Rio Tinto 2Q Iron-Ore Output Rose 3% on Year -- Commodity Comment
19 July 2023 - 11:18AM
Dow Jones News
Rio Tinto on Wednesday said it expects 2023 iron-ore shipments
to reach the top half of company guidance, but downgraded
production expectations for a number of other commodities,
including alumina and refined copper. Here are some remarks from
the miner's second-quarter report.
On Pilbara iron ore mines:
"We produced 81.3 million [metric tons] in the second quarter,
3% higher than the corresponding period of 2022. The ramp-up of
Gudai-Darri continued to plan, with the mine reaching nameplate
capacity on a sustained basis during the period. Challenges at the
Yandicoogina mine associated with materials handling and plant
reliability, highlighted in the first quarter, continued into the
period.
Shipments of 79.1 million tons were 1% lower than the second
quarter of 2022, and 4% lower than the prior quarter. This was
primarily due to planned major maintenance at the Dampier Port and
a train derailment on 17 June. The rail line was reopened on 21
June.
With ongoing operational improvements across the Pilbara system,
and uplift from implementation of the Safe Production System, full
year shipments are expected to be in the upper half of the original
320 to 335 million ton range. With higher production anticipated in
the second half, SP10 is expected to be a larger proportion of
shipments (first half 2023 = 10%)."
On alumina operations:
"Alumina production of 1.9 million tons was in line with the
second quarter of 2022 as improved operational stability at our
Yarwun and Vaudreuil refineries was offset by unplanned plant
downtime at Queensland Alumina Limited (QAL). As a result, our full
year alumina production has been reduced to 7.4 to 7.7 million tons
(previously 7.7 to 8.0 million tons), as QAL implements initiatives
to improve plant stability and production rates."
On bauxite output:
"Bauxite production of 13.5 million tons was 5% lower than the
second quarter of 2022 as our Weipa operations were impacted by the
higher-than-average first quarter rainfall, which continued to
reduce pit access and led to longer haul distances. Production was
further affected by equipment downtime at both Weipa and Gove. As a
result, our bauxite full year production is expected to be at the
lower end of our 54 to 57 million ton range, as we implement plans
to recover lost production at both operations through the remainder
of the year."
On refined copper production:
"Refined copper production was 56% lower than the second quarter
of 2022 as we commenced the largest rebuild of the smelter and
refinery in Kennecott's history in May 2023. The [circa] $300
million rebuild has incorporated approximately 300 engineering and
maintenance projects and we are on track to complete the full scope
of work.
While inspecting the integrity of the flash converting furnace,
we identified additional work necessitating a full rebuild, rather
than the planned partial rebuild. The full rebuild is expected to
further improve asset stability and process safety management,
however as a result the consolidated scope of work is now expected
to be completed in September 2023 (previously August 2023)."
As a result of the extension, refined copper production guidance
has been reduced to 160,000-190 tons, from an earlier estimate of
180,000-210,000 tons, and copper C1 unit cost guidance has been
increased to $1.80 to $2.00 a pound from $1.60 to $1.80 a pound
previously, the miner said.
On Escondida copper mine:
"Mined copper production was 6% lower than the second quarter of
2022 due to 10% lower concentrator throughput rates following
unplanned maintenance, and lower crusher and conveyor availability.
In addition, there was also a 16% decrease in copper recoverable
from ore stacked for leaching due to lower grades and volume of
stacked material."
On Oyu Tolgoi underground project:
"We continue to see strong performance from the underground
mine, with a total of 54 drawbells opened from Panel 0, including
18 drawbells during the quarter. To date we are yet to lose a
drawbell or draw point from the underground mine.
Shaft sinking rates improved during the quarter and at the end
of June, shafts 3 and 4 reached 627 meters and 740 meters below
ground level, respectively. Final depths required for shafts 3 and
4 are 1,148 and 1,149 meters below ground level, respectively. As
reported in our presentation materials for the Oyu Tolgoi site
tour, we now expect both shafts to be commissioned in the second
half of 2024 (previously first half of 2024) with shaft sinking
rates now meeting those required for completion."
Write to Rhiannon Hoyle at rhiannon.hoyle@wsj.com
(END) Dow Jones Newswires
July 18, 2023 21:03 ET (01:03 GMT)
Copyright (c) 2023 Dow Jones & Company, Inc.
Rio Tinto (ASX:RIO)
Historical Stock Chart
From Nov 2024 to Dec 2024
Rio Tinto (ASX:RIO)
Historical Stock Chart
From Dec 2023 to Dec 2024