VANCOUVER, BC, Oct. 15,
2024 /CNW/ - FPX Nickel Corp. (TSXV: FPX) (OTCQB:
FPOCF) ("FPX" or the "Company") is pleased to
announce that it has successfully completed pilot-scale
hydrometallurgy refinery testwork and produced battery-grade nickel
sulphate from its Baptiste Nickel Project ("Baptiste" or the
"Project"). Following on the Company's successful 2023
bench-scale hydrometallurgy refining testwork program, the 2024
pilot plant represents a significant step forward in demonstrating
the technical maturity of refining Baptiste's awaruite concentrate.
This milestone marks completion of the campaign funded in
part by a grant from Natural Resources Canada ("NRCan")
under the Government of Canada's
Critical Minerals Research, Development and Demonstration
("CMRDD") program, which is advancing the commercial
readiness of processing technologies to support the development of
Canada's EV battery material
supply chain.
Highlights
- Successful Pilot-Scale Testwork: Continuous pilot-scale
testing of all leaching unit operations confirmed the refinery
flowsheet and generated the expected low-impurity leach solution
for downstream purification and crystallization testwork
- Flowsheet Optimization: Testwork has led to flowsheet
improvement through the removal of unit operations in the leaching
area that proved redundant during continuous, steady-state
piloting
- Production of Battery-Grade Nickel Sulphate: Bench-scale
testing of solution purification and crystallization unit
operations further demonstrate FPX Nickel's ability to produce
battery-grade nickel sulphate crystals from Baptiste's awaruite
concentrate
"The results of our hydrometallurgy refinery pilot plant
testwork confirm the technical advantages of awaruite nickel
mineralization to produce battery-grade nickel sulphate, further
demonstrating the opportunity to develop a more streamlined nickel
supply chain entirely in Canada,"
commented Andrew Osterloh, FPX
Nickel's Senior Vice-President, Projects & Operations.
"Baptiste would represent an almost 50% increase to
Canada's current annual nickel
production, all without adding to or displacing any of Canada's nickel smelting or complex refinery
capacity, thereby pioneering a uniquely low-cost, low-carbon link
between mining and EV battery production. The results from
our pilot plant testwork are currently being incorporated into our
Awaruite Refinery Scoping Study, which will contain a detailed
evaluation of capital, operating costs and the overall economics of
the awaruite refinery; the Study remains on track for
completion in the first quarter of 2025."
Background
As reported in the Company's news release dated April 30, 2024, FPX operated a mineral processing
pilot plant earlier this year and successfully generated awaruite
concentrate to feed a downstream hydrometallurgical refining pilot
plant (the "2024 Hydromet Program"). FPX re-engaged
Sherritt Technologies Ltd. to conduct the 2024 Hydromet Program,
building on Sherritt's successful completion of the previous
bench-scale hydrometallurgical testwork in 2023 (the "2023
Hydromet Program", described in the Company's May 17, 2023 news release).
Building on the 2023 Hydromet Program, the 2024 Hydromet Program
aimed to further demonstrate the viability of FPX's refinery
flowsheet under pilot-scale and continuous operating
conditions. Additionally, the 2024 Hydromet Program also
aimed to validate the new ammonia-based purification flowsheet, as
discussed in the Company's news release dated September 16, 2024.
Hydrometallurgical Refinery Pilot Plant
The 2024 Hydromet Program was conducted in two phases.
Phase 1 consisted of continuous, pilot-scale processing
of all unit operations in the leaching area as outlined in Figure
2. Phase 2 consisted of batch, bench-scale processing of
all unit operations in the purification and crystallization area.
A portion of leach solution produced during Phase 1 has been
reserved for future continuous, pilot-scale processing of the
purification and crystallization area, ensuring the final refinery
strategy is supported by purification and crystallization
requirements defined in collaboration with FPX Nickel's downstream
partners.
Leaching Area
Continuous, pilot-scale leaching ran for five days and was fed
with the high-grade (60% Ni) awaruite concentrate produced during
the earlier mineral processing pilot plant. The flowsheet
configuration and operating conditions were the same as the 2023
Hydromet Program, with pressure leaching conducted at a moderate
temperature (150°C) and pressure (750 kPag). The key
performance metrics established at the start of the pilot plant
campaign were to obtain high overall nickel and cobalt leach
extractions while generating a final leach solution with high
nickel and low impurity concentrations.
These key performance metrics are summarized in Table 1, which
also presents the basis of the previous economic study (see the
Company's news release dated September 6,
2023). In the pressure leach, excellent nickel and
cobalt overall leach extractions were achieved at 99.3% and 97.9%,
respectively. These high extractions include the unoptimized
start-up period, highlighting the robustness of the leach
system.
In the atmospheric leach (which utilizes awaruite to neutralize
and purify the pressure leach solution), excellent impurity removal
was achieved, including the near-complete removal of iron,
aluminum, chromium and copper. The final leach solution
contained greater than 100 g/L nickel, which is very high by
industry standards and will reduce the capital and operating costs
for downstream purification and crystallization unit operations.
The impurity elements of zinc, manganese, and calcium are all
low due to the inherent low concentration of these impurities in
Baptiste's awaruite concentrate.
Table 1 – Leaching area key performance metrics achieved
during piloting
|
Pilot
Plant
Results
|
Previous
Study
Basis
|
Overall Leach
Extractions
|
Nickel (%)
|
99.3
|
99.3
|
Cobalt (%)
|
97.9
|
99.5
|
Final Leach Solution
Composition
|
pH
|
5.5
|
>4.5
|
Nickel (g/L)
|
104
|
95
|
Cobalt (g/L)
|
2.1
|
1.5
|
Magnesium
(g/L)
|
1.6
|
1.5
|
Iron (g/L)
|
<0.003
|
<0.003
|
Aluminium
(g/L)
|
<0.003
|
<0.003
|
Chromium
(g/L)
|
<0.003
|
<0.003
|
Copper (g/L)
|
<0.003
|
<0.05
|
Zinc (g/L)
|
0.01
|
<0.05
|
Manganese (g/L)
|
0.01
|
<0.05
|
Calcium
(g/L)
|
0.01
|
<0.05
|
In addition to the core leaching operations, the leaching area
also includes two smaller circuits to manage build-up of certain
trace elements, including copper removal and aluminum/chromium
removal. The copper removal circuit, which removes copper by
a cementation process, was successfully operated during piloting.
Aluminum and chromium were both shown to deport with pressure leach
residue, supporting the deletion of this slipstream removal
circuit, thereby simplifying the overall leach flowsheet.
Additionally, solid-liquid separation characterization testing
was completed on both pressure leach and atmospheric leach
residues, with reasonable settling and filtration rates observed
for both. These results will inform dewatering equipment
sizing and specifications in the ongoing Awaruite Refinery Scoping
Study.
Purification and Crystallization
A portion of the bulk solution generated from the leaching area
pilot was processed in bench-scale batch testing through cobalt
solvent extraction, nickel solvent extraction, and nickel sulphate
crystallization. This purification scheme is simpler relative
to that required to process other nickel intermediates such as MHP
and MSP, with this simplicity made possible by the low impurities
contained in, and the neutralization properties of, the awaruite
concentrate.
In order to validate the new purification flowsheet developed
during Refinery Value Engineering studies (see the Company's news
release dated September 16, 2024),
solvent extraction operations utilized ammonia as the neutralizing
reagent (rather than caustic, which was used in the 2023 Hydromet
Program). Along with lower operating costs, the change to an
ammonia-based flowsheet allows for the production of an ammonium
sulphate byproduct, a valuable fertilizer product, instead of the
previous sodium sulphate waste product. The new ammonia-based
purification unit operations achieved similar successful
performance and results as those achieved during the 2023 Hydromet
Program, with the produced crystals (see Figure 1 and Table 2)
continuing to meet the strict target specifications for battery
applications.
Table 2 – Baptiste Nickel Sulphate Crystal Quality vs. Target
Specification
Element
|
Units
|
Nickel Sulphate
Crystals
|
Baptiste
Testwork
|
Target
Specification1
|
Nickel
|
wt%
|
>22
|
>22
|
Aluminum
|
ppm
|
<1
|
<5
|
Arsenic
|
ppm
|
<1
|
<2
|
Calcium
|
ppm
|
<1
|
<5
|
Cadmium
|
ppm
|
<1
|
<1
|
Cobalt
|
ppm
|
1
|
<50
|
Chromium
|
ppm
|
<1
|
<3
|
Copper
|
ppm
|
<1
|
<3
|
Iron
|
ppm
|
<1
|
<3
|
Potassium
|
ppm
|
<1
|
<10
|
Magnesium
|
ppm
|
3
|
<5
|
Manganese
|
ppm
|
<1
|
<5
|
Sodium
|
ppm
|
<10
|
<20
|
Lead
|
ppm
|
<1
|
<2
|
Silicon
|
ppm
|
<5
|
<10
|
Zinc
|
ppm
|
3
|
<5
|
Note 1: Based on review
of industrially available products and battery producers'
requirements
|
Path Forward
With the completion of the hydrometallurgical testwork reported
herein, the Company has completed all testing associated with the
CMRDD funding provided by NRCan. Refinery testing results are
being incorporated into the ongoing Awaruite Refinery Scoping
Study, the results of which will be available in the first quarter
of 2025.
Qualified Person
The metallurgical information in this news release has been
prepared in accordance with Canadian regulatory requirements set
out in National Instrument 43-101: Standards of Disclosures for
Minerals Projects of the Canadian Securities Administrators ("NI
43-101"). Testwork was supervised, reviewed, and verified by
Kyle D. Marte, P.Eng., FPX Nickel's
Principal Metallurgist and a "Qualified Person" as defined by NI
43-101.
About the Baptiste Nickel Project
The Company's Baptiste Nickel Project represents a large-scale
greenfield discovery of nickel mineralization in the form of a
sulphur-free, nickel-iron mineral called awaruite
(Ni3Fe) hosted in an ultramafic/ophiolite complex.
The Baptiste mineral claims cover an area of 408 km2,
west of Middle River and north of
Trembleur Lake, in central British Columbia. In addition to
the Baptiste Deposit itself, awaruite mineralization has been
confirmed through drilling at several target areas within the same
claims package, most notably at the Van Target which is located 6
km to the north of the Baptiste Deposit. Since 2010,
approximately US $30 million has been
spent on the exploration and development of Baptiste.
The Baptiste deposit is located within the territories, keyohs,
and consultative boundaries of the Tl'azt'en Nation, Binche
Whut'enne, Yekooche First Nation, and Takla
Nation.
About FPX Nickel Corp.
FPX Nickel Corp. is focused on the exploration and development
of the Decar Nickel District, located in central British Columbia, and other occurrences of the
same unique style of naturally occurring nickel-iron alloy
mineralization known as awaruite. For more information, please view
the Company's website at https://fpxnickel.com/ or contact
Martin Turenne, President and CEO,
at (604) 681-8600 or ceo@fpxnickel.com.
On behalf of FPX Nickel Corp.
"Martin Turenne"
Martin Turenne, President, CEO and
Director
Forward-Looking Statements
Certain of the statements made and information contained
herein is considered "forward-looking information" within the
meaning of applicable Canadian securities laws. These statements
address future events and conditions and so involve inherent risks
and uncertainties, as disclosed in the Company's periodic filings
with Canadian securities regulators. Actual results could differ
from those currently projected. The Company does not assume the
obligation to update any forward-looking statement.
Neither the TSX Venture Exchange nor its Regulation Services
Provider accepts responsibility for the adequacy or accuracy of
this release.
SOURCE FPX Nickel Corp.