TIDMGKO

RNS Number : 1503Q

Greenko Group plc

10 October 2013

10 October 2013

Greenko Group plc

("Greenko" or "the Company")

Trading Update

Greenko, the Indian developer, owner and operator of clean energy projects, today provides a trading update for the first half of its 2013-14 financial year, covering the period 1(st) April 2013 to 30(th) September 2013:

   --       Trading in-line with expectations 
   --       Installed capacity increased from 309 MW to 412 MW 
   --       Generation increased 15% to 650 GWh, compared to the previous year 
   --       102 MW of new wind capacity commissioned/completed since 1(st) April 2013 
   --       On track to complete construction of over 250 MW of new wind capacity this financial year 

Operational projects

Overall performance is in line with expectations, with generation increasing 15%, to 650 GWh, compared to the same period in 2012. The early monsoon helped increase southern hydro generation by 39%, and the wind assets delivered a strong performance. Northern hydro is now running well, with good plant availability helping offset earlier delays due to a late snowmelt and third party transmission issues. The biomass assets continue to underperform, due to issues around fuel supply, price and availability.

Projects under construction

   --       Ratnagiri Wind Farm (101.6 MW - Maharashtra). 

Phase-1 (65.6 MW) was successfully commissioned at the start of the period. Phase-2 (36.0 MW) is scheduled to start construction in late 2013, with the turbines starting to arrive on site by year-end. The grid connection and sub-station for the entire site were completed during Phase-1, which helps keep the full capacity on track for commissioning by the 2014 wind season.

   --       Basvanbagewadi Wind Farm (151.2 MW - Karnataka). 

Total export capacity at the Basvanbagewadi site was increased from 158 MW to 180 MW, to support 151.2 MW for the project and 30 MW for the Matrix and Mangalore projects (see below).

o Phase-1 (51.2 MW): the thirty-two GE 1.6 XLE turbines were commissioned in September, together with the 180 MW sub-station for the entire site;

o Phase-2 (50.0 MW): has begun construction using the Gamesa G97-2.0 turbines, which have started to arrive on site. Phase-2 remains on track for commissioning in early 2014;

o Phase-3 (50.0 MW): land acquisition is in progress and a construction schedule should be announced shortly.

   --       Matrix Wind Farm(15.0 MW - Karnataka). 

Located within the Basvanbagewadi site and using the same grid connection, Matrix will sell its output directly to a multi-national IT Park via a 10-year PPA. Commissioning is planned for November 2013.

   --       Mangalore Energy Wind Farm(15.0 MW - Karnataka). 

Following the successful Matrix Wind Farm captive model, a second 15 MW wind farm is being developed within the Basvanbagewadi site and also using the same grid connection. Commissioning is expected in December 2013 and the off-taker is a business park with multi-national clients.

   --       Balavenkatpuram Wind Farm (200 MW - Andhra Pradesh). 

o Phase-1 (51.2 MW) using the enhanced GE 1.6 XLE turbine is complete, connected to the grid and commissioned. It should shortly begin selling power, once final State certification is received;

o Phase-2 and Phase-3 (100 MW) will use the G97-2.0 wind turbine. Land acquisition for these two phases is complete, turbines are being delivered to site and initial construction has begun. Commissioning is planned for late 2013 and March 2014 respectively.

   --       Dikchu Hydropower(96.0 MW - Sikkim). 

Key components of the project are progressing well. Over 50% of the project's civil works is completed, including a substantial part of the powerhouse. The majority of the Alsthom turbines and the electro-magnetic components have been delivered to site, enabling the installation of key equipment to begin. The project experienced delays due to abnormal weather conditions earlier in the year, but remains on schedule to begin commissioning in late 2014, ready for 2015's generating season.

   --       Additional Hydropower(92.6 MW - Karnataka and Himachal Pradesh). 

Five smaller projects are under construction and remain on schedule for commissioning in 2014 and early 2015.

Outlook

The backdrop for renewable energy in India remains positive, as conventional power assets struggle to supply power to the grid, due to both fuel supply and off-take price issues. Greenko's wind and hydro portfolio in many States can now profitably supply power below the price of conventional generation. This, coupled with increased demand, means that Greenko is well positioned to provide financially attractive, sustainable long-term returns.

Greenko's results for the six months ending 30 September 2013 will be announced during the week beginning 2nd December 2013.

Anil Chalamalasetty, CEO of Greenko, said:

"Our portfolio approach continues to pay off, with good results in the first half. This year, we have added a further 102 MW of new wind capacity and are well on track to add a total of 250 MW of wind power, with projects already engaged for a further 250 MW the following year. Given that the project orders for our 2015 target of 1,000 MW are in place, with costs fixed in Rupees and an Indian energy market becoming increasingly favourable for hydro and wind power, we are very optimistic about the returns our portfolio will deliver."

-Ends-

For further information please visit www.greenkogroup.com or call:

 
 Greenko Group plc 
 Anil Chalamalasetty / Mahesh 
  Kolli 
 Vasudeva Rao Kaipa / Mark Thompson    +44 (0)20 7920 3150 
 
 Arden Partners plc 
 Richard Day / Adrian Trimmings        +44 (0)20 7614 5917 
 
 Tavistock Communications 
 Matt Ridsdale / Mike Bartlett         +44 (0)20 7920 3150 
 

About Greenko

Greenko is a mainstream participant in the growing Indian energy industry and a market leading owner and operator of clean energy projects in India utilising a de-risked portfolio of wind, run-of-river hydropower, natural gas and biomass assets. The Group is now focused on building new utility scale wind farms and hydropower projects across India. Greenko intends to increase the installed capacity it operates by winning concessions to develop and build new greenfield assets, as well as making selective acquisitions which enhance shareholder value.

Greenko's portfolio is carefully planned and managed to ensure it offers investors diversification and spreads its risk across a number of projects that utilise various well-proven environmental technologies. The Company's goal is to reach 1,000 MW of operational capacity in 2015 and approximately 2,000 MW in 2018.

With a core belief in sustainability both operationally and environmentally, Greenko endeavours to be a responsible business playing an important role in the community beyond its role in the power generation industry. The Company maintains a continuous involvement in localised projects and community programmes which centre on education, health and wellbeing, environmental stewardship and improving rural infrastructure.

Greenko Group plc was admitted to trading on the AIM market of the London Stock Exchange (LSE: GKO) in November 2007.

This information is provided by RNS

The company news service from the London Stock Exchange

END

TSTUKRNROAARRAA

Greenko (LSE:GKO)
Historical Stock Chart
From Nov 2024 to Dec 2024 Click Here for more Greenko Charts.
Greenko (LSE:GKO)
Historical Stock Chart
From Dec 2023 to Dec 2024 Click Here for more Greenko Charts.