Bitdeer Technologies Group (NASDAQ: BTDR)
(“
Bitdeer” or the “
Company”), a
world-leading technology company for blockchain and
high-performance computing, today announced its unaudited mining
and operations updates for October 2024.
Operational Update
- Self-mined Bitcoin: 174 Bitcoins.
- Mining Rig Manufacturing and R&D:
- SEALMINER A1:
- Mass production in progress. Approximately 3.7 EH/s of machines
to be manufactured and delivered by January 2025, of which
approximately 0.4 EH/s of machines are already manufactured and on
the way to data centers, and 1.7 EH/s of machines are in
production.
- On track to be delivered to Texas and Norway sites and fully
energized by Q1 2025.
- SEALMINER A2:
- Final testing of air and hydro-cooling mining machines achieved
226 TH/s and 446 TH/s, respectively and 16.5 J/TH efficiency.
- Commenced mass production. Secured capacity as of this report
date will generate approximately 18 EH/s hashrate, expected to be
used for sale to external customers and self-mining.
- SEAL03:
- Successfully taped-out SEAL03 chip in October with an expected
chip efficiency of 10 J/TH.
- HPC/AI:
- TLM Group successfully completed its feasibility assessment of
Bitdeer’s U.S. sites, reporting positive results regarding
suitability for Tier 3 HPC/AI datacenters, due to the availability
of land, power, fiber and water resources.
- Discussions ongoing with multiple development partners and
potential end users for these sites.
- Bitdeer AI cloud services powered by NVIDIA DGX SuperPod with
H100 systems achieved approximately 90% average utilization.
- Hosting:
- Client-hosted mining machines increased by 3,000 units,
contributing approximately 0.8 EH/s.
- Mining Datacenters:
- Construction of the Tydal, Norway, 40 MW phase 1 expansion
remains on track to be energized in December 2024.
- Rockdale, Texas, USA, 100MW hydro-cooling conversion expected
to be delayed one month from original schedule due to the US dock
workers strike in early October. Expected phased completion during
Q1 2025.
- Jigmeling, Bhutan, 500 MW construction remains on track with
the primary substation expected to be completed by Q1 2025.
Management Commentary
“In October, we made meaningful progress on our ASIC technology
roadmap,” stated Linghui Kong, Chief Business Officer of Bitdeer.
“We officially commenced mass production of our SEALMINER A1 and A2
machines. SEALMINER A1 production plan is now expected to produce
approximately 3.7 EH/s of units and delivery has already begun with
expected phased energization between December and the end of Q1
2025. SEALMINER A2 first production run with secured capacity as of
October 2024 is expected to produce approximately 18 EH/s and will
be used for both self-mining and selling to external customers.
Notably, the SEALMINER A2 will be a significant milestone for
Bitdeer as we begin offering these machines to customers starting
in 2025. We will continue to provide this hashrate progress as a
commitment to maintaining transparency for all stakeholders,
including shareholders, suppliers, and especially clients, which
will need clear guidance to make rational decisions. In addition,
we began initial tape out of our 3rd generation chip with an
industry-leading target efficiency of 10 J/TH and anticipate
initial sample wafers in Q2 2025.”
Matt continued, “Looking forward, we remain fully committed to
executing a successful market entry into the multi-billion dollar
ASIC market in 2025. We are already engaged in discussion with a
number of potential customers, and early demand is promising,
indicating strong interest in our cutting-edge technology and the
industry’s desire for technology and supply chain diversification.
We are excited to meet this demand and begin driving a
differentiated and diversified revenue stream for our
shareholders.”
Production and Operations Summary
Metrics |
Oct 2024 |
Sep 2024 |
Oct 2023 |
Total hash rate under management1
(EH/s) |
18.0 |
17.1 |
21.2 |
- Proprietary hash rate |
8.7 |
8.6 |
8.7 |
• Self-mining |
8.4 |
8.1 |
7.2 |
• Cloud Hash Rate |
0.3 |
0.5 |
1.5 |
- Hosting |
9.3 |
8.5 |
12.5 |
Mining machines under management |
168,000 |
165,000 |
221,000 |
- Self-owned2 |
87,000 |
87,000 |
92,000 |
- Hosted |
81,000 |
78,000 |
129,000 |
Bitcoin mined (self-mining only) |
174 |
164 |
462 |
1 Total hash rate under management as of
October 31, 2024 across the Company’s three primary business lines:
Self-mining, Cloud Hash Rate, and Hosting.
- Self-mining refers to cryptocurrency mining
for the Company’s own account, which allows it to directly capture
the high appreciation potential of cryptocurrency.
- Cloud Hash Rate offers hash rate subscription
plans and shares mining income with customers under certain
arrangements. The Cloud Hash Rate stated above reflects the
contracted hash rate with customers at month-end. However,
throughout the month, the Cloud Hash Rate may transition to
Self-mining hash rate if customers opt to not make their monthly
electricity payments for various reasons.
- Hosting encompasses a one-stop mining machine
hosting solution including deployment, maintenance, and management
services for efficient cryptocurrency mining.
2 Self-owned mining machines are for the
Company’s self-mining business and Cloud Hash Rate business.
Infrastructure Construction Update
Rockdale, Texas - 100 MW Hydro-cooling
conversion underway:
- Demolition work completed.
- Cooling system will be delivered and installed in phases from
Q4 2025 to Q1 2025.
- Due to supply chain delays from the US dock workers strike in
early October, the expected phased energization timeline is
expected to occur one month later, now between January and March
2025.
Tydal, Norway - 175 MW site expansion is
progressing well, with several key milestones achieved:
- Buildings and groundwork completed, along with the construction
of the transformer foundation and housing.
- Orders for transformer and electrical equipment have been
placed, with delivery and installation currently in progress.
Additionally, the procurement and delivery of containers and
hydro-cooling systems are underway, and drainage systems
construction is ongoing.
- Construction of the substation completed.
- Tydal, Norway Expansion Phase 1 of 40 MW remains on track to be
energized by Q4 2024.
Massillon, Ohio - 221 MW site is also making
progress:
- Substation conceptual design is completed and long lead-time
electrical equipment for the substation have been ordered.
- Engineering, Procurement, and Construction (EPC) contractor has
been selected for the substation construction.
- Civil work is ongoing, with the majority expected to be
completed by the end of Q4 2024 or Q1 2025.
- Building design is completed, and construction is anticipated
to begin in Q4 2024, earlier than expected.
- Estimated energization timeline remains on track for
mid-to-late 2025.
Jigmeling, Bhutan - 500MW site is progressing
well, with the following key milestones achieved:
- Civil work is anticipated to be completed by the end of
September 2024. Construction of transformer and container
foundations is in progress and will be completed in phases, with
the last phase expected by the end of February 2025.
- 132kv/140MW and 220kv/360MW substation designs are completed
with construction anticipated to be ready by the end of Q1
2025.
- Orders for the procurement of transformers and electrical
equipment have been placed, with delivery and installation to be
completed in phases over the next two quarters.
- Procurement and delivery of containers and hydro-cooling
systems are in progress, with completion in phases by the end of Q1
2025.
Power Infrastructure Summary
Site / Location |
Capacity (MW) |
Status |
Timing3 |
Electrical capacity |
|
|
|
- Rockdale, Texas |
563 |
Online |
Completed |
- Knoxville, Tennessee |
86 |
Online |
Completed |
- Wenatchee, Washington |
13 |
Online |
Completed |
- Molde, Norway |
84 |
Online |
Completed |
- Tydal, Norway |
50 |
Online |
Completed |
- Gedu, Bhutan |
100 |
Online |
Completed |
Total electrical capacity |
8954 |
|
|
Pipeline capacity |
|
|
|
- Tydal, Norway Phase 1 |
40 |
In progress |
Q4 2024 |
- Tydal, Norway Phase 2 |
135 |
In progress |
Mid 2025 |
- Massillon, Ohio |
221 |
In progress |
Mid-to-late 2025 |
- Clarington, Ohio Phase 1 |
266 |
In progress |
Q3 2025 |
- Clarington, Ohio Phase 2 |
304 |
Pending approval |
Estimate 2026 |
- Jigmeling, Bhutan |
500 |
In progress |
Mid-to-late 2025 |
- Rockdale, Texas |
179 |
In planning |
Estimate 2026 |
Total pipeline capacity |
1,645 |
|
|
Total global electrical capacity |
2,540 |
|
|
3 Indicative timing. All timing references are to calendar
quarters and years.4 Figures may not add due to rounding.
Upcoming Conferences and Events
- November 7: LetsTalkAlts Conference in San Diego,
California
- November 13-14: Cantor Crypto, Digital Assets & AI
Infrastructure Conference in Miami, Florida
- November 18: Q3 2024 Earnings Conference Call
- November 20-21: North American Blockchain Summit in Dallas,
Texas
- December 4: B. Riley Crypto & Energy Infrastructure
Conference in New York City
About Bitdeer Technologies Group
Bitdeer is a world-leading technology company
for blockchain and high-performance computing. Bitdeer is committed
to providing comprehensive computing solutions for its customers.
The Company handles complex processes involved in computing such as
equipment procurement, transport logistics, datacenter design and
construction, equipment management, and daily operations. The
Company also offers advanced cloud capabilities to customers with
high demand for artificial intelligence. Headquartered in
Singapore, Bitdeer has deployed datacenters in the United States,
Norway, and Bhutan. To learn more,
visit https://ir.bitdeer.com/ or follow Bitdeer on X @
BitdeerOfficial and LinkedIn @ Bitdeer Group.
Investors and others should note that Bitdeer
may announce material information using its website and/or on its
accounts on social media platforms, including X, formerly known as
Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages
investors and others to review the information it posts on the
social media and other communication channels listed on its
website.
Forward-Looking Statements
Statements in this press release about future expectations,
plans, and prospects, as well as any other statements regarding
matters that are not historical facts, may constitute
“forward-looking statements” within the meaning of The Private
Securities Litigation Reform Act of 1995. The words “anticipate,”
“look forward to,” “believe,” “continue,” “could,” “estimate,”
“expect,” “intend,” “may,” “plan,” “potential,” “predict,”
“project,” “should,” “target,” “will,” “would” and similar
expressions are intended to identify forward-looking statements,
although not all forward-looking statements contain these
identifying words. Actual results may differ materially from those
indicated by such forward-looking statements as a result of various
important factors, including factors discussed in the section
entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as
well as discussions of potential risks, uncertainties, and other
important factors in Bitdeer’s subsequent filings with
the U.S. Securities and Exchange Commission. Any
forward-looking statements contained in this press release speak
only as of the date hereof. Bitdeer specifically disclaims any
obligation to update any forward-looking statement, whether due to
new information, future events, or otherwise. Readers should not
rely upon the information on this page as current or accurate after
its publication date.
For investor and media inquiries, please
contact:
Investor RelationsOrange GroupYujia
ZhaibitdeerIR@orangegroupadvisors.com
Public RelationsBlocksBridge ConsultingNishant
Sharmabitdeer@blocksbridge.com
Bitdeer Technologies (NASDAQ:BTDR)
Historical Stock Chart
From Nov 2024 to Dec 2024
Bitdeer Technologies (NASDAQ:BTDR)
Historical Stock Chart
From Dec 2023 to Dec 2024