Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument" or
the "Company") is pleased to announce the progress on flotation
plant construction at the Selinsing Gold Mine in Malaysia to
produce saleable sulphide gold concentrates. The flotation plant
construction includes: project management, project validation,
flotation design and engineering, procurement, construction and
commissioning.
Charlie Northfield, General Manager and the
Project Sponsor at the Selinsing Gold Mine, commented: “I am
thrilled to report that we are on schedule for construction
completion in June 2022. To mitigate the risk of delays that might
be caused by the Covid 19 pandemic from time to time, we are making
our best efforts to advance deliverables ahead of the schedule. Our
ability to move quickly is a testament to the capacity and
experience of the on-site team. We will provide further updates on
the flotation plant construction process in the weeks to come.”
Project Management
The project management team is led by the
oversight board chaired by Cathy Zhai, President and CEO,
comprising Project Sponsor, Project Manager, Project Controller and
the Plant Manager as the end user. The procurement and engineering
team on site are Selinsing employees. The majority of key project
personnel participated in the existing Selinsing gold plant
construction work back in 2008 to 2010. Six new employees will be
recruited at different times in the construction and four personnel
seconded from the existing Selinsing workforce.
Detailed Engineering Design
Following completion of independent flotation
testwork and amendment of conceptual design of the flotation plant
by Orway Mineral Consultants (“OMC”) (refer to July 6th 2021 news
release), the contract for detailed engineering design was awarded
to Mincore Pty Ltd. (“Mincore”), an Australia based engineering
company.
The scope of work undertaken by Mincore
included: the development of the 3D model of the flotation
processing plant, preparation of equipment specifications and data
sheets, and development of the control system for the new process
equipment. Plant design aims to maximize gravity flow and to
provide plant access for maintenance while allowing the current
gravity / CIL plant operation to continue without interruption. The
plant layout design allows for the future addition of the proposed
BIOX® circuit and ancillary works.
Up to September 30th 2021 Mincore has achieved
80% completion of the design work. HAZOP design reviews have been
carried out for the new process facilities to identify and mitigate
any operational safety issues. Civil and structural drawings are
scheduled for completion on October 31st 2021; mechanical and
piping drawings will be issued for construction by November 30th
2021.
Lim Teck Chong, Flotation Plant Project Manager,
commented: “The successful flotation testwork gave us the green
light to proceed with all aspects of the development of the
project. The detailed engineering design is approaching completion
and the pilot plant is expected to be completed this month.
Procurement, earthworks, and recruitment have all progressed as we
ramp up and prepare for civil foundation work to begin.”
Figure 1 is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/b66d6a8e-baeb-42e5-ac8a-2ad921b4c613
Procurement
Procurement of long lead equipment items has
been completed and contracts have been awarded for the supply of
flotation cells, concentrate and water recovery thickeners, and the
concentrate filter press. Technical and financial appraisals have
been completed and contracts are being prepared for the air
blowers, compressor, slurry pumps and 11kV/415V transformer.
Procurement is continuing for the motor control centre, agitators,
reagent pumps and plate work for conditioning and reagent
tanks.
The flotation pilot plant has been delivered to
site and is currently being set up at the research and development
laboratory. The pilot plant features a ball mill and classifier,
rougher/scavenger flotation cells and three stages of cleaner
flotation to replicate the flowsheet of the full scale flotation
plant. The pilot plant will be used for operator training, reagent
trials, and for the preparation of concentrate samples for
potential customers. The pilot plant is expected to be fully
operational before the end of October 2021.
Risk control over the long lead items is focused
on periodical inspection and shipping scheduling, which faces
global challenges during the pandemic period.
Construction
Flotation construction includes: earthworks,
civil engineering, structural engineering, mechanical and
electrical installation and other associated plant upgrades.
Contractor Engagement: Suitably experienced
Malaysian contractors have been shortlisted for the construction
work according to discipline comprising: civil and structural,
mechanical and piping, and electrical and instrumentation. Most of
these contractors have worked on previous construction phases of
the Selinsing operation. The contract has been awarded to reroute
the power cables to the primary and secondary ball mills outside of
the new flotation plant footprint to avoid any interference during
construction work.
Civil Foundation Work: 75% of the earthworks
have been completed for the plant foundations, and final
excavations will be conducted once civil drawings have been issued
for construction. Civil foundation work is expected to commence in
early November, starting with the construction of the retaining
wall extension, and followed by civil works in the flotation area,
concentrate and water recovery thickeners and the filter press
building. At the same time the foundations will be constructed for
the new warehouse, reagents mixing and air services buildings.
Transition to Flotation
The production of flotation concentrate is
expected to commence in July 2022 as soon as all of the flotation
cells, concentrate thickener and filter press have been
commissioned. In the current production schedule the CIL plant will
continue operation until commissioning of the flotation plant
commences. We will keep the production going as long as possible to
generate cash flow primarily from Selinsing, Buffalo Reef pits and
the Peranggih Prospect, provided that readers shall understand that
there might be an interruption to production due to the Covid
pandemic, and there might be volatility of production in transition
to the new life of mine from the existing remaining life of
mine.
During the period from late August to the
beginning of October, while the CIL plant has continued operation
throughout the time, the elution heat exchanger however has been
offline after 10 years’ of service, and the spare was unexpectedly
found to have failed. Gold pours were put on hold until October
when the unit was re-built and back in service. A suitable
replacement heat exchanger has been located in Kuala Lumpur and an
order has been placed to secure this unit and delivery is awaited.
The Company keeps its repair and maintenance program going to
ensure sustained production as planned.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE:D7Q1)
is an established Canadian gold producer that owns and operates the
Selinsing Gold Mine in Malaysia. Its experienced management team is
committed to growth and is also advancing the Murchison Gold
Projects comprising Burnakura, Gabanintha and Tuckanarra (20%
interest) in the Murchison area of Western Australia. The Company
employs approximately 200 people in both regions and is committed
to the highest standards of environmental management, social
responsibility, and health and safety for its employees and
neighboring communities.
Cathy Zhai, President and CEOMonument Mining
LimitedSuite 1580 -1100 Melville StreetVancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web
site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T:
+1-604-638-1661 x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release."
Forward-Looking Statement
This news release includes statements containing
forward-looking information about Monument, its business and future
plans ("forward-looking statements"). Forward-looking statements
are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the
Company's plans with respect to its mineral projects and the timing
and results of proposed programs and events referred to in this
news release. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as
"plans", "expects" or "does not expect", "is expected", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates" or
"does not anticipate", or "believes", or variations of such words
and phrases or state that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved". The forward-looking statements in this news release are
subject to various risks, uncertainties and other factors that
could cause actual results or achievements to differ materially
from those expressed or implied by the forward-looking statements.
These risks and certain other factors include, without limitation:
risks related to general business, economic, competitive,
geopolitical and social uncertainties; uncertainties regarding the
results of current exploration activities; uncertainties in the
progress and timing of development activities; foreign operations
risks; other risks inherent in the mining industry and other risks
described in the management discussion and analysis of the Company
and the technical reports on the Company's projects, all of which
are available under the profile of the Company on SEDAR at
www.sedar.com. Material factors and assumptions used to develop
forward-looking statements in this news release include:
expectations regarding the estimated cash cost per ounce of gold
production and the estimated cash flows which may be generated from
the operations, general economic factors and other factors that may
be beyond the control of Monument; assumptions and expectations
regarding the results of exploration on the Company's projects;
assumptions regarding the future price of gold of other minerals;
the timing and amount of estimated future production; the expected
timing and results of development and exploration activities; costs
of future activities; capital and operating expenditures; success
of exploration activities; mining or processing issues; exchange
rates; and all of the factors and assumptions described in the
management discussion and analysis of the Company and the technical
reports on the Company's projects, all of which are available under
the profile of the Company on SEDAR at www.sedar.com. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking statements, there may be other factors that cause
results not to be as anticipated, estimated or intended. There can
be no assurance that such statements will prove to be accurate, as
actual results and future events could differ materially from those
anticipated in such statements. Accordingly, readers should not
place undue reliance on forward-looking statements. The Company
does not undertake to update any forward-looking statements, except
in accordance with applicable securities laws.
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Nov 2024 to Dec 2024
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Dec 2023 to Dec 2024