Definitive Feasibility Study
08 September 2009 - 6:54PM
UK Regulatory
TIDMFND
For Release: 8th September 2009
FINDERS RESOURCES LIMITED
Progress on Wetar Copper Definitive Feasibility Study
Finders Resources Limited (FND AIM/ASX) is pleased to report that the
definitive feasibility study (DFS) into its Wetar Copper Project is
substantially complete, with all project planning concepts and design
criteria covering infrastructure, mining and process now finalised.
As described in the Company's June 2009 quarterly report, one of the
key design criteria for the project has been the decision to
incorporate the 18,500tpa Whim Creek plant (which Finders has an
option to purchase for A$5 million) with an expansion of the existing
demonstration plant to 4,500tpa. In this regard the Company has
carried out further engineering design work than originally planned
to ensure the successful integration of the two plants to produce the
planned 23,000tpa of copper cathode.
A review of capital and operating costs generated by the DFS manager,
Ausenco, is underway. Part of this process includes analysis of
contractor pricing, and some delays are being experienced in
receiving responses from participating contractors.
In addition, ongoing operational results from the demonstration plant
have been a key component of the DFS, providing vital information to
substantially de-risk the full-scale project. The Company is pleased
that the ongoing copper leaching characteristics of the demonstration
ore heaps, after making appropriate allowances for the different
operating conditions between a demonstration plant and a full-scale
project, are consistent with the design criteria adopted in the DFS.
However, the demonstration plant leach pads have seen higher levels
of acid generation than those estimated during the laboratory test
work phase and an acid neutralisation plant has been constructed and
commissioned at the demonstration plant. This has also led to extra
test work in the DFS to determine the acid neutralisation criteria
required for the full-scale project. Adequate limestone resources
for the acid neutralisation required for the full-scale operation are
available from within the immediate project area, which will
substantially mitigate the additional costs of an acid neutralisation
circuit to the full scale development.
The Company now expects that with responses from contractors expected
in the next few weeks, and the additional neutralisation test work
currently being performed, the DFS results will be ready for
distribution to the market in 4 to 5 weeks time.
Finders Managing Director, Chris Farmer commented: "Although lagging
slightly behind our original schedule, the additional scope for the
DFS to include both acid neutralisation and a fully integrated
development incorporating expansion of our existing demonstration
plant with the Whim Creek SX-EW process plant optioned from Straits
Resources will significantly reduce the development risk for what
remains a low cost brownfields project."
For further information please contact
Finders Resources Ltd:
Russell Fountain Non-Executive Chairman +61 2 9211 8299
Chris Farmer Managing Director info@findersresources.com
Financial PR:
Doug Macdonald Capital Group (in +61 424 255 959
Australia)
Nick Elwes College Hill (in the UK) +44 20 7457 2020
RFC Corporate Finance Ltd - Nomad::
Rob Adamson Managing Director +61 2 9250 0000
Stuart Laing Executive Director +61 8 9480 2500
FinnCap - Finders' Broker for the AIM market:
Mathew Robinson Corporate Finance Director +44 (0) 20 7600 1658
Joe Lunn Analyst +44 20 7600 1658
Background on Finders Resources
Finders, listed on AIM and ASX, is the operator of the Wetar Copper
Project (92% and earning), and the Ojolali Gold-Silver Project (72%
with option), both located in Indonesia.
At the Wetar Project, as part of a definitive feasibility study, a
demonstration SX-EW plant with 5t per day copper cathode capacity was
commissioned in February 2009 and is permitted to process 100,000t of
ore from the Kali Kuning deposit. The demonstration plant is
producing LME Grade A copper cathode at planned rates. The Company
is targeting commercial production of 20-25,000 tonnes per year
cathode by 2010, subject to final feasibility, permitting and project
funding.
At the Ojolali Project, Finders controls what it considers to be a
major new epithermal gold district, and has been undertaking an
extensive exploration program comprising detailed drilling to
establish an initial mining resource, supported by extensive surface
geophysical and geochemical surveys. Finders believe that the Ojolali
project has strong potential to generate cash flow through open pit
CIL/CIP development of the gold resource at the Jambi Oxide gold
deposit.
For further information on results previously reported and a full
resource statement please visit our website www.findersresources.com.
Disclaimer
This announcement may or may not contain certain "forward-looking
statements". All statements, other than statements of historical
fact, which address activities, events or developments that Finders
believes, expects or anticipates will or may occur in the future, are
forward-looking statements. Forward-looking statements are often, but
not always, identified by the use of words such as "seek",
"anticipate", "believe", "plan", "estimate", "targeting", "expect",
and "intend" and statements that an event or result "may", "will",
"can", "should", "could", or "might" occur or be achieved and other
similar expressions. These forward-looking statements reflect the
current internal projections, expectations or beliefs of Finders
based on information currently available to Finders. Statements in
this document that are forward-looking and involve numerous risks and
uncertainties that could cause actual results to differ materially
from expected results are based on the Company's current beliefs and
assumptions regarding a large number of factors affecting its
business. Actual results may differ materially from expected results.
There can be no assurance that (i) the Company has correctly measured
or identified all of the factors affecting its business or the extent
of their likely impact, (ii) the publicly available information with
respect to these factors on which the Company's analysis is based is
complete or accurate, (iii) the Company's analysis is correct or (iv)
the Company's strategy, which is based in part on this analysis, will
be successful. Finders expressly disclaims any obligation to update
or revise any such forward-looking statements
=--END OF MESSAGE---
This announcement was originally distributed by Hugin. The issuer is
solely responsible for the content of this announcement.