B2Gold Corp. (TSX: BTO, NYSE AMERICAN: BTG, NSX: B2G) (“B2Gold” or
the “Company”) is pleased to provide a construction update on the
Goose Project, located in the 100% owned Back River Gold District
in Nunavut, Canada. B2Gold acquired the Back River Gold District as
part of the acquisition of Sabina Gold & Silver (“Sabina”) in
April 2023.
Goose Project Construction Update
Highlights
- Goose Project remains on
schedule for mill completion in Q1 2025: The 2023 winter
ice road season was completed, with B2Gold receiving all critical
materials necessary to maintain the schedule to complete
construction of the mill in the first quarter of 2025. Currently,
camp construction is underway, generators are being installed, and
construction workshops are being erected.
- Total initial capital
expenditure estimate of C$800 million, in line with B2Gold
expectations since the Sabina acquisition announcement, reflects
scope changes to further optimize the Goose Project:
B2Gold has updated the construction budget to de-risk the project
and construct a reliable and low operating cost mine. In addition,
the Company has made the decision to accelerate underground mining
development to increase annual gold production over the first five
years of the mine plan, including the mining of the Umwelt crown
pillar (discussed below). The cost to accelerate underground mining
is estimated at an additional C$90 million.
- Accelerated underground
mining development to increase average gold production in the first
five years to over 300,000 ounces per year: Mining is
underway in the Echo open pit, which will be mined out prior to
process commissioning to provide tailings storage capacity.
Underground mining has exceeded 1,500 meters of horizontal
development and the initial ventilation raise will reach the
surface shortly.
- Underground mining is now
scheduled to mine and backfill the full Umwelt crown pillar earlier
in the mine life, which is expected to contribute over 150,000
ounces of gold production to the life of mine plan:
Geotechnical and mine design and engineering is underway with the
goal of mining and backfilling the crown pillar prior to completion
of the Umwelt open pit using long-hole stoping methods to increase
production rates and reduce operating costs. The crown pillar zone
contains over 150,000 ounces of gold, which will be mined and
processed earlier in the mine life than prior mine plans.
- First winter ice road
successfully brought all required materials to complete building
envelopes in 2023: Concrete, steel, and consumables
required for construction were successfully transported to the
Goose Project site on the winter ice road and are staged at the
construction site. Construction equipment including cranes,
generators, welders, lifts, and tooling are in operation and being
used for camp and workshop construction. Completion of the 2023
winter ice road successfully de-risked the development of future
winter ice roads.
- Site construction is
ongoing, led by Kieran Loughran, who has successfully managed five
construction projects for B2Gold and its predecessor company Bema
Gold: Mr. Loughran and the B2Gold in-house construction
team have successfully built the following projects on-time and
on-budget over the past three decades: the Julietta and Kupol mines
in Russia, the La Libertad mine in Nicaragua, the Otjikoto mine in
Namibia, and the Fekola mine in Mali. The B2Gold in-house
construction team is complemented by key personnel previously
working on the project with Sabina.
Goose Project Initial Capital
Build-Up
Category |
|
ApproximateAmount |
B2Gold Commentary |
Initial Capital Expenditure (“Capex”) Estimate –
March 2021 Feasibility Study |
C$M |
$610 |
- Initial capex
estimate from March 2021 NI 43-101 Feasibility Study for the Goose
Project
|
Inflationary Impacts through Sabina Acquisition Closing (April
2023) |
C$M |
$130 |
- Total inflation of
~20%, in line with industry inflationary pressures from 2021 to
2023
|
Last Sabina Internal Capex Estimate – April
2023 |
C$M |
$740 |
|
B2Gold In-House Construction and Purchasing Teams |
C$M |
($70) |
- Savings due to the
use of B2Gold’s in-house construction and purchasing teams
|
B2Gold Design Changes and Consumables Pricing |
C$M |
$130 |
- Additional
equipment, steel, and tankage to ensure reliable and low cost
operation
- Inflation of fuel
and consumables to market prices
|
Updated Initial Capex Estimate |
C$M |
$800 |
- Updated
initial capex to execute a de-risked Goose Project based on the
March 2021 Feasibility Study
|
Accelerated Underground Mining |
C$M |
$90 |
- Underground mining
accelerated to increase gold production over first five years of
the mine life
- Accelerates mining
of the Umwelt crown pillar, which contributes over 150,000 ounces
of gold production to the life of mine plan
|
Total Project Cost Estimate |
C$M |
$890 |
- Total
project costs required to execute an improved Goose
Project
|
Less: Project Costs Incurred Through April 2023 |
C$M |
($340) |
- Project costs
incurred by Sabina through April 2023
|
Remaining Project Costs to be Incurred by B2Gold |
C$M |
$550 |
- Project costs to be
incurred by B2Gold through Q1 2025
|
In addition, B2Gold will undertake a build up of
working capital over the next 24 months in order to materially
de-risk the execution of the production ramp-up phase. Areas of
focus for working capital include:
- Accelerated purchase and additional
storage of diesel fuel to manage the requirements of operations in
2025;
- Critical inventory of consumables
and spares for mining and processing to avoid the requirement for
air transport; and
- Development of open pit and
underground ore stockpiles to provide a consistent and
uninterrupted feed to the process plant.
B2Gold Goose Project Capital
Changes
Utilization of B2Gold In-House Construction and
Purchasing Team
Since closing of the acquisition of Sabina in
April 2023, B2Gold has worked to integrate its in-house
construction team with the Sabina team, as well as rescope the
external contractors working on the Goose Project. Through these
integration efforts and based on prior experience at B2Gold’s
current operations, the Company estimates that moving to an
owner-operated construction model versus a fixed priced EPC
contract for the construction of the process plant will save money
and result in a mill with higher availability and lower sustaining
capital requirements. Using an owner-operated team also allows for
flexibility in construction and the ability to refocus construction
activities as needed.
In addition, the B2Gold in-house purchasing team
has identified significant savings by purchasing certain mobile
equipment versus the ‘lease to own’ purchase model utilized by
Sabina, and through lower negotiated pricing for certain reagents
and consumables required for project construction and
commissioning.
B2Gold Design Changes and Consumables
Pricing
Through the due diligence period of the
acquisition of Sabina and now managing the Goose Project, the
B2Gold team has identified various items that will be added to the
original Sabina scope in order to further de-risk the construction
phase and maximize the long-term value of the asset. These items
include, among others:
- Emulsion explosives plant and
mining support fleet;
- Additional power generation
capacity and expanded site power distribution;
- Additional shipping redundancy
costs to further de-risk the timing of mill completion in Q1
2025;
- Secondary steel including
platforms, grating, and handrails to meet project and safety
requirements;
- Information Technology and
Enterprise Resource Planning improvements;
- Improved on-site assay lab;
and
- Additional fuel tanks at the Marine
Laydown Area and at the Goose Project to provide extended on-site
operating reserves (and to support potential project
expansions).
In addition, the Company has used current market
pricing for costing of various consumables utilized during the
construction phase, mainly related to fuel and diesel.
Goose Project Update Life of Mine
Plan
The B2Gold technical team continues to analyze
ways to optimize the Goose Project life of mine plan. Areas of
optimization currently being studied include:
- Mining of the Umwelt crown
pillar
- The crown pillar between the Umwelt
open pit and underground mining areas contains over 150,000 ounces
of gold and was only partially included in prior production
schedules.
- Geotechnical and mine design and
engineering is underway with the goal of mining and backfilling the
crown pillar prior to completion of the Umwelt open pit.
- Underground mining
method
- Development mining is effective in
complex high grade deposits, but with relatively high mining
costs.
- The B2Gold engineering team has
determined that most of the Umwelt underground mine can be mined
effectively with long-hole stoping, which is expected to reduce
costs and increase ore production rates.
- Renewable power
generation
- The Sabina team identified the
potential for wind power generation during prior ownership, and
studies are in progress to identify the best solution and to
quantify the potential operational and cost impact to the Goose
Project.
B2Gold anticipates the completion of an updated
Goose Project life of mine plan in the second half of 2023.
About B2Gold
B2Gold is a low-cost international senior gold
producer headquartered in Vancouver, Canada. Founded in 2007,
today, B2Gold has operating gold mines in Mali, Namibia and the
Philippines and numerous exploration and development projects in
various countries including Canada, Mali, Colombia, Finland and
Uzbekistan. B2Gold forecasts total consolidated gold production of
between 1,000,000 and 1,080,000 ounces in 2023.
Qualified Persons
Bill Lytle, Senior Vice President and Chief
Operating Officer, a qualified person under NI 43-101, has approved
the scientific and technical information related to operations
matters contained in this news release.
ON BEHALF OF B2GOLD CORP.
“Clive T.
Johnson” President and Chief Executive
Officer
The Toronto Stock Exchange and NYSE American LLC
neither approve nor disapprove the information contained in this
news release.
Production guidance presented in this news
release reflect total production at the mines B2Gold operates on a
100% project basis. Please see our Annual Information Form dated
March 16, 2023 for a discussion of our ownership interest in the
mines B2Gold operates.
This news release includes certain
“forward-looking information” and “forward-looking statements”
(collectively “forward-looking statement”) within the meaning of
applicable Canadian and United States securities legislation,
including: projections; outlook; guidance; forecasts; estimates;
statements regarding future or estimated financial and operational
performance, gold production and sales, revenues and cash flows,
and capital costs (sustaining and non-sustaining) and operating
costs, and including, without limitation: total consolidated gold
production of between 1,000,000 and 1,080,000 ounces in 2023; the
completion of mill construction at the Goose Project being
completed in the first quarter of 2023; the capital cost estimate
for the Goose Project being approximately C$890 million; the
underground mining now scheduled to include 150,000 ounces from the
Umwelt crown pillar; the Umwelt underground mine being mined with
long-hole stoping, which could reduce costs and increase ore
production rates; the identification of various items that will be
added to the original Sabina scope in order to de-risk the
construction phase and maximize the long-term value of the asset.
All statements in this news release that address events or
developments that we expect to occur in the future are
forward-looking statements. Forward-looking statements are
statements that are not historical facts and are generally,
although not always, identified by words such as "expect", "plan",
"anticipate", "project", "target", "potential", "schedule",
"forecast", "budget", "estimate", "intend" or "believe" and similar
expressions or their negative connotations, or that events or
conditions "will", "would", "may", "could", "should" or "might"
occur. All such forward-looking statements are based on the
opinions and estimates of management as of the date such statements
are made.
Forward-looking statements necessarily involve
assumptions, risks and uncertainties, certain of which are beyond
B2Gold's control, including risks associated with or related to:
the volatility of metal prices and B2Gold's common shares; changes
in tax laws; the dangers inherent in exploration, development and
mining activities; the uncertainty of reserve and resource
estimates; not achieving production, cost or other estimates;
actual production, development plans and costs differing materially
from the estimates in B2Gold's feasibility and other studies; the
ability to obtain and maintain any necessary permits, consents or
authorizations required for mining activities; environmental
regulations or hazards and compliance with complex regulations
associated with mining activities; climate change and climate
change regulations; the ability to replace mineral reserves and
identify acquisition opportunities; the unknown liabilities of
companies acquired by B2Gold; the ability to successfully integrate
new acquisitions; fluctuations in exchange rates; the availability
of financing; financing and debt activities, including potential
restrictions imposed on B2Gold's operations as a result thereof and
the ability to generate sufficient cash flows; operations in
foreign and developing countries and the compliance with foreign
laws, including those associated with operations in Mali, Namibia,
the Philippines and Colombia and including risks related to changes
in foreign laws and changing policies related to mining and local
ownership requirements or resource nationalization generally,
including in response to the COVID-19 outbreak; remote operations
and the availability of adequate infrastructure; fluctuations in
price and availability of energy and other inputs necessary for
mining operations; shortages or cost increases in necessary
equipment, supplies and labour; regulatory, political and country
risks, including local instability or acts of terrorism and the
effects thereof; the reliance upon contractors, third parties and
joint venture partners; the lack of sole decision-making authority
related to Filminera Resources Corporation, which owns the Masbate
Project; challenges to title or surface rights; the dependence on
key personnel and the ability to attract and retain skilled
personnel; the risk of an uninsurable or uninsured loss; adverse
climate and weather conditions; litigation risk; competition with
other mining companies; community support for B2Gold's operations,
including risks related to strikes and the halting of such
operations from time to time; conflicts with small scale miners;
failures of information systems or information security threats;
the ability to maintain adequate internal controls over financial
reporting as required by law, including Section 404 of the
Sarbanes-Oxley Act; compliance with anti-corruption laws, and
sanctions or other similar measures; social media and B2Gold's
reputation; risks affecting Calibre having an impact on the value
of the Company's investment in Calibre, and potential dilution of
our equity interest in Calibre; as well as other factors identified
and as described in more detail under the heading "Risk Factors" in
B2Gold's most recent Annual Information Form, B2Gold's current Form
40-F Annual Report and B2Gold's other filings with Canadian
securities regulators and the U.S. Securities and Exchange
Commission (the "SEC"), which may be viewed at www.sedar.com and
www.sec.gov, respectively (the "Websites"). The list is not
exhaustive of the factors that may affect B2Gold's forward-looking
statements
B2Gold's forward-looking statements are based on
the applicable assumptions and factors management considers
reasonable as of the date hereof, based on the information
available to management at such time. These assumptions and factors
include, but are not limited to, assumptions and factors related to
B2Gold's ability to carry on current and future operations,
including: the timing, extent, duration and economic viability of
such operations, including any mineral resources or reserves
identified thereby; the accuracy and reliability of estimates,
projections, forecasts, studies and assessments; B2Gold's ability
to meet or achieve estimates, projections and forecasts; the
availability and cost of inputs; the price and market for outputs,
including gold; foreign exchange rates; taxation levels; the timely
receipt of necessary approvals or permits; the ability to meet
current and future obligations; the ability to obtain timely
financing on reasonable terms when required; the current and future
social, economic and political conditions; and other assumptions
and factors generally associated with the mining industry.
B2Gold's forward-looking statements are based on
the opinions and estimates of management and reflect their current
expectations regarding future events and operating performance and
speak only as of the date hereof. B2Gold does not assume any
obligation to update forward-looking statements if circumstances or
management's beliefs, expectations or opinions should change other
than as required by applicable law. There can be no assurance that
forward-looking statements will prove to be accurate, and actual
results, performance or achievements could differ materially from
those expressed in, or implied by, these forward-looking
statements. Accordingly, no assurance can be given that any events
anticipated by the forward-looking statements will transpire or
occur, or if any of them do, what benefits or liabilities B2Gold
will derive therefrom. For the reasons set forth above, undue
reliance should not be placed on forward-looking statements.
For more information on B2Gold please visit the Company website at www.b2gold.com or contact:
Michael McDonald
VP, Investor Relations & Corporate Development
+1 604-681-8371
investor@b2gold.com
Cherry DeGeer
Director, Corporate Communications
+1 604-681-8371
investor@b2gold.com
B2Gold (AMEX:BTG)
Historical Stock Chart
From Jan 2025 to Feb 2025
B2Gold (AMEX:BTG)
Historical Stock Chart
From Feb 2024 to Feb 2025