% of the workforce comprised of Brazilians. Of the
total workforce, 66% are from the nearby communities of Itaituba,
Morais Almeida, Mamoal, and Jardim
do Ouro.
Health & Safety
The Corporation continues to deliver on its core value of
prioritizing health and safety with a total of 856,329 man-hours
worked year to date with no Lost Time Incidents
("LTIs").
Figure 9 – Daily Morning Safety Meeting and
Stretching
Project Development Timeline
The Project remains on track and on budget for commercial
production in H2-2024.
Qualified Person
Louis-Pierre Gignac, President
& Chief Executive Officer of GMIN, a QP as defined in NI
43-101, has reviewed the press release on behalf of the Corporation
and has approved the technical disclosure contained in this press
release.
Timetable and Next Steps
Having made the positive construction decision, the Corporation
will be focused on the following activities:
- Completion of detailed engineering through H1-23;
- Issuance of inaugural ESG report in 2023; and
- Commercial production in H2-24.
Feasibility Study 3D VRIFY
Presentation
To view a 3D VRIFY presentation of the Study please click on the
following link: Feasibility Study 3D VRIFY Presentation, or
visit the Corporation's website at www.gminingventures.com.
About G Mining Ventures
Corp.
G Mining Ventures Corp. (TSXV: GMIN) (OTCQX: GMINF) is a mining
company engaged in the acquisition, exploration and development of
precious metal projects, to capitalize on the value uplift from
successful mine development. GMIN is well-positioned to grow into
the next mid-tier precious metals producer by leveraging strong
access to capital and proven development expertise. GMIN is
currently anchored by its flagship Tocantinzinho Gold Project in
mining friendly and prospective State of Pará, Brazil.
Neither the TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this press release.
Cautionary Statement on
Forward-Looking Information
All statements, other than statements of historical fact,
contained in this press release constitute "forward-looking
information" and "forward-looking statements" within the meaning of
certain securities laws and are based on expectations and
projections as of the date of this press release. Forward-looking
statements contained in this press release include, without
limitation, those related to (i) the Project being brought into
commercial production in H2-2024; (ii) completion of the full camp
in March; and (iii) more generally, the sections entitles
"Timetable and Next Steps" and "About G Mining Ventures
Corp.".
Forward-looking statements are based on expectations,
estimates and projections as of the time of this press release.
Forward-looking statements are necessarily based upon a number of
estimates and assumptions that, while considered reasonable by the
Corporation as of the time of such statements, are inherently
subject to significant business, economic and competitive
uncertainties and contingencies. These estimates and assumptions
may prove to be incorrect. Such assumptions include, without
limitation, those relating to the price of gold and currency
exchange rates and those underlying the items listed on the above
section entitled "About G Mining Ventures Corp.".
Many of these uncertainties and contingencies can directly or
indirectly affect, and could cause, actual results to differ
materially from those expressed or implied in any forward-looking
statements. There can be no assurance that, notably but without
limitation, the Corporation will (i) continue to progress on all
fronts at the Project, to carry the self-perform approach with
similar success as proven in the past and to continue taking care
of the health and safety of all its stakeholders (with no Lost Time
Incidents), (ii) keep its expenditures and schedule in line with
the February 9, 2022, Feasibility
Study, (iii) carry its next steps as per the above timetable, (iv)
bring the Project into commercial production in the second half of
2024, or at all, (v) advance TZ into one of the largest
operating gold mines in Brazil, or
(vi) use TZ to grow GMIN into the next intermediate producer, as
future events could differ materially from what is currently
anticipated by the Corporation. There is also no assurance that the
State of Pará, in Brazil, will
remain a mining friendly and prospective
jurisdiction.
By their very nature, forward-looking statements involve
inherent risks and uncertainties, both general and specific, and
risks exist that estimates, forecasts, projections and other
forward-looking statements will not be achieved or that assumptions
do not reflect future experience. Forward-looking statements are
provided for the purpose of providing information about
management's expectations and plans relating to the future. Readers
are cautioned not to place undue reliance on these forward-looking
statements as a number of important risk factors and future events
could cause the actual outcomes to differ materially from the
beliefs, plans, objectives, expectations, anticipations, estimates,
assumptions and intentions expressed in such forward-looking
statements. All of the forward-looking statements made in this
press release are qualified by these cautionary statements and
those made in the Corporation's other filings with the securities
regulators of Canada including,
but not limited to, the cautionary statements made in the relevant
sections of the Corporation's (i) Annual Information Form dated
June 3, 2022, for the financial year
ended December 31, 2021, and (ii)
Management Discussion & Analysis. The Corporation cautions that
the foregoing list of factors that may affect future results is not
exhaustive, and new, unforeseeable risks may arise from time to
time. The Corporation disclaims any intention or obligation to
update or revise any forward-looking statements or to explain any
material difference between subsequent actual events and such
forward-looking statements, except to the extent required by
applicable law.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/g-mining-ventures-hosts-inaugural-site-visits-to-tocantinzinho-gold-project-and-provides-project-update-301763049.html
SOURCE G Mining Ventures Corp