Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument" or
the "Company") is pleased to report that flotation construction
work progress at the Selinsing Gold Mine in Malaysia has reached
85% completion in line with the budget. The commissioning targets
to complete in November 2022, thereafter three months ramp up
period for commercial production in January 2023.
President and CEO Cathy Zhai commented, “We are
pleased to see the team has overcome the difficult period with the
Shanghai COVID-19 pandemic lockdown and the global logistics
blockage. The installation is progressing rapidly with close
monitoring. In the meantime, we have been in communications with
potential buyers to review major terms and continue to optimize
saleable gold concentrates for a better economic outcome.”
Construction Highlights
- Overall project is 85% complete to
date in line with the budget.
- Equipment continues to arrive at
the Selinsing site; the concentrate filter press departed port on
September 24, later than expected, and plans to arrive in early
November 2022.
- Pre-commissioning (dry & wet)
will commence in October; full commissioning targets late
November/or early December 2022.
- First concentrate production
planned to commence late November 2022, ramping up to full
production anticipated in January 2023.
Flotation Design &
Engineering
To date all work related to flotation detail
design and engineering have been completed, pending the submission
of application for TNB power supply upgrade from 3.8 MW to 4.0
MW.
Procurement
Overall procurement is 89% completed, pending
primarily the delivery of the filter press to the site in November
2022.
Most equipment has been delivered to the
Selinsing site, including but not limited to the flotation cells
from Beijing assembled and delivered by BGRIMM Machinery and
Technology Co Ltd (Figure 1); the concentrate and the water
recovery thickeners supplied by Metso Outotec; flotation blowers,
compressor and compressed air dryer delivered by Atlas Copco.
First-fill flotation reagent have been purchased
awaiting delivery. Transportation costs have increased due to
COVID-19 pandemic related global supply chain issues, to be offset
by mine development costs. Partial reagent consumables have been
delivered and are stored inside the reagent warehouse building.
Figure 1: View of Flotation Plant Circuit
Construction
Figure 1 is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/3a06e4ae-caf3-4456-a4f5-472cc9cb5517
Construction
Construction work consists of foundation and
civil work, steel structure work, plant equipment fabrication and
installation work, piping work, electrical cabling work,
installation of plant automation system, installation of electrical
system and plant infrastructure including reagent warehouse,
concentrate store yard and drainage system at the plant area.
Flotation plant construction
has achieved 85% completion to date. Earthworks, foundations,
piping works connecting reagent tanks and air supply system to
flotation cells circuit have been completed. Civil works and
structural work installation are 100% completed. Mechanical
installation is 96% complete with all reagent tanks, flotation
cells and thickeners installed. Pipe racks have been erected from
the reagent building to the flotation circuit, from the concentrate
thickener to concentrate filter building and from the flotation
circuit to the water recovery thickener. Electrical installation is
81% complete, and the control room is 100% complete. Pipelines have
been laid and connected to pumps. Electrical installation work of
cable trays and cable pulling is now 60%
completed.
The flotation plant is equipped with a plant
automation system, which consists of SCADA system and process
instrumentation monitoring devices. All the pumps, flotation cell
circuit, concentrate filter, concentrate thickeners, blowers and
air compressor are controlled using a program logic control system
(PLC Siemens & Allen Bradley). A provision backup generator of
750kVA as an emergency power supply in case of any power failures
will keep essential services running. Enertech Sdn Bhd (Siemens
distributor in Malaysia) supplied the hardware and software for the
control system. The hardware for the control system panel (PLC) was
delivered to site and installed in the prefabricated power
substation (E-House), together with the motor control centre panel
(MCC).
Other infrastructure includes:
the reagent warehouse, the air services building, the concentrate
filter building, and other facilities. The reagent storage
warehouse and the air service building are constructed. Dosing pump
has been installed inside the reagent building with foundation and
steel structure work completed. Plate work of bag breakers, reagent
mixing tanks with agitator equipment are installed. The compressor
and the flotation blowers have been installed in the air service
building. Foundation and structure work for the concentrate filter
building (Figure 2) is completed, and most of the roof and cladding
have been done, awaiting installation of the filter press.
Figure 2: Concentrate Filter
Building
Figure 2 is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/bffdbda0-fef3-459d-b83f-93a02469f1e2
Mine Development
Pre-stripping and sulphide ore stockpile mining
were started at Buffalo Reef in July 2022 in preparation for: the
completion of the flotation plant, the start of commissioning and
the ramp up of production. The tailings storage facility (“TSF”)
construction has been completed for current year tailing storage
requirements. The river diversion at Buffalo Reef has been
completed.
Commissioning
Commissioning work is expected to start in
October and completed in November 2022. Commissioning scope of work
will be divided into dry, wet and ore commissioning. Upon
completion of the commissioning work production will be ramped
up.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE:D7Q1)
is an established Canadian gold producer that 100% owns and
operates the Selinsing Gold Mine in Malaysia and the Murchison Gold
Project in the Murchison area of Western Australia. It has 20%
interest in Tuckanarra Gold Project jointly owned with Odyssey Gold
Ltd in the same region. The Company employs approximately 200
people in both regions and is committed to the highest standards of
environmental management, social responsibility, and health and
safety for its employees and neighboring communities.
Cathy Zhai, President and CEOMonument Mining
LimitedSuite 1580 -1100 Melville StreetVancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web
site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T:
+1-604-638-1661 x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release."
Forward-Looking Statement
This news release includes statements containing
forward-looking information about Monument, its business and future
plans ("forward-looking statements"). Forward-looking statements
are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the
Company's plans with respect to its mineral projects and the timing
and results of proposed programs and events referred to in this
news release. Generally, forward-looking information can be
identified by the use of forward-looking terminology such as
"plans", "expects" or "does not expect", "is expected", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates" or
"does not anticipate", or "believes", or variations of such words
and phrases or state that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved". The forward-looking statements in this news release are
subject to various risks, uncertainties and other factors that
could cause actual results or achievements to differ materially
from those expressed or implied by the forward-looking statements.
These risks and certain other factors include, without limitation:
risks related to general business, economic, competitive,
geopolitical and social uncertainties; uncertainties regarding the
results of current exploration activities; uncertainties in the
progress and timing of development activities; foreign operations
risks; other risks inherent in the mining industry and other risks
described in the management discussion and analysis of the Company
and the technical reports on the Company's projects, all of which
are available under the profile of the Company on SEDAR at
www.sedar.com. Material factors and assumptions used to develop
forward-looking statements in this news release include:
expectations regarding the estimated cash cost per ounce of gold
production and the estimated cash flows which may be generated from
the operations, general economic factors and other factors that may
be beyond the control of Monument; assumptions and expectations
regarding the results of exploration on the Company's projects;
assumptions regarding the future price of gold of other minerals;
the timing and amount of estimated future production; the expected
timing and results of development and exploration activities; costs
of future activities; capital and operating expenditures; success
of exploration activities; mining or processing issues; exchange
rates; and all of the factors and assumptions described in the
management discussion and analysis of the Company and the technical
reports on the Company's projects, all of which are available under
the profile of the Company on SEDAR at www.sedar.com. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking statements, there may be other factors that cause
results not to be as anticipated, estimated or intended. There can
be no assurance that such statements will prove to be accurate, as
actual results and future events could differ materially from those
anticipated in such statements. Accordingly, readers should not
place undue reliance on forward-looking statements. The Company
does not undertake to update any forward-looking statements, except
in accordance with applicable securities laws.
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Nov 2024 to Dec 2024
Monument Mining (TSXV:MMY)
Historical Stock Chart
From Dec 2023 to Dec 2024