Ascot Resources Ltd. (
TSX: AOT; OTCQX:
AOTVF) (“
Ascot” or the
“
Company”) today announces second quarter
production results and provides a commissioning update at the
Company’s Premier Gold Mine (“
Premier”), located
on Nisga’a Nation Treaty Lands in the prolific Golden Triangle of
northwestern British Columbia. Initial commissioning material was
introduced into the grinding circuit of the mill on March 31, 2024,
initial commissioning ore started to be processed on April 8, 2024,
and first gold was poured on April 20, 2024. During the remainder
of the quarter, the Company continued commissioning the mill, water
treatment plant, and established the secondary underground egress
at the Big Missouri deposit to commence production in its planned
stoping areas. Many of the commissioning challenges encountered in
the mill have been addressed, which is starting to demonstrate an
increasing frequency and quantity of gold pours.
SECOND QUARTER 2024
HIGHLIGHTS
- Established the second egress and exhaust vent raise at the Big
Missouri deposit on June 18th
- Project to date development of 3,861 metres, of which 89%
relates to Big Missouri and 11% relates to Premier Northern Lights
(“PNL”)
- Second quarter development of 1,764 metres, of which 1,381
metres related to Big Missouri and 383 metres relates to PNL.
Significant progress in the second half of the quarter has been
made at PNL where the development rates have increased to over 6
metres per day
- The operation is moving from mining lower-grade commissioning
ore from the development headings to mining of the planned
higher-grade stoping areas.
- During the quarter, Ascot processed 85,436 dry tonnes of mostly
development ore in the commissioning of the mill, containing an
estimated total of 5,713 ounces of gold
- Poured 839 ounces of gold and 1,288 ounces of silver, and an
estimated 3,178 ounces of gold-in-process remains in the mill
circuit
- Sold 735 ounces of gold to the offtaker at an average realized
price of US$2,357/oz (C$3,229/oz)
- Delivered 42 ounces of gold and 562 ounces of sliver per stream
and royalty arrangements
- The Company addressed a number of commissioning issues in the
mill related to the gravity circuit, elution circuit, and
thickening process
- Cash balance at June 30, 2024 of approximately C$12
million
Derek White, President & CEO, and Director
commented, "Ascot progressed through many important milestones in
the second quarter, including the start of processing commissioning
ore in the mill, the first gold pour from the gravity circuit, and
subsequent pours from the carbon-in-leach circuit as a part of the
commissioning process. While various challenges were encountered
within the mill startup, many corrective measures and changes have
been made, resulting in an upward trajectory in processing
reliability, throughput, and the ensuing gold pours. With stoping
activity in higher-grade areas having started at the Big Missouri
deposit, we anticipate a noticeable increase in gold pours in the
very near term.”
Figure 1 – Q2 2024 daily tonnes
milled
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/86b438bc-9c11-46fb-bd1e-b609b010f1e9
MiningThe pace of underground
mine development at the Big Missouri deposit increased in Q2 2024.
Total lateral development in the quarter was 1,764 metres,
comprising 525 metres in development ore and 1,239 metres in waste
at Big Missouri, and 383 metres of decline development at PNL. A
total of 47,158 wet tonnes of ore was mined in Q2 2024, and was
primarily sourced from development headings, with stoping activity
being commenced in late June after secondary egress was
established. The remaining mill feed came from previously mined
stockpiles. In various locations, waste development headings
encountered mineralized material approximately 20–30 metres or more
before reaching stope shapes, and as such that mined material was
stockpiled and fed to the mill as commissioning material.
As at June 30, 2024, there were approximately
11,614 tonnes of stockpiled ore to be processed in addition to the
live feed from Big Missouri underground stoping ore. Since the
secondary egress is in place, mining is now targeting planned
higher-grade stope blocks which have been averaging approximately
800 tonnes per day over the last weeks of June. This trend is
expected to continue in July.
At the Premier-Northern Light
(“PNL”) deposit near the mill, development rates
in the single-heading decline accelerated in the quarter, with the
mining contractor consistently achieving approximately 6 metres per
day for the month of June. Total development in Q2 2024 was 390
metres and 565 metres to go until the Company reaches the first
development ore which is anticipated in September of 2024 with
stope production commencing in October.
Mill CommissioningSince the
introduction of rock into the mill at the end of Q1 2024, there has
been a steady increase in crushing and grinding performance. To
June 30, 2024, the mill has processed 85,436 tonnes, achieving over
2,000 tonnes per day for 13 days in that period and reaching
nameplate capacity of approximately 2,500 tonnes per day on June
21, 2024. This has proved the mill can achieve nameplate milling
targets and has satisfied key vendor requirements.
On April 20, 2024, the first gold was poured
from gold recovered through the gravity circuit as a part of the
commissioning process. The first pour from gold recovered from the
CIL circuit was completed in late May 2024, with subsequent pours
having been completed in June and now continuing on a regular
basis. The first gold pour using both the gravity and CIL circuit
was completed on June 27, 2024, and that was the largest pour to
date.
During Q2 2024, the Company faced commissioning
challenges throughout the process plant but particularly in the
areas of the elution circuit boiler, carbon management, thickener
flocculation, and metallurgical sampling and estimation. In
addition, global supply chain challenges and vendor support have
been the source of some delays in implementing changes in the mill.
These challenges have mostly been surmounted with many process
changes made in June, and the Company is starting to see the
benefits of those changes in the amount of gold contained in each
pour.
The average grade processed to date is estimated
to be approximately 2 g/t gold. This is an estimate because during
commissioning, as is customary, there is an amount of gold being
built up in the processing circuit. This gold-in-circuit inventory
is currently estimated to be approximately 3,178 ounces.
Cash Balance and
LiquidityAscot’s cash balance at the end of Q1 2024 was
C$47 million. By the end of Q2 2024, this decreased to
approximately C$12 million. The decrease in cash is attributable to
the aforementioned mill commissioning challenges and delays in gold
pours. However, with the process changes being implemented, and
with the ability to mine stope ore at Big Missouri and feed higher
grade material to the mill, the gold pours are now being conducted
on a regular basis and generating more revenue. Ascot management is
evaluating the potential requirement for additional capital,
including an inventory prepay facility and/or a modest equity
financing in order to maintain a sufficient cash balance through
the commissioning process and meet the Company’s debt covenants. As
at June 30, 2024, the Company was in technical non-compliance with
certain covenants in its lending and stream arrangements. The
Company has obtained waivers for this non-compliance through the
end of July. The Company continues to work constructively with its
lenders and stream provider.
Qualified Person
John Kiernan, P.Eng., Chief Operating Officer of
the Company is the Company’s Qualified Person (QP) as defined by
National Instrument 43-101 and has reviewed and approved the
technical contents of this news release.
On behalf of the Board of Directors of
Ascot Resources Ltd.“Derek C. White”President & CEO,
Director
For further information
contact: David Stewart, P.Eng.
VP, Corporate Development & Shareholder
Communications dstewart@ascotgold.com 778-725-1060 ext. 1024
About Ascot Resources Ltd.
Ascot is a Canadian mining company focused on
commissioning its 100%-owned Premier Gold Mine, which poured first
gold in April 2024 and is located on Nisga’a Nation Treaty Lands,
in the prolific Golden Triangle of northwestern British Columbia.
Concurrent with commissioning Premier towards commercial production
anticipated in the second half of 2024, the Company continues to
explore its properties for additional high-grade gold
mineralization. Ascot’s corporate office is in Vancouver, and its
shares trade on the TSX under the ticker AOT and on the OTCQX under
the ticker AOTVF. Ascot is committed to the safe and responsible
operation of the Premier Gold Mine in collaboration with Nisga’a
Nation and the local communities of Stewart, BC and Hyder,
Alaska.
For more information about the Company, please
refer to the Company’s profile on SEDAR+ at www.sedarplus.ca or
visit the Company’s web site at www.ascotgold.com.
The TSX has not reviewed and does not accept
responsibility for the adequacy or accuracy of this release.
Cautionary Statement Regarding
Forward-Looking Information
All statements and other information contained
in this press release about anticipated future events may
constitute forward-looking information under Canadian securities
laws ("forward-looking statements").
Forward-looking statements are often, but not always, identified by
the use of words such as "seek", "anticipate", "believe", "plan",
"estimate", "expect", "targeted", "outlook", "on track" and
"intend" and statements that an event or result "may", "will",
"should", "could", “would” or "might" occur or be achieved and
other similar expressions. All statements, other than statements of
historical fact, included herein are forward-looking statements,
including statements in respect of the advancement and development
of the PGP and the timing related thereto, the completion of the
PGP mine, the Company’s ability to raise financing and be in
compliance with its debt and stream agreements, the production of
gold and management’s outlook for the remainder of 2024 and beyond.
These statements involve known and unknown risks, uncertainties and
other factors that may cause actual results or events to differ
materially from those anticipated in such forward-looking
statements, including the business of Ascot; risks related to
exploration and potential development of Ascot's projects; business
and economic conditions in the mining industry generally;
fluctuations in commodity prices and currency exchange rates;
uncertainties relating to interpretation of drill results and the
geology, continuity and grade of mineral deposits; the need for
cooperation of government agencies and indigenous groups in the
exploration and development of Ascot’s properties and the issuance
of required permits; the need to obtain additional financing to
develop properties and uncertainty as to the availability and terms
of future financing; the possibility of delay in exploration or
development programs and uncertainty of meeting anticipated program
milestones; uncertainty as to timely availability of permits and
other governmental approvals; and other risk factors as detailed
from time to time in Ascot's filings with Canadian securities
regulators, available on Ascot's profile on SEDAR+ at
www.sedarplus.ca including the Annual Information Form of the
Company dated March 25, 2024 in the section entitled "Risk
Factors". Forward-looking statements are based on assumptions made
with regard to: the estimated costs associated with construction of
the project; the ability to maintain throughput and production
levels at the PGP mill; the tax rate applicable to the Company;
future commodity prices; the grade of mineral resources and mineral
reserves; the ability of the Company to convert inferred mineral
resources to other categories; the ability of the Company to reduce
mining dilution; the ability to reduce capital costs; and
exploration plans. Forward-looking statements are based on
estimates and opinions of management at the date the statements are
made. Although Ascot believes that the expectations reflected in
such forward-looking statements and/or information are reasonable,
undue reliance should not be placed on forward-looking statements
since Ascot can give no assurance that such expectations will prove
to be correct. Ascot does not undertake any obligation to update
forward-looking statements, other than as required by applicable
laws. The forward-looking information contained in this news
release is expressly qualified by this cautionary statement.
Ascot Resources (TSX:AOT)
Historical Stock Chart
From Oct 2024 to Nov 2024
Ascot Resources (TSX:AOT)
Historical Stock Chart
From Nov 2023 to Nov 2024